Key takeaways
- DOE picked four sites in July 2025 from an initial pool of 16 identified through an April 2025 request for information.1
- Developers lease, not buy: at Oak Ridge, DOE sought long-term leases funded solely by applicants, who must build, operate and decommission their projects and secure interconnection.5
- Early selections pair data centers with new power: a 1 GW data center with about 2 GW of on-site generation at Savannah River, and 2 GW of new gas generation plus up to 2.6 GW of batteries at Paducah.67
- EO 14318 covers projects needing more than 100 MW of new load or at least $500 million of capital, and revoked the January 2025 order on AI infrastructure on federal sites.28
- The first BLM approval, an 88.5-acre site near Boulder City, Nevada, was put on hold in September 2026 after appeals over its environmental review.39
01Why federal land is now on the table
Federal land for data centers became policy in two steps. On January 14, 2025, Executive Order 14141 directed agencies to make federal sites available for lease to non-federal entities to build frontier AI infrastructure and clean power by the end of 2027, with a central role for the Departments of Defense and Energy.10 On July 23, 2025, Executive Order 14318, “Accelerating Federal Permitting of Data Center Infrastructure,” replaced that approach, revoking EO 14141.8
EO 14318 states that federal land and resources should be used for data center development where consistent with the land’s intended purpose. It defines a data center project as one requiring more than 100 MW of new load dedicated to AI, and qualifying projects include those with at least $500 million in committed capital expenditures or more than 100 MW of incremental load.2 It also directs agencies to apply and expand NEPA categorical exclusions and to streamline other permits.211
The appeal is easy to see. DOE sites often come with existing transmission, large water supplies, a long industrial history and security perimeters. They also come with conditions a private parcel does not: federal ownership stays in place, use must fit the agency’s mission, and the lease runs on federal procurement rules and timelines.
Fig. 1Federal land for data centers, 2025–2026
- EO 14141 signedFederal sites for AI infrastructure
- DOE request for information16 candidate sites identified
- Four DOE sites; EO 14318July 2025
- INL and Oak Ridge solicitationsSeptember 2025
- Army conditional selectionsMarch 2026, Fort Bliss and Dugway
- BLM Townsite approvalJune 26, 2026, Boulder City, Nevada
- Savannah River and Paducah picksJuly 2026
02The four DOE sites
DOE announced the four sites in July 2025, saying they could host both data centers and power generation. The pool started with 16 locations identified after an April 2025 request for information.1 Each site then moved through its own solicitation.
| Site | State | What was offered | Status reported |
|---|---|---|---|
| Idaho National Laboratory | Idaho | Request for applications issued September 8, 2025, for land within the 890-square-mile site121 | No award found in public reporting |
| Oak Ridge Reservation | Tennessee | Request for proposals for long-term leases on two parcels: East Tennessee Technology Park and land next to Oak Ridge National Laboratory5 | No award found in public reporting |
| Paducah Gaseous Diffusion Plant | Kentucky | Redevelopment of parts of the former 3,500-acre plant site17 | Partnership announced July 20267 |
| Savannah River Site | South Carolina | Ten tracts totaling 3,103 acres13 | Amentum and DC Blox selected July 2026; lease under negotiation6 |
At Oak Ridge, DOE’s Office of Environmental Management and Office of Science evaluated proposals on technological readiness, financial viability and plans to complete regulatory and permitting requirements.5 Those criteria are a useful preview of what any federal site will ask: a credible power plan, a balance sheet and a permitting schedule, not just a site plan.
Most of these sites are former nuclear weapons or fuel-cycle complexes, so parts of them carry legacy contamination and active cleanup; the Oak Ridge solicitation itself came partly from DOE’s Office of Environmental Management.5 Our guide to repurposing industrial and power plant sites covers the diligence that follows from that history.
03What the first selections look like
The two 2026 selections show DOE favoring projects that bring their own power. At Savannah River, DOE selected Amentum and DC Blox to develop an AI data center with dedicated on-site generation; the project description calls for a 1 GW data center alongside about 2 GW of on-site generation, and the parties will now negotiate a phased lease.6
At Paducah, DOE announced a partnership in late July 2026 with a group including Big Rivers Electric, Brookfield, NextEra Energy and local cooperatives. NextEra is to develop 2 GW of new grid-connected gas-fired generation, upgrade transmission and deploy up to 2.6 GW of battery storage; the announcement did not mention nuclear power.7
Fig. 2First DOE site selections, 2026
- planned Savannah River AI data center
- 1 GW
- planned on-site generation at Savannah River
- ~2 GW
- new gas generation at Paducah
- 2 GW
- battery storage at Paducah
- Up to 2.6 GW
For developers, the pattern matters more than the names. Federal sites reward teams that can pair load with new generation, whether behind the meter or grid-connected, which is the same logic behind nuclear and SMR siting at or near DOE land.
