Key takeaways
- U.S. geothermal plants are mostly in the western states and Hawaii, where heat is close to the surface; California generates the most.1
- DOE’s 2024 Liftoff report found next-generation geothermal could reach about 90 GW by 2050, roughly a twentyfold increase.5
- Nevada regulators approved the Clean Transition Tariff in 2025, letting NV Energy buy 115 MW from Fervo’s Corsac Station and supply it to Google.42
- Fervo’s Cape Station delivered its first 33 MW in September 2026; Phase I is about 100 MW and Phase II adds 400 MW, expected in 2028.3
- Geothermal kept full federal tax credits for projects starting construction by 2033, while wind and solar credits were cut back.67
- Site questions for geothermal are about federal land, drilling permits, induced seismicity, water and transmission, not the data center parcel alone.89
01Why data centers want geothermal
Data centers run at high load factor, so a buyer trying to match consumption with clean energy hour by hour needs supply that does not stop at night or in calm weather. Geothermal plants produce steady output from underground heat, which is why it is often grouped with nuclear as “clean firm” power. Google described its Nevada tariff as a way to buy 24/7 clean energy from new resources, and analysts saw it as firm, dispatchable renewable power that avoids overbuilding solar and adding gas.2
The constraint is scale and geography. Most U.S. geothermal plants are in the western states and Hawaii, where geothermal resources lie close to the surface, and California generates the most electricity from it; The Geysers in Northern California is the largest known dry steam field in the world.1 DOE’s 2024 Pathways to Commercial Liftoff report argues that next-generation techniques could expand U.S. geothermal to about 90 GW by 2050, roughly twenty times today’s fleet.5
Fig. 1Geothermal and data centers in numbers
- Next-gen geothermal potential by 2050
- ~90 GW
- Geothermal for Google under Nevada’s tariff
- 115 MW
- First Cape Station block online, Sept. 2026
- 33 MW
- Cape Station planned by 2028
- ~500 MW
For site selection, geothermal matters in two ways: as a clean firm resource a utility can add for a data center customer, and occasionally as a reason to locate a campus near a resource. This guide covers both, with more weight on the first, which is how nearly all current deals work.
02Conventional, enhanced and closed-loop geothermal
Conventional hydrothermal plants need hot water or steam in naturally permeable rock, which limits them to specific fields. DOE’s Liftoff report defines next-generation geothermal as enhanced geothermal systems (EGS) or closed-loop systems, which borrow drilling methods from oil and gas to create or bypass reservoirs in hot rock that conventional plants cannot use.5 The report put the investment needed for initial liftoff of 2–5 GW at $20–25 billion through 2030.5
Fig. 2Three ways to make geothermal power
Mature
Conventional hydrothermal
- Needs natural hot fluid and permeable rock
- Limited to known fields, mostly in the West
- Example: The Geysers, California
Now commercial
Enhanced geothermal (EGS)
- Creates a reservoir in hot, dry rock
- Uses horizontal drilling and stimulation
- Example: Fervo’s Cape Station, Utah
Early stage
Closed-loop
- Fluid circulates inside sealed well casing
- Does not rely on groundwater to function
- Example: XGS Energy’s New Mexico plan
EGS developers have also benefited from public research. DOE’s FORGE field laboratory near Milford in Beaver County, Utah, was set up to develop and test technologies to create, sustain and monitor EGS reservoirs.12 Fervo’s Cape Station is in the same county.3 The geology that suits EGS is broader than conventional fields, but it still favors the hot, thin crust of the Great Basin and other western regions.
