A BlackForge Ventures company
BlackForge Data Centers

Power & interconnection

Behind-the-Meter vs. Front-of-the-Meter Power for Data Centers

Behind-the-meter power is generation or storage on the customer’s side of the utility meter, serving the data center directly; front-of-the-meter resources sit on the grid side and deliver power through the utility or transmission system. Behind-the-meter supply is growing fast, with one 2026 forecast putting behind-the-meter projects at roughly 40% of the new Lower 48 data center capacity expected through 2030,1 but it brings air permitting, fuel and operating responsibilities, as xAI’s turbine permit in Memphis showed.2 Regulators are still writing the rules for hybrid arrangements: FERC ordered PJM in December 2025 to create new transmission services for co-located loads, and Texas now requires review of co-location deals with existing plants.34

Last reviewed · 9 min read · BlackForge Data Centers

Key takeaways

  • The meter is the dividing line between the customer’s system and the utility’s.
  • Behind-the-meter resources serve the load directly and reduce what the grid must deliver; customers that keep grid backup usually pay standby charges.5
  • Front-of-the-meter resources connect to the grid and reach the data center through it, with grid reliability as the backstop.
  • Co-location with an existing plant is regulated closely: FERC rejected an expanded Talen–Amazon agreement in 2024, then ordered PJM to define co-location services in 2025.36
  • Texas SB 6 requires ERCOT review and PUCT approval of net metering arrangements between existing generators and large loads.4
  • Many campuses combine both: grid service plus on-site generation or storage.
Public data · Power trackerLarge-load power tracker39 utilities and their data center power rules, from public filings.

01What “behind the meter” and “front of the meter” mean

The utility revenue meter marks where the utility’s system ends and the customer’s begins. Everything on the utility side, including transmission lines, substations owned by the utility and power plants selling into the grid, is front of the meter. Everything on the customer side is behind the meter.

Fig. 1Where the meter divides a data center’s supply

  1. 01Grid generationUtility plants, independent generators, PPAs
  2. 02Transmission and utility substationUtility or transmission owner’s system
  3. 03Revenue meterThe dividing line
  4. 04Customer substation and on-site plantTurbines, engines, fuel cells, batteries
  5. 05Campus and IT loadServed by the grid, on-site supply or both
Simplified. Everything above the revenue meter is front of the meter; everything below it is behind the meter. Ownership and metering points vary by utility and market.

For a data center, behind-the-meter usually means generation or storage inside the campus electrical system: gas turbines or reciprocating engines, fuel cells, batteries, solar, or in some proposals a power plant next door feeding the campus directly. Front-of-the-meter means power that comes through the grid, whether from the utility’s own plants, market purchases or a contracted generator somewhere else on the system.

Backup generators are technically behind the meter, but they are not what people usually mean. The term is mostly used for resources that run routinely, either to serve the load or to cut what the grid has to deliver. Utility rules often draw the same line: Southern California Edison, for example, exempts generators used solely for emergency backup from its standby rates.5

02How each arrangement works for a data center

Behind-the-meter vs. front-of-the-meter at a glance
FactorBehind the meterFront of the meter
Where the resource connectsCustomer side of the meter, inside the campus systemUtility or transmission system
Who usually owns and operatesCustomer or a third party under contractUtility, independent generator or market participant
Effect on grid demandReduces net demand the grid must serveNone directly; grid delivers the full load
Interconnection pathMay still need utility review, and a generator interconnection if it can exportLoad interconnection for the data center; separate generator interconnection for the resource
Main permitsAir permits, fuel supply, local land use for the plantHandled by the resource owner, often at another site
Reliability backstopGrid service if retained; otherwise on-site redundancyGrid reliability planning standards
Grid charges if grid is keptStandby or backup charges, often with a capacity reservation charge5Standard demand and energy charges under the tariff
Siting impactNeeds land, fuel access and emissions headroom on or near the campusNeeds strong transmission access at the campus

In practice the line blurs. A campus may take firm grid service for most of its load and run on-site generation to cover a gap. A plant next to a campus may be front of the meter on paper, selling into the grid, while also supplying the campus under a contract. How the arrangement is classified depends on metering, ownership and the rules of the utility and market. In PJM, for example, FERC’s new contract demand services for co-located loads require the load to be separately metered from the generator and able to limit what it draws from the grid.3

03Why developers consider behind-the-meter power

  • Speed. Where grid upgrades would take years, on-site generation can sometimes start serving load sooner, as bridge power or as a long-term supply.
  • Smaller grid request. Serving part of the load on site can reduce the upgrades the grid needs and may shorten studies.
  • Cost control. Owning generation can hedge energy prices, though it adds fuel price exposure and operating cost.
  • Resilience. On-site resources can carry load during grid events, in addition to backup systems.
  • Flexibility credit. A load that can switch to on-site power during grid stress may qualify for faster or flexible service where utilities and markets offer it. DOE’s 2025 proposal to FERC included expedited studies for flexible and curtailable loads.7

