Key takeaways
- Firm service is planned to hold through normal outages; non-firm service sits lower in curtailment priority and can be cut when the system is constrained.41
- SPP’s CHILLS, approved by FERC on June 5, 2026, offers non-firm transmission service for up to seven years while a large load secures firm service.15
- PJM’s Board in January 2026 directed a “connect and manage” framework in which new large loads without their own new generation would be curtailed before pre-emergency demand response.2
- Texas Senate Bill 6 requires non-critical large loads interconnecting on or after December 31, 2025, to have remote-disconnect capability for emergency load shed.6
- Classic retail interruptible riders trade a bill credit for a cap on interruption hours, but some are small, closed or capped.78
- Backup generators are not a free hedge: federal air rules limit non-emergency run hours for emergency engines.3
01What “firm” service actually means
Every service agreement answers one question: under what conditions can the utility stop delivering power to you? With firm service the answer is “only in emergencies the system was not planned to withstand.” The utility and its transmission planner study the grid so that your contracted load can be served through normal contingencies, such as the loss of a line or transformer. That is why firm service for a large load often waits on network upgrades and new generation, and why it is the bottleneck behind most interconnection delays.
Non-firm service starts from a different promise: you get power when the system has room. In FERC’s December 2025 order on co-located load in PJM, the non-firm contract demand service it described is an as-available service with curtailment priority below firm customers.4 Interruptible and curtailable service are the retail-rate versions of the same idea, usually written into a tariff rider with a credit, a notice period and a cap on hours.7
The terms overlap and utilities use them loosely. In this guide, “non-firm” and “conditional” refer to service granted before the grid is fully built to support the load, and “interruptible” refers to a rate option a customer chooses for a discount. The legal definition in your own agreement is what counts, so read it, and confirm with the utility how it applies.
Fig. 1Three ways to take grid service
Default goal
Firm
- Planned to serve full load through normal outages
- Often waits on upgrades and generation
- Highest curtailment priority
- Basis for most financing
Bridge
Non-firm or conditional
- Uses capacity available today
- Can be cut when the system is constrained
- Often time-limited until upgrades finish
- Faster path to energization
Interruptible rider
- Customer opts in for a bill credit
- Interruption hours capped by tariff
- Notice period set in the rider
- Often has size limits or enrollment caps
02Conditional service while grid upgrades are built
The most important development for site selection is conditional service as a bridge. The logic is simple: the transmission system may have spare capacity in most hours today, even though it cannot yet serve a new load firmly under every contingency. Rather than make the customer wait years for upgrades, the grid operator connects the load now and keeps the right to cut it when the system is stressed.
SPP’s Conditional High Impact Large Load Service (CHILLS) is the clearest example. FERC approved it on June 5, 2026.1 Under CHILLS, SPP provides transmission service using available transmission capacity for up to seven years while the large load acquires firm service, and SPP can cut service when the system is constrained or under emergency conditions.1 The seven-year limit is meant to push customers to obtain designated resources or complete the upgrades needed for firm long-term service through existing tariff processes.5
At the distribution level, Pacific Gas and Electric’s Flex Connect program offers faster connections in exchange for curtailment agreements while local upgrades are completed.9 A flexible connection of this kind typically pairs a firm portion of the load with a conditional portion that relies on on-site or co-located resources during limited periods of system stress.10
Fig. 2Illustrative path from conditional to firm
Illustrative- Load study and agreement
- Conditional serviceCurtailable when the system is constrained
- Network upgrades built
- Firm serviceFull contracted load, normal priority
For a developer the question is not only whether conditional service exists, but whether there is a credible, dated path to firm service at the end of it. Ask what upgrades are assumed, who is funding them and what happens if they slip. Our guide to transmission upgrades and cost allocation covers the funding side.
03PJM, FERC and the national push
PJM has moved on two tracks. For loads co-located with generation, FERC in December 2025 directed PJM to create three new transmission service options: an interim non-firm service while upgrades are built, a firm contract demand service and a non-firm contract demand service.114 FERC found that PJM’s tariff lacked services reflecting co-located loads “willing and able to limit their energy withdrawals from the transmission system under certain conditions.”11 Our guide to co-locating data centers with power plants covers that configuration.
For grid-connected large loads, the PJM Board’s January 16, 2026 decision on the Critical Issue Fast Path process for large load additions paired a voluntary “bring your own new generation” track with expedited interconnection, and a “connect and manage” framework for new large loads that do not bring generation.2 Under that framework, curtailment is expected to occur before pre-emergency demand response is deployed, and the Board described it as an interim solution while new load outpaces new capacity.2 PJM forecasts roughly 70 GW of new large-load demand by 2038, alongside about 15 GW of generation retired since 2022.212
FERC has since widened the scope. On June 18, 2026, it issued show cause orders to all six FERC-jurisdictional RTOs and ISOs, requiring each to show that its tariff adequately addresses large-load interconnection or to propose reforms, with responses due by August 17, 2026.13 Expect more non-firm and conditional products to emerge from those filings. The PJM site selection guide and the ISO and RTO guide explain how market rules shape siting.
