A BlackForge Ventures company
BlackForge Data Centers

Water, gas & fiber

Data Center Water Requirements and Cooling Choices

A data center’s water needs depend mostly on how it rejects heat: evaporative cooling consumes significant water, while air-cooled and closed-loop systems use very little on site but more electricity.12 U.S. data centers consumed roughly 17 billion gallons of water directly in 2023, and Lawrence Berkeley National Laboratory’s scenarios show that figure rising sharply by 2028.3 Site selection therefore asks two questions: how much water the chosen cooling design needs on the peak day, and whether the site can supply that water and dispose of the wastewater reliably for decades.

Last reviewed · 11 min read · BlackForge Data Centers

Key takeaways

  • Cooling design drives water use far more than building size alone. In a cooling tower, evaporation is the main way heat leaves, and that water is consumed.1
  • Water and power trade off: low-water designs usually use more electricity, especially on hot days, though warmer liquid cooling narrows the gap.2
  • Supply is only half the question. Cooling tower blowdown becomes wastewater, and a large sewer discharger is likely to be regulated as a significant industrial user.4
  • Water law differs sharply by region: western states follow prior appropriation, where seniority decides who gets water in a shortage, while most eastern states follow riparian principles.5
  • Disclosure is spreading. As of 2026, Utah and Virginia have enacted data center water reporting laws, and more states have bills pending.67
  • Reclaimed water and low-water designs can ease local concerns. Ashburn, Virginia data centers have cooled with reclaimed water for more than a decade.9

01Where does water go in a data center?

Most data center water use is for heat rejection. Servers turn nearly all the electricity they use into heat, and that heat has to leave the building. Evaporating water is a very efficient way to move heat, which is why evaporative systems are common. In a cooling tower, the Department of Energy’s Federal Energy Management Program describes evaporation as the tower’s primary function and the way heat is transferred to the environment.1 The water that evaporates is consumed and does not return to the source.

Other uses are smaller but still need planning:

  • Cooling tower blowdown: water drained to keep dissolved minerals from building up, which becomes wastewater.
  • Drift and leaks: small amounts carried out of the tower as droplets or lost from basins and overflows.
  • Humidification and adiabatic assist on air handlers or dry coolers during hot periods.
  • Domestic water for staff, plus landscaping where it is used. Even a design that evaporates no cooling water still uses water for restrooms and kitchens.
  • Fire protection: sprinkler supply and, often, on-site storage tanks and pumps sized to the fire code and the local fire authority.
  • Make-up water for closed loops, which is small once the loop is filled.

There is also an indirect water footprint in the power supply, since many power plants use water for cooling. The 2024 LBNL report puts indirect water use by U.S. data centers at roughly 211 billion gallons (about 800 billion liters) in 2023, about twelve times the direct figure.3 That does not show up on the site’s water bill, but it is part of the full picture, and it is why a dry-cooled campus is not automatically a low-water campus.

Fig. 1Data center water by the numbers

Direct U.S. data center use, 2023
~17 billion gal
Indirect use at power plants, 2023
~211 billion gal
Data center share of Loudoun potable use
9%
Avoided per site yearly (Microsoft est.)
125M+ liters
National figures are LBNL estimates for 2023.3 The Loudoun share is for an average day.10 Microsoft’s figure is its own estimate per data center, not a measured result.2

02Cooling choices and their water use

The cooling design is usually set by the developer or end user, but the site influences it. A site with abundant water and a mild climate supports different choices than a hot, dry site with tight water supply. Our guide to closed-loop and waterless cooling goes deeper on the low-water options.