The trend is large but uncertain. Enverus forecasts about 62 GW of new Lower 48 data center capacity through 2030, roughly 40% of it from behind-the-meter projects, but it ties only 26% of its 2030 additions to projects under construction or in late development, against about 96% for 2028.1 Some proposals are very large, such as a 5 GW off-grid gas project announced in Texas in August 2025 to serve a hyperscale data center.8 Others in the market expect fully off-grid campuses to remain “the exception, not the rule.”9

Fig. 2Behind-the-meter power in one 2030 forecast

new data center capacity through 2030
~62 GW
share from behind-the-meter projects
~40%
added gas demand from these projects, 2030
~1.3 Bcf/d
of 2030 additions at advanced stages
26%
Enverus Intelligence Research forecast for the Lower 48, July 2026. Forecasts, not built capacity.1

Natural gas is the most common fuel for large behind-the-meter generation today, which ties these projects to pipeline access. During April and May 2026 earnings calls, midstream companies and gas utilities announced deals to ship fuel to data centers with co-located gas generation and outlined new or upsized pipelines.10 Our guides to on-site generation and bridge power, gas pipeline access and gas turbines vs. reciprocating engines cover the fuel and equipment side.

04The tradeoffs of behind-the-meter supply

Behind-the-meter power moves responsibilities from the utility to the project. Those responsibilities are real and they shape the site.

  • Air permitting. Generators that run routinely face stricter permitting than emergency-only units, and emissions limits can cap how much can run. See air permits for data center generators.
  • Fuel supply. A gas plant needs firm pipeline capacity, and sometimes on-site fuel backup.
  • Redundancy. If the plant is the main supply, the campus needs enough units to cover outages and maintenance, which means installing more capacity than the load.
  • Land and noise. Generation yards, fuel equipment and their setbacks take acreage and affect neighbors.
  • Regulatory treatment. Some states limit who may sell power to a customer, and a third-party-owned plant serving one customer may raise those questions. Rules vary by state, so confirm them with counsel.
  • Grid charges. Customers that self-supply but keep grid service usually pay standby rates, often including a capacity reservation charge; some utilities also apply departing load charges.5

The xAI Colossus site in Memphis shows how permitting can become the constraint. The Shelby County Health Department approved a permit in July 2025 that lets xAI keep operating 15 gas turbines, subject to formal emissions limits, testing requirements and deadlines.2 Before that, residents and advocates said the company had run more turbines than it had applied for without the appropriate permits; the company said its temporary turbines were covered by an exemption.11

05Co-location and the rules for hybrid arrangements

The hardest classification questions come up when a data center sits next to an existing plant. In November 2024, FERC voted 2–1 to reject an amended interconnection service agreement that would have raised the co-located load at Talen’s Susquehanna nuclear plant, serving an Amazon Web Services campus, from 300 MW to 480 MW, finding PJM had not justified its nonstandard terms; the existing 300 MW arrangement stayed in place.612 Opponents had argued the arrangement would let the data center avoid transmission costs that other PJM customers would then pay.612

On December 18, 2025, FERC found PJM’s tariff unjust and unreasonable for lacking clear terms for co-located load and ordered it to offer new transmission options alongside Network Integration Transmission Service, including an interim non-firm service that lets co-located load draw from the grid before network upgrades are finished.313 FERC also directed PJM to revise its rules for retail behind-the-meter generation and set a paper hearing on rates.3

Fig. 3Transmission options for co-located load in PJM

Traditional

Network service (NITS)

  • Load designated as network load
  • Billed on gross demand
  • Firm service after upgrades

Firm contract demand

  • Firm up to a set MW quantity
  • Penalties for exceeding it
  • Separate metering from the generator

Non-firm contract demand

  • Interruptible, as available
  • Curtailed before firm customers
  • Taken at 0 MW by loads that never draw
Simplified from FERC’s December 2025 order; rates and details were left to compliance filings and a paper hearing.313

Texas took a statutory route. Senate Bill 6 requires a net metering arrangement between an existing generator and a co-located large load to be reviewed by ERCOT and approved by the PUCT, and it requires large loads to disclose on-site backup generation able to serve at least 50% of their demand, which ERCOT may direct them to use in an emergency.4 As of June 2026, ERCOT reported two such arrangements approved, in April and May, with three more pending PUCT review.14 See co-locating data centers with power plants and Texas Senate Bill 6.

06Front-of-the-meter options beyond standard grid service

Front-of-the-meter does not only mean buying from the utility under its standard tariff. Data centers also use the grid to reach resources they help bring online.