04BLM public lands: the Boulder City test case
The Bureau of Land Management’s first data center approval shows the legal friction federal land can carry. On June 26, 2026, BLM approved a data center on 88.5 acres of public land in Eldorado Valley, within Boulder City, Nevada, drawing up to 167 MW. BLM did so by amending a right-of-way previously granted for a 19 MW solar project with 35 MW of battery storage, relying on the environmental analysis prepared for that project rather than a new one.3
Boulder City, environmental groups and residents appealed to the Interior Board of Land Appeals, arguing that a data center is a materially different use whose water, air and other effects were never analyzed.14 On September 1, 2026, an administrative judge stayed the permit, finding the appellants had made a persuasive showing that BLM erred in treating the data center as substantially the same as the solar project it had reviewed in 2023.9 A stay is not a final ruling; the board’s decision on the merits was still to come.
05Military installations and enhanced use leases
The Army and Air Force are offering land through enhanced use leases (EULs), which let a service lease non-excess property to a private partner. The Army’s first EUL request for data centers covered installations including Fort Hood, Fort Bliss, Fort Bragg and Dugway Proving Ground; projects must be compatible with the military mission, the Pentagon can end leases for non-compliance, and offerors must describe their local outreach. Terms could run as long as 50 years.15 In March 2026 the Army announced conditional selections: Carlyle for about 1,384 acres at Fort Bliss, Texas, and CyrusOne for about 1,201 acres at Dugway Proving Ground, Utah, with leases still to be finalized.4
In April 2026 the Department of the Air Force issued a request for lease proposals for about 4,700 acres across Joint Base Elmendorf-Richardson, Eielson Air Force Base and Clear Space Force Station in Alaska, in 12 identified parcels. Under the EUL model the Air Force receives at least fair market value, and the developer is responsible for financing, permitting, construction and long-term operation.16
Fig. 3Three federal land routes compared
Idaho, Oak Ridge, Paducah, SRS
DOE site lease
- Competitive solicitation per site
- Long-term lease, privately funded
- Developer builds, runs, decommissions
- Power plan weighs heavily
Public lands
BLM right-of-way
- Grant or amended right-of-way
- Field office decision
- Appealable to the land appeals board
- First approval stayed in 2026
Army, Air Force
Military EUL
- Non-excess base land
- At least fair market value
- Must fit the military mission
- Developer finances and permits
06How a federal site differs from private land
A federal lease removes some problems and adds others. Compare it with a private ground lease, covered in our guide to ground leases for data centers.
- Environmental review: projects with substantial federal involvement may need NEPA review. EO 14318 directs that projects receiving less than 50% of their funding from federal sources not be treated as major federal actions, but a lease or right-of-way on federal land is still an agency decision, as the Boulder City dispute shows.1114
- Power: the land does not bring firm power by itself. Oak Ridge applicants must secure their own utility interconnection agreements.5
- End of term: DOE expects developers to decommission what they build.5
- Mission limits: military leases can be terminated for non-compliance with mission requirements.15
- Local taxes and politics: federal land is generally outside local property tax rolls, and local opposition can still shape outcomes, as Boulder City’s appeal shows.9 See our guide to property taxes on data center projects for how local property taxes normally work.
07How to approach a federal site opportunity
- 01Track solicitations on SAM.gov and agency news pages; each site runs on its own deadline.
- 02Read the evaluation criteria first. At Oak Ridge they were technological readiness, financial viability and permitting plans.5
- 03Build the power case early: new generation, storage and transmission upgrades featured in both 2026 DOE selections.7
- 04Plan for a project-specific environmental review, and for appeals.9
- 05Price the lease against private alternatives, including decommissioning obligations and the time a federal process adds.
- 06Line up local support. The Army asks offerors to describe their community outreach, and Boulder City’s appeal shows what happens when a host community objects.15
Treat a federal solicitation like any other site decision: confirm power, water, access and buildable area on the actual parcel offered, not on the reputation of the larger reservation. Ten tracts at one site can differ as much as ten private farms.13
Federal land is one option among several. If you are weighing a federal solicitation against private sites, we can get a site reviewed for power, water and buildable area, using the same methodology we apply to private land.