Common cooling approaches compared
ApproachHow heat leavesOn-site water useEnergy tradeoff
Water-cooled chillers with cooling towersEvaporation in cooling towersHigh; steady and highest in hot weatherEfficient, with lower peak electrical demand
Direct or indirect evaporative air coolingEvaporation cools outside or recirculated airModerate; seasonal, peaking on hot daysVery efficient, especially in dry climates
Air-cooled chillers or dry coolersFans move heat to outside air with no evaporationMinimalMore electricity and larger equipment yards, especially in hot climates
Hybrid or adiabatic dry coolersDry most of the year, water spray on the hottest daysLow; concentrated in peak periodsMiddle ground on energy and water
Closed-loop liquid cooling (direct-to-chip or immersion)Liquid carries heat to chillers or one of the systems aboveNear zero for cooling if the final heat rejection is dryWarm liquid allows more economizer hours and narrows the penalty

The tradeoff is real. Choosing a dry design to save water raises energy use and can raise the peak power the site has to request from the utility. Microsoft’s zero-water design, announced in 2024, shows how the industry is narrowing that gap: chip-level cooling in a sealed loop that is filled once during construction, with warmer coolant temperatures that let high-efficiency economizing chillers help offset the added power.2 Climate still decides how big the penalty is, which our guide to climate and cooling in site selection covers.

Fig. 2Climate and water supply shape the cooling choice

Cool ← Climate → Hot

Dry or hybrid cooling

Saves water but raises peak power; plan for the hottest hours.

Evaporative works well

Lowest energy use; size supply and sewer for the peak day.

Dry coolers, economizers

Many free-cooling hours; little water beyond domestic use.

Most flexible

Most designs work; choose on energy cost and owner policy.

Tight ← Local water supply → Ample

A way to frame the decision, not a rule. Owners also weigh rack density, power cost and their own water commitments.

03Measuring water use: WUE and its limits

Water Usage Effectiveness (WUE), defined by The Green Grid as part of the same family of metrics as PUE, divides a facility’s annual site water use in liters by the energy used by its IT equipment in kilowatt-hours; lower is better, and a source-based version adds the water consumed off site to generate the facility’s electricity.11 Published values give a sense of scale: Facebook reported 0.22 liters per kWh for one quarter at its Prineville, Oregon campus, and Microsoft reported a fleet average of 0.30 liters per kWh in fiscal 2024, down 39% from 0.49 in 2021.122

WUE is useful for comparing designs, but it is an annual average, and operators do not always count the same water, so read the definition behind any reported figure. For site selection, the more important figure is often peak daily demand on the hottest days, because that is what the water supplier and the wastewater system have to handle. Ask the design team for both the annual volume and the peak day, and see our WUE guide for how to read reported figures.

WUE and PUE (Power Usage Effectiveness) usually pull in opposite directions. A design that improves one tends to worsen the other, so look at them together.

04Water sources and what to verify

Municipal or regional water utility

The simplest source when capacity exists. Confirm treatment and supply capacity, the size and pressure of the nearest main, any required extensions, connection fees, rate structure and drought curtailment rules. A written capacity or will-serve statement from the utility is a useful early step. Our guide to municipal water and sewer capacity covers that conversation.

Groundwater

On-site wells can work where aquifers are productive, but they need hydrogeologic testing and, in most states, permits. Every western state recognizes prior appropriation, under which the priority date of a user’s first diversion decides who receives water in a shortage, rights do not depend on owning land along the stream, and rights can be lost through nonuse. Riparian law, more common in the East, ties water to land along a waterbody and gives each owner a right to reasonable use; several wetter western states blend elements of both.5 Many states treat groundwater under separate rules, and some areas restrict new large withdrawals, so read our guide to water rights and groundwater and confirm with a water attorney.

Reclaimed water

Treated wastewater from a municipal plant can supply cooling towers and reduces demand on drinking water supplies. Loudoun Water supplies reclaimed water to data centers in Ashburn, Virginia, and one Ashburn campus hooked up to the reclaimed loop in 2013 with a design for three independent sources (an on-site well, reclaimed water and potable utility water), each able to carry the full cooling load.139 Reclaimed water requires a pipeline from the treatment plant, an agreement with the operator and treatment suited to its quality. Proximity to a wastewater plant is worth noting in screening; see reclaimed water for cooling.

Surface water

Rivers and lakes can supply large volumes, but withdrawals usually need state permits or water rights, and building an intake in a river or lake can require federal and state permits for work in waters.