04Texas: curtailment written into law
Texas took a statutory route. Senate Bill 6, enacted in 2025, defines large loads as 75 MW or more (the PUCT may lower the threshold) and ties curtailment authority to firm load-shed emergencies rather than ordinary peak conditions.6 Key provisions for site planning:
- Non-critical large loads interconnecting on or after December 31, 2025, must have remote-disconnect capability for emergency load shedding.6
- Large loads with on-site backup generation able to serve at least 50% of their demand must disclose those facilities to the utility and ERCOT.6
- ERCOT may issue emergency notices directing large loads with backup generation to reduce load or deploy that generation.6
- The PUCT and ERCOT must develop new demand-response and reliability services, including a competitively procured program in which participants receive 24 hours’ notice before a curtailment request.6
The PUCT adopted its implementing interconnection rule for ERCOT loads of 75 MW or more on September 18, 2026.14 In practice every new large load in ERCOT now carries some exposure to emergency curtailment, whether or not it signs up for anything voluntary. Our guide to Texas Senate Bill 6 covers the law in detail, and ERCOT site selection covers the market.
05Retail interruptible riders
Long before data centers, utilities offered interruptible rates to industrial customers who could shut down a process for a few hours in exchange for a lower bill. These riders still exist and some data center operators look at them, but they were not designed for 100 MW-plus loads.
| Tariff | Key limits | Status |
|---|---|---|
| East Kentucky Power Cooperative, Rate D | Interruptible demand of 250 kW to 20,000 kW, with a maximum number of interruption hours per year7 | Available to owner-members; the sheet cited is a superseded 2026 version, so check the current one7 |
| AES Indiana, Rider 14 | Minimum 1,500 kW interruptible demand; total program capacity capped at 100 MW8 | Closed to new customers; effective July 27, 20268 |
The pattern is common: a size ceiling below what a hyperscale campus needs, a program cap, or a closed enrollment.78 Where a rider does fit, the terms that matter are the credit, the notice period, the maximum hours per event and per year, and the penalty for failing to curtail. A large-load tariff may also include its own curtailment or minimum-bill terms; see large-load tariffs and electric service agreements.
06What curtailment asks of the site
Accepting non-firm service is an operating decision as much as a contract term. A data center has three ways to ride through a curtailment: reduce IT load, shift work elsewhere, or run on-site power. The first two are covered in our guide to flexible data center loads and demand response. The third is constrained by air permits.
Under Clean Air Act rules, certain stationary emergency engines may run without an hourly limit in true emergencies but are limited to 100 hours a year for non-emergency operation, of which up to 50 hours may be used under certain demand response arrangements.3 EPA’s May 2025 guidance set out five conditions for that 50-hour use, including dispatch by the local balancing authority or transmission and distribution operator to avoid interruption of local supply.315
Fig. 3Numbers that bound non-firm service
That is why a site that plans to accept meaningful curtailment usually needs permitted prime or bridge power, not just emergency diesel. Gas supply, emissions permits and generator footprint then become part of the land question. See on-site generation and bridge power and microgrids and battery storage.
07What to ask before accepting non-firm service
- 01What triggers a curtailment: system emergency, local constraint, price, or operator discretion?
- 02What notice is given, and what is the maximum duration per event and per year?
- 03Is the curtailment full or partial, and what portion of the load stays firm?
- 04What upgrades or resources convert the service to firm, on what date, and who pays if they slip?
- 05What penalties apply if the load does not curtail on time?
- 06What on-site generation may run during curtailment under the site’s air permit?
Get the answers in writing and have counsel and an electrical engineer review the agreement. A parcel near a constrained substation can still be a good site if conditional service is available and the site can carry the backup it implies. If you want to know where a parcel stands, get a site reviewed.
Common questions
What is the difference between firm and non-firm power for a data center?
Firm service is planned to deliver the full contracted load through normal grid contingencies. Non-firm service is delivered when capacity is available and carries a lower curtailment priority, so it can be cut when the system is constrained.4 Non-firm service is often offered as a bridge while upgrades for firm service are built.1
What is SPP’s CHILLS?
CHILLS is SPP’s Conditional High Impact Large Load Service, approved by FERC on June 5, 2026. It provides non-firm transmission service to large loads for up to seven years using available capacity, while the customer obtains firm service, and SPP can cut it when the system is constrained or in emergencies.15
Can ERCOT curtail my data center under Texas SB 6?