03Cape Station: enhanced geothermal at commercial scale
Fervo’s first Cape Station plant synchronized to the grid on September 24, 2026 and declared commercial operation on September 30, one day before its contractual date, after 23 months of construction.3 It was described as the first greenfield enhanced geothermal development in the world to reach contractual commercial operation.3 The first “GeoBlock” produces 33 MW net; Phase I is about 100 MW across three blocks, with the other two expected by January 1, 2027, and Phase II, a further 400 MW, is under construction for 2028.3
Fig. 3Cape Station capacity milestones
- First GeoBlock (Sept. 2026)33
- Phase I (by Jan. 2027)100
- Phases I and II (2028)500
- Permitted expansionUp to 2 GW
MW
The project reports about 900 MW of contracted offtake and permitting for expansion up to 2 GW.3 For data center planners, the point is less this one site than the proof that EGS can be built on a schedule and financed. It also shows the pace: even fast EGS adds capacity in tens to hundreds of megawatts over several years, against single campus requests of a gigawatt or more. Treat geothermal as one part of a supply portfolio, alongside the options in our renewable procurement guide.
04Google, NV Energy and the Clean Transition Tariff
Google and NV Energy asked Nevada regulators in June 2024 to approve a Clean Transition Tariff (CTT). Under it, NV Energy buys power from Fervo’s 115 MW Corsac Station enhanced geothermal project and supplies it to Google at a set rate, and Google receives credit for the project’s energy and capacity on the bills for its Storey County data centers, offsetting demand charges.2 At filing, Reuters reported the deal would raise geothermal supply for Google’s Nevada operations from 3.5 MW to 115 MW in about six years.13
Fig. 4How Nevada’s Clean Transition Tariff works
- 01
Developer builds
Fervo develops the 115 MW Corsac Station geothermal project.
- 02
Utility buys
NV Energy contracts for the plant’s output.
- 03
Customer pays premium
Google pays the cost above the utility’s “but-for” resource mix.
- 04
Bill credits
Energy and capacity credits offset Google’s demand charges.
- 05
Others held harmless
Contract terms protect other customers if the project underperforms.
The structure matters because it is a utility tariff rather than a private contract. The customer pays a premium equal to the difference between the new clean resource and the “but-for” mix the utility would otherwise have procured, the tariff requires a minimum monthly load of 5 MW, and contract terms are meant to keep other customers from paying any part of the project even if it underperforms or the customer uses less power than expected.2 The Public Utilities Commission of Nevada approved it in 2025.4 Fervo has said the deal prompted outreach from dozens of other hyperscalers and AI companies seeking clean firm power.14
For a developer, a CTT-style tariff can make a utility territory more attractive by giving the large customer a path to new clean firm supply inside a regulated utility. Compare it with sleeved and virtual deals in our guide to power purchase agreements, and with hourly accounting in 24/7 carbon-free energy.
05Other geothermal deals for data centers
Meta has signed two separate 150 MW geothermal agreements. In August 2024 it agreed to buy up to 150 MW of new geothermal power from Sage Geosystems, which uses a geopressured approach, with the first phase targeted for 2027 at a site east of the Rocky Mountains still to be chosen.15 In June 2025 it signed a two-phase, 150 MW agreement with XGS Energy for a closed-loop project to supply the PNM grid and Meta’s New Mexico data centers, with both phases projected to operate by 2030.11 Meta described the XGS deal as an agreement to advance geothermal development, not yet a power purchase contract.11
| Buyer | Developer | Size | Where | Status |
|---|---|---|---|---|
| Fervo (Corsac Station) | 115 MW | Nevada, via NV Energy tariff | Tariff approved 20254 | |
| Meta | Sage Geosystems | Up to 150 MW | East of the Rockies, site not announced | First phase targeted 202715 |
| Meta | XGS Energy | 150 MW, two phases | New Mexico, PNM grid | Targeted by 203011 |
Announced dates are targets. Before treating any of these as available supply for a nearby site, check the utility’s integrated resource plan and interconnection queue, and our New Mexico and Nevada guides.