05Wastewater and blowdown

Evaporative cooling concentrates the minerals in the water, and the system has to bleed some of it off as blowdown. The ratio of dissolved solids in the circulating water to those in the make-up water is called cycles of concentration, and FEMP identifies blowdown control as the biggest water-saving lever in tower operation.1 EPA’s WaterSense guidance notes that many systems run at two to four cycles, that six or more may be possible with good water quality and treatment, and that going from three to six cycles cuts make-up water by about 20% and blowdown by about half.14

Fig. 3Make-up water vs. cycles of concentration

Illustrative
  • 2 cycles200
  • 3 cycles150
  • 4 cycles133
  • 6 cycles120
  • 10 cycles111

gallons per 100 gallons evaporated

Illustrative calculation, ignoring drift: make-up equals evaporation times C/(C-1). Going from three to six cycles cuts make-up by 20%, matching EPA’s figure; gains flatten beyond that.14

That wastewater needs a destination. Discharging to the municipal sewer requires capacity at the treatment plant and usually an industrial user permit under the National Pretreatment Program, which sets limits on what the water can contain.4 A user discharging 25,000 gallons a day or more of process wastewater, or 5% or more of the plant’s capacity, generally qualifies as a significant industrial user with closer oversight.4 A direct discharge to a stream needs a National Pollutant Discharge Elimination System (NPDES) permit under the Clean Water Act. Our guide to wastewater and cooling water discharge covers both paths.

Some sites treat and reuse blowdown on site or move toward zero liquid discharge, which reduces the burden on local systems but adds equipment and cost. Stormwater is handled separately, through site grading, detention and stormwater permits.

06Water as a community and disclosure issue

Water use is one of the most common local concerns about data centers, particularly in areas with drought history or stressed aquifers. Even where the share is modest, it is visible: Loudoun County reports that data centers account for about 9% of potable water use on an average day, and since March 2025 its special exception process has given officials and the public more visibility into the water impacts of new proposals.10

States are also moving from voluntary disclosure toward reporting rules. Examples as of October 2026:

  • Utah enacted water reporting for new data centers of at least 10,000 square feet that use 75 acre-feet or more a year, applying to facilities established on or after July 1, 2026.6
  • Virginia’s HB 496, enacted in 2026, requires local water suppliers to report the water they deliver to data centers, with the figures posted in aggregated form on the Department of Environmental Quality’s website.7
  • In Ohio, House Bill 784, introduced in March 2026, would require data centers to report monthly and annual water use and bar water figures from nondisclosure agreements with local governments.15
  • A Caltech tracker lists further reporting proposals in states including Colorado, Washington, Indiana, Georgia and Illinois.8

Projects that use low-water cooling, reclaimed water or a clear drought operating plan tend to have an easier conversation. Our guides to water stress and drought risk and community engagement cover how to address these concerns early and accurately.

07How to screen a site for water

When we screen a site, water review starts with the cooling assumption, because a dry-cooled campus and an evaporative campus have very different needs. Then:

  • Identify the water provider and request capacity, main size and pressure at the site.
  • Check groundwater conditions, state permitting and any local restrictions on new wells, and whether the state follows prior appropriation, riparian rules or a hybrid.
  • Locate the nearest wastewater treatment plant and ask about capacity for blowdown, pretreatment permit limits and reclaimed water availability.
  • Ask the design team what cycles of concentration the make-up water quality will support, since that sets the blowdown volume.
  • Review drought history and the provider’s curtailment rules.
  • Confirm fire flow and whether on-site storage will be needed.
  • Check state and local water reporting rules that will apply once the site operates.
  • Note the local attitude toward water use, from public records and prior projects.

Water is one line in the full site selection checklist, and it is rarely evaluated in isolation from power and climate. If you want a second opinion on a specific parcel, you can get a site reviewed.

CalculatorCooling water use →CalculatorFiber latency & distance →

Common questions

How much water does a data center use?