SB 6 ties curtailment of large loads to firm load-shed emergencies and requires non-critical large loads interconnecting on or after December 31, 2025, to have remote-disconnect capability.6 ERCOT may also direct large loads with backup generation to reduce load or run that generation during emergencies.6 Confirm how the PUCT’s implementing rules apply to your project.
Can I run diesel backup generators during a curtailment?
In a true emergency, emergency engines generally may run without an hourly limit, but non-emergency operation is capped at 100 hours a year, with up to 50 of those hours usable for qualifying demand response under conditions EPA clarified in 2025.315 Your state air permit may be stricter, so check it before relying on generators for planned curtailment.
Notes
- 1.Utility Dive, “FERC approves SPP non-firm, large-load transmission service,” 2026. utilitydive.com
- 2.PJM Interconnection Board of Managers, “PJM Board Letter re Results of the CIFP Process: Large Load Additions,” 2026. pjm.com
- 3.Sidley Austin, “US EPA Issues New Guidance on Data Center Emergency Generator Operations,” 2025. sidley.com
- 4.Foley & Lardner, “FERC Opens New Paths for Co-Located Loads in PJM: What Data Center and Power Generation Developers Need to Know,” n.d. foley.com
- 5.Federal Energy Regulatory Commission, “195 FERC ¶ 61,196, Order on Revisions to Add the Conditional High Impact Large Load Service (Docket ER26-1323),” 2026. spp.org
- 6.National Law Review, “Texas Senate Bill 6 Ushers In Major Overhaul of Large Load Interconnection and Grid Access Rules,” 2025. natlawreview.com
- 7.East Kentucky Power Cooperative (Kentucky PSC tariff filing), “Rate D – Interruptible Service,” 2026. psc.ky.gov
- 8.AES Indiana, “Rider 14 Interruptible Power,” 2026. aesindiana.com
- 9.Latitude Media, “PG&E is laying the groundwork for flexible data center interconnection,” n.d. latitudemedia.com
- 10.Renewable Energy World, “Flexible interconnection promises speed to power for utilities, data center developers | Q&A with Camus Energy,” n.d. renewableenergyworld.com
- 11.Beveridge & Diamond, “FERC Orders PJM to Create Clear Rules for Co-Located Data Centers and Large Loads,” 2025. bdlaw.com
- 12.T&D World, “PJM Board Outlines Plans to Integrate Large Loads in 2026,” 2026. tdworld.com
- 13.Orrick, “FERC Show Cause Orders Signal Broad Reform to Large Load Interconnection Policies,” 2026. orrick.com
- 14.White & Case, “PUCT sets financial commitments for data center interconnection as governor pauses permit approvals,” 2026. whitecase.com
- 15.U.S. Environmental Protection Agency, “RICE Memo on Duke Energy Regulatory Interpretation,” 2025. epa.gov
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Power & interconnection
- How Much Power Does a Data Center Need?
- Transmission Voltage and Data Centers: 69 kV to 765 kV
- Substation Proximity and Capacity for Data Center Sites
- How the Large-Load Utility Interconnection Process Works
- ISOs, RTOs and Utility Territories in Data Center Siting
- What Is Powered Land?
- Load Ramp Schedules: How to Phase Power for a Data Center Campus
- Redundant Utility Feeds and Dual Substations for Data Centers
- Behind-the-Meter vs. Front-of-the-Meter Power for Data Centers
- Transmission Upgrades for Data Centers: Who Pays for Them?
- Microgrids and Battery Storage at Data Center Sites
- Co-Locating Data Centers With Power Plants
- Nuclear and Small Modular Reactors: Siting Considerations for Data Centers
- Renewable Energy Procurement and How It Affects Data Center Siting
- What Is a Utility Load Study for a Data Center?
- PJM Capacity Prices and Data Center Load Growth
- Contribution in Aid of Construction (CIAC) and Line Extensions for Data Centers
- Transformer and Switchgear Lead Times for Data Centers
- Substation Configurations for Data Center Campuses: Ring Bus, Breaker-and-a-Half and Double Bus
- Electricity Rates and Power Costs for Data Center Sites
- Power Purchase Agreements for Data Centers: Physical, Virtual and Sleeved
- 24/7 Carbon-Free Energy and Hourly Matching for Data Centers
- Gas Turbines vs. Reciprocating Engines for Data Center On-Site Power
- Fuel Cells for Data Center Power: How They Work and Where They Fit
- NERC Reliability Standards and Large Data Center Loads: Ride-Through, Load Loss and Registration
- From Signed Agreement to Energization: The Data Center Power Timeline
- Hydropower and Data Center Siting: Public Power, Allocations and Drought Risk
- Geothermal Power for Data Centers: Enhanced Geothermal, Clean Tariffs and Siting in the West
- Surplus Interconnection Service and Retired Power Plant Sites: How Existing Grid Rights Get Reused