Common questions
Which DOE sites are available for AI data centers?
DOE selected four in July 2025: Idaho National Laboratory, the Oak Ridge Reservation in Tennessee, the Paducah Gaseous Diffusion Plant in Kentucky and the Savannah River Site in South Carolina.1 Each has its own solicitation, and as of October 2026 developers had been selected at Savannah River and Paducah.67 The Army runs a separate leasing program on its bases.4
Can a company buy federal land for a data center?
The DOE and military programs offer long-term leases, not sales. At Oak Ridge, DOE sought long-term leasing agreements funded solely by the applicants.5 Military enhanced use leases require at least fair market value.16
What did the July 2025 executive order on data centers do?
Executive Order 14318 directs agencies to make suitable federal land available for data centers and to speed permitting, including through NEPA categorical exclusions.2 It covers projects with more than 100 MW of new load or at least $500 million of committed capital, among other criteria.2
Notes
- 1.American Public Power Association, “DOE Announces Site Selection for AI Data Center and Energy Infrastructure Development on Federal Lands,” 2025. publicpower.org
- 2.The White House, “Accelerating Federal Permitting of Data Center Infrastructure,” 2025. whitehouse.gov
- 3.Field & Stream, “Data Center Approved for Public Land in Nevada,” 2026. fieldandstream.com
- 4.U.S. Army, “Army reaches conditional agreement with private industry for hyperscaled data centers,” 2026. army.mil
- 5.U.S. Department of Energy, “U.S. Energy Department Seeks Proposals for AI Data Centers, Energy Projects at Oak Ridge,” 2025. energy.gov
- 6.Data Center Dynamics, “DOE selects Amentum, DC Blox to develop behind-the-meter AI data center at Savannah River Site in South Carolina,” 2026. datacenterdynamics.com
- 7.American Nuclear Society, Nuclear Newswire, “Private-sector data center plans advance for Paducah and Savannah River sites,” 2026. ans.org
- 8.GovRegs (U.S. Code, 15 U.S.C. 9401 editorial notes), “Editorial Notes, 15 U.S.C. 9401,” n.d. govregs.com
- 9.Outdoor Life, “Public Land Data Center Paused,” 2026. outdoorlife.com
- 10.Covington & Burling, Global Policy Watch, “January 2025 AI Developments: Transitioning to the Trump Administration,” 2025. globalpolicywatch.com
- 11.Sheppard Mullin, “Trump Administration Gives Data Centers a Big Push,” 2025. sheppard.com
- 12.Hogan Lovells, “DOE opens the door to AI data centers and energy projects at the Idaho National Laboratory,” 2025. hoganlovells.com
- 13.World Nuclear News, “Data centres and energy proposals sought for Savannah River and other US federal sites,” 2025. world-nuclear-news.org
- 14.Ashurst Perkins Coie, “Federal Lands as the New AI Data Center Frontier,” 2026. ashurstperkinscoie.com
- 15.DefenseScoop, “Army looks to lease out land on 4 military installations for new commercial data centers,” 2026. defensescoop.com
- 16.ClearanceJobs, “Air Force Eyes Arctic AI Boom With New Data Center Push in Alaska,” 2026. news.clearancejobs.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Land & site fundamentals
- How Much Land Does a Data Center Need?
- Data Center Site Selection Criteria: The Complete Checklist
- Parcel Assembly for Data Center Campuses
- Gross vs. Buildable Acreage: How Much of a Site You Can Use
- Site Shape, Access and Frontage for Data Centers
- Can My Land Host a Data Center? A Landowner’s Guide
- Greenfield vs. Brownfield Data Center Sites: Which Is Better?
- Mineral Rights and Easements: How They Affect Data Center Land
- Title Review and ALTA Surveys for Data Center Land
- Can Farmland Be Converted to a Data Center?
- Data Center Land Option Agreements: Key Terms for Landowners
- What Drives Data Center Land Value? Power, Timing, Entitlements and Size
- Topographic Surveys and LiDAR for Data Center Site Selection
- Heavy-Haul Routes and Construction Access for Data Centers
- Certified Sites and Shovel-Ready Programs: What They Mean for Data Centers
- Eminent Domain and Transmission Line Easements: A Landowner’s Guide
- Conservation Easements and Deed Restrictions on Data Center Land
- Subdivision, Platting and Lot Consolidation for Data Center Sites
- Agricultural Tax Status and Rollback Taxes When Farmland Is Developed