It varies too widely for one number. A data center using evaporative cooling towers can consume large volumes, especially in hot weather, while one using air-cooled chillers or closed-loop systems may use little more than an office building. Nationally, U.S. data centers used roughly 17 billion gallons directly in 2023, according to LBNL’s 2024 report.3 Ask for both the annual volume and the peak-day demand.

Do all data centers need water for cooling?

No. Air-cooled chillers, dry coolers and closed-loop liquid systems can reject heat without evaporating water, though they generally use more electricity, particularly on hot days. Many designs use water only during peak conditions. Every data center still needs water for domestic use and fire protection, so a site needs at least a basic water service even if the cooling is dry.

What is WUE in a data center?

WUE, or Water Usage Effectiveness, is a metric from The Green Grid. It equals the facility’s annual site water use in liters divided by the energy used by IT equipment in kilowatt-hours. Lower values mean less water per unit of computing; Microsoft, for example, reported 0.30 liters per kWh across its fleet.2 Because it is an annual average, WUE does not show the peak-day demand that water and sewer systems must handle.

Can a data center use recycled water?

Yes. Many data centers use reclaimed water, which is treated municipal wastewater, for cooling towers, and data centers in Ashburn, Virginia have done so for more than a decade.9 It reduces demand on drinking water supplies and can ease community concerns. It requires a pipeline from a nearby treatment plant, an agreement with the operator and on-site treatment matched to the water quality. Availability depends on the local utility and state reuse rules.

Do data centers have to report their water use?

It depends on the state. As of October 2026, for example, Utah requires reporting from new data centers above set size and water thresholds, and Virginia requires water suppliers to report deliveries to data centers, published in aggregate.67 Other states, including Ohio, have bills pending, so check current law where the site sits.15

Notes

  1. 1.U.S. Department of Energy, Federal Energy Management Program, “Best Management Practice #10: Cooling Tower Management,” n.d. energy.gov
  2. 2.Microsoft, “Sustainable by design: Next-generation datacenters consume zero water for cooling,” 2024. microsoft.com
  3. 3.Lawrence Berkeley National Laboratory, “2024 United States Data Center Energy Usage Report,” 2024. eta-publications.lbl.gov
  4. 4.American Institute of Chemical Engineers, ChEnected, “Water: Industrial Discharge Permits,” 2011. chenected.aiche.org
  5. 5.Colorado State Archives, “Early Water Law,” n.d. archives.colorado.gov
  6. 6.The Water Report, “New Law Mandates Utah Data Center Water Reporting,” 2026. thewaterreport.com
  7. 7.WMRA, “New Virginia law requires data center water usage be made public,” 2026. wmra.org
  8. 8.Caltech, Linde Center for Science, Society, and Policy, “Annotated state legislation on data center reporting,” 2026. lcssp.caltech.edu
  9. 9.Data Center Knowledge, “RagingWire Ashburn Hooking Up to Reclaimed Water Loop,” 2013. datacenterknowledge.com
  10. 10.Loudoun County, Virginia, “Data Centers: Water Considerations,” n.d. loudoun.gov
  11. 11.The Green Grid, “WP#35 - Water Usage Effectiveness (WUE): A Green Grid Data Center Sustainability Metric,” 2011. thegreengrid.org
  12. 12.DatacenterDynamics, “Facebook first to report WUE figures for Prineville data center,” n.d. datacenterdynamics.com
  13. 13.Data Center Knowledge, “In Ashburn, Recycled Water to Keep Data Centers Cool,” n.d. datacenterknowledge.com
  14. 14.U.S. Environmental Protection Agency, WaterSense, “WaterSense at Work, page 199,” n.d. 19january2017snapshot.epa.gov
  15. 15.Ohio House of Representatives, “Reps. Cockley and Lett Introduce Legislation Regarding Data Center Water Consumption Nondisclosure Agreements,” 2026. ohiohouse.gov

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Terms in this guide

Related guides

More in Water, gas & fiber

Guide 1 of 18 in Water, gas & fiber · all 242 guides · glossary · calculators