  • Power purchase agreements with generators elsewhere on the grid, physical or financial depending on the market.
  • Utility programs that dedicate new resources to a large customer’s load, where offered.
  • Market purchases in regions with retail choice, through a competitive supplier.
  • Co-location next to an existing plant with power delivered through the grid, which keeps transmission planning and charges in the picture.3

These approaches keep the grid’s reliability as the backstop but leave the project dependent on the load interconnection and on transmission upgrades. Which options exist depends heavily on whether the site is in a vertically integrated utility territory or a competitive market. Federal rules may also shift: DOE’s 2025 proposal covered co-located hybrid facilities directly connected to the transmission system as well as large loads.7

07How the choice affects site selection

The decision is less about which model is better than which constraints the site can meet. A useful way to frame it is to start with the grid and treat behind-the-meter supply as a tool for gaps in capacity, timing or cost. Our decision guide on grid power vs. on-site generation walks through that choice.

  1. 01Establish what the grid can deliver at the site, and when.
  2. 02Size the gap between that and the project’s ramp.
  3. 03Check whether the site has gas access, air permitting room and land for a plant.
  4. 04Confirm how the utility and state treat self-supply, standby service, co-location and third-party ownership.
  5. 05Decide whether on-site generation is a bridge, a permanent share of supply or a resilience layer.

When we screen a site, we record both profiles: what it offers for grid service and what it offers for on-site generation. Sites that score well on both keep the most options open as a project’s needs change. To test a specific parcel against both, you can get a site reviewed.

CalculatorIT load to grid demand →CalculatorBackup generators & fuel →

Common questions

What does behind-the-meter mean for a data center?

Behind-the-meter refers to generation or storage on the data center’s side of the utility meter, serving the campus directly. Examples include on-site gas turbines or engines, fuel cells, batteries and solar. It reduces the net demand the grid has to serve. Emergency backup generators are technically behind the meter, but the term usually refers to resources that run routinely, and some utilities exempt emergency-only units from standby rates.5

What is front-of-the-meter power?

Front-of-the-meter power comes from resources on the grid side of the meter, connected to the utility or transmission system. The data center receives it through its utility service, whether the energy comes from the utility’s plants, market purchases or a power purchase agreement with a generator elsewhere, and grid reliability planning backs it up.

Can a data center run entirely behind the meter, off the grid?

It is technically possible but demanding. A fully islanded campus needs generation to cover its peak load plus outages and maintenance, a firm fuel supply, air permits for routine operation and its own controls. Large off-grid gas projects have been announced,8 but some in the market expect fully off-grid campuses to remain the exception rather than the rule.9

Is behind-the-meter generation faster than waiting for grid power?

Sometimes. Where grid upgrades would take years, on-site generation may start serving load sooner. But it has its own timeline: air permits, gas pipeline capacity, equipment lead times and local approvals. Permitting disputes, like those over the xAI turbines in Memphis, can slow or constrain a project.11

Notes

  1. 1.Enverus, “Off the Grid, on the Gas,” 2026. enverus.com
  2. 2.CNBC via NBC San Diego, “Musk’s xAI scores permit for gas-burning turbines to power Grok supercomputer in Memphis,” 2025. nbcsandiego.com
  3. 3.Beveridge & Diamond, “FERC Orders PJM to Create Clear Rules for Co-Located Data Centers and Large Loads,” 2025. bdlaw.com
  4. 4.Baker Botts, “Texas Senate Bill 6: Understanding the Impacts to Large Loads and Co-Located Generation,” 2025. bakerbotts.com
  5. 5.Southern California Edison, “Standby Fact Sheet and FAQ,” 2025. sce.com
  6. 6.Data Center Dynamics, “FERC blocks plan for Susquehanna nuclear plant interconnection to Amazon data center,” 2024. datacenterdynamics.com
  7. 7.Foley & Lardner, “DOE Proposes New Federal Standards for Interconnecting Large Loads to the Grid,” 2025. foley.com
  8. 8.Data Center Dynamics, “Pacifico Energy unveils 5GW off-grid natural gas project in Texas slated to serve a hyperscale data center,” 2025. datacenterdynamics.com
  9. 9.Bisnow, “‘The Exception, Not The Rule’: Despite Hype, Off-Grid Data Centers Fueled By Natural Gas May Be Rare,” n.d. bisnow.com
  10. 10.S&P Global, “Pipeline operators strike deals as data centers turn to colocated generation,” 2026. spglobal.com
  11. 11.Inside Climate News, “In South Memphis, Elon Musk’s Colossus Operated Gas Turbines Without Appropriate Permits, Residents and Activists Claim,” 2025. insideclimatenews.org
  12. 12.World Nuclear News, “Regulator rejects amended Susquehanna power agreement,” 2024. world-nuclear-news.org
  13. 13.Jones Day, “FERC Issues Anticipated Order on Data Center Colocation in PJM Region,” 2025. jonesday.com
  14. 14.ERCOT, “Trending Topic: Grid Reliability, Data Centers and Net Metering Arrangements,” 2026. ercot.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Terms in this guide

Related guides

More in Power & interconnection

Guide 12 of 35 in Power & interconnection · all 242 guides · glossary · calculators