06Siting geothermal, and data centers near it, in the West
Much of the West’s geothermal resource lies on federal land, so the Bureau of Land Management sets the pace for exploration and leasing. BLM has moved to speed geothermal development, including a categorical exclusion under NEPA for qualifying exploration that removes the need for a full environmental review, while still checking for extraordinary circumstances such as impacts to endangered species or cultural resources.8 See federal land for AI data centers for the land side.
Two technical risks recur in EGS. The first is induced seismicity: DOE issued a protocol for addressing induced seismicity from EGS in 2012 and a complementary best practices document in 2014, and project mitigation plans follow them, starting with screening and community outreach.9 The second is water. A 2026 Utah State University Extension review reports that recent Utah geothermal projects do not use fresh water and that new well designs are expected to cut use of brackish water.10 Ask any developer for its seismic monitoring plan and water source; our seismic risk guide covers the data center side.
Placing a campus right next to a geothermal plant is rarely necessary and often impractical. Good resources tend to be remote, plants are smaller than large campuses, and the plant usually sells into the grid. The more common pattern is a campus in a utility territory that is adding geothermal, linked by transmission. Where a direct connection is considered, the issues in co-locating data centers with power plants and behind-the-meter supply apply.
07Federal tax credits after the 2025 budget law
The 2025 budget law, known as the One Big Beautiful Bill, treated geothermal more favorably than wind and solar. Geothermal Rising reported that it preserves the full Section 48E investment and Section 45Y production tax credits for projects beginning construction by 2033, with a phase-down through 2036.6 By contrast, the law ends investment tax credit eligibility for wind and solar projects placed in service after December 31, 2027.7 Because the credits lower the cost of new geothermal, they also lower the premium a customer pays under a tariff that charges the difference between a new clean resource and the utility’s “but-for” mix.2 Longer credit runway also supports the financing of geothermal projects a utility might add for data center customers; confirm eligibility for a specific project with tax counsel.
08What to ask when geothermal is part of the plan
- 01Is the geothermal supply a utility tariff, a PPA or a direct connection, and who carries the risk if the plant runs late or underperforms?2
- 02What capacity is operating today, and what is only contracted or permitted?3
- 03Does the serving utility offer, or plan to offer, a clean transition style tariff, and what minimum load does it require?2
- 04For any plant near the site, what is the seismic monitoring and mitigation plan?9
- 05What water does the plant use, and does it compete with the data center’s cooling supply?10
- 06Is the project on federal land, and where is it in BLM leasing and review?8
Geothermal rarely decides a site by itself, but it can tip a choice between western utility territories. For a broader regional view, see our Mountain West guide and hydropower and data centers. If you want an outside read on a specific parcel’s power path, you can get a site reviewed.
Common questions
Can geothermal power a whole data center?
In principle yes, since geothermal runs around the clock, but plants are small next to large campuses: Fervo’s first Cape Station block is 33 MW, and the whole site is planned at about 500 MW by 2028.3 Most data centers buy geothermal as part of a grid supply mix.
What is enhanced geothermal?
Enhanced geothermal systems create a reservoir in hot rock that lacks natural permeability, using drilling techniques adapted from oil and gas. DOE counts EGS and closed-loop systems as next-generation geothermal, with potential of about 90 GW by 2050.5
What is the Clean Transition Tariff?
It is a Nevada utility tariff, approved in 2025, under which NV Energy buys 115 MW from Fervo’s Corsac Station and supplies it to Google, which pays a premium over the utility’s normal resource mix and receives bill credits.42
Which states have the best geothermal for data centers?
Conventional geothermal is concentrated in the West and Hawaii, with California generating the most.1 Next-generation projects tied to data center demand are in Nevada and New Mexico, and Utah hosts the first commercial-scale enhanced geothermal plant.211
Notes
- 1.U.S. Energy Information Administration, “Geothermal explained: Where geothermal energy is found,” n.d. eia.gov
- 2.Utility Dive, “NV Energy seeks new tariff to supply Google with 24/7 power from Fervo geothermal plant,” 2024. utilitydive.com
- 3.Energy Global, “Fervo Energy declares commercial operation at Cape Station ahead of schedule,” 2026. energyglobal.com
- 4.ThinkGeoEnergy, “Nevada approves first-of-its-kind geothermal power supply agreement,” 2025. thinkgeoenergy.com
- 5.American Public Power Association, “Geothermal energy capacity could increase 20-fold, DOE says in latest report,” 2024. publicpower.org
- 6.Energy Global, “Geothermal Rising welcomes geothermal incentives in recent bill signed by President Trump,” 2025. energyglobal.com
- 7.Renewable Energy World, “‘One Big Beautiful Bill’ signed into law, reflects de-prioritization of renewable energy,” 2025. renewableenergyworld.com
- 8.U.S. Bureau of Land Management, “BLM takes steps to accelerate geothermal energy development,” n.d. www-26.blm.gov
- 9.U.S. Department of Energy, “Preliminary Induced Seismicity Mitigation Plan (Snake River Plain, ID) R1,” 2016. energy.gov
- 10.Utah State University Extension, “Geothermal Energy in Utah: A Safe Technology With Limited Environmental Impacts,” 2026. extension.usu.edu
- 11.Data Center Dynamics, “Meta, XGS ink 150MW geothermal deal in New Mexico,” 2025. datacenterdynamics.com
- 12.U.S. Department of Energy, “FORGE U of U Enhanced Geothermal System Presentation,” 2017. energy.gov
- 13.Reuters (via AOL), “Google partners with Nevada utility for geothermal to power data centers,” 2024. aol.com
- 14.Latitude Media, “The Clean Transition Tariff won approval in Nevada. What’s next for Fervo?,” 2025. latitudemedia.com
- 15.Data Center Knowledge, “Meta Inks Geothermal Deal for Data Centers,” 2024. datacenterknowledge.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Power & interconnection
- How Much Power Does a Data Center Need?
- Transmission Voltage and Data Centers: 69 kV to 765 kV
- Substation Proximity and Capacity for Data Center Sites
- How the Large-Load Utility Interconnection Process Works
- Power Timelines: Why “When” Matters as Much as “Where”
- ISOs, RTOs and Utility Territories in Data Center Siting
- On-Site Generation and Bridge Power for Data Centers
- What Is Powered Land?
- Load Ramp Schedules: How to Phase Power for a Data Center Campus
- Redundant Utility Feeds and Dual Substations for Data Centers
- Large-Load Tariffs and Electric Service Agreements, Explained
- Behind-the-Meter vs. Front-of-the-Meter Power for Data Centers
- Transmission Upgrades for Data Centers: Who Pays for Them?
- Microgrids and Battery Storage at Data Center Sites
- Co-Locating Data Centers With Power Plants
- Nuclear and Small Modular Reactors: Siting Considerations for Data Centers
- Renewable Energy Procurement and How It Affects Data Center Siting
- What Is a Utility Load Study for a Data Center?
- Firm vs. Interruptible Electric Service for Data Centers
- Flexible Data Center Loads and Demand Response
- Texas Senate Bill 6: What It Means for Data Centers and Large Loads
- PJM Capacity Prices and Data Center Load Growth
- Contribution in Aid of Construction (CIAC) and Line Extensions for Data Centers
- Transformer and Switchgear Lead Times for Data Centers
- Substation Configurations for Data Center Campuses: Ring Bus, Breaker-and-a-Half and Double Bus
- Electricity Rates and Power Costs for Data Center Sites
- Gas Turbines vs. Reciprocating Engines for Data Center On-Site Power
- Fuel Cells for Data Center Power: How They Work and Where They Fit
- NERC Reliability Standards and Large Data Center Loads: Ride-Through, Load Loss and Registration
- From Signed Agreement to Energization: The Data Center Power Timeline
- Surplus Interconnection Service and Retired Power Plant Sites: How Existing Grid Rights Get Reused
