BlackForge Data Centers

Power & interconnection

Hydropower and Data Center Siting: Public Power, Allocations and Drought Risk

Hydropower drew data centers to central Washington and western New York because it was cheap, carbon-free and dispatchable, but the cheap existing hydro is largely spoken for. Utilities such as Grant and Chelan County PUDs now serve new large loads under separate rates and frameworks that pass the cost of new supply to the data center,12 and New York’s low-cost hydro is allocated in fixed blocks tied to jobs and location.3 Hydro output also swings with water: EIA expected 2024 U.S. hydropower to be the lowest since 2001, driven by drought in the Pacific Northwest.4

Last reviewed · 9 min read · BlackForge Data Centers

Key takeaways

  • Washington produced about 25% of U.S. utility-scale hydroelectric generation in 2024, and Grand Coulee is the largest U.S. power plant by capacity.5
  • Grant PUD’s eight data center operators used about 280 aMW in 2025, roughly 37% of its average system load; its 2024 queue held 1,568 MW of data center requests.67
  • New load in a hydro PUD rarely gets legacy hydro cost: Grant serves “New Large Load” under a separate schedule, and Chelan’s framework offers market, customer-sourced or negotiated supply.12
  • In New York, Western New York Hydropower is a 695 MW block limited to businesses within 30 miles of the Niagara Power Project, awarded competitively.38
  • Hydro is energy-limited: EIA forecast Northwest hydro in 2024 about 23% below its 10-year average.94
  • Hyperscalers are now contracting existing hydro directly, as in Google’s 2025 framework with Brookfield for up to 3,000 MW.10

01Why hydropower attracts data centers

Hydropower has three traits that data center buyers value at once: low operating cost, no direct emissions and output that can be scheduled within the limits of the water available. That combination helped draw large campuses to the Columbia River towns of central Washington, and it is why New York’s low-cost Niagara hydro has long been used as an economic development tool.3

The resource is concentrated. EIA reports that Washington generated more electricity from hydropower than any other state, about a quarter of the national total in 2024, and that Grand Coulee on the Columbia is the largest power plant in the United States by capacity.5 Most U.S. hydropower capacity sits in the Pacific Northwest.4 Regional analysts note that hydro still provides more than half of the Northwest grid’s nameplate capacity.11

Fig. 1Hydropower and the Northwest grid

Washington’s share of U.S. hydro output, 2024
~25%
Hydro share of Northwest nameplate capacity
50%+
Data centers’ share of Grant PUD load, 2025
~37%
Priest Rapids and Wanapum dams combined
2,100+ MW
Washington figures from EIA’s state profile;5 capacity share from regional adequacy analysis;11 Grant PUD figures from the utility.6

For site selection, the useful distinction is between hydro as a regional advantage and hydro as power actually available to a new customer. The first is a matter of geography. The second depends on who owns the dams, who already has rights to their output and what the serving utility’s rules say about new large loads, which is where most of the diligence lies. Our Pacific Northwest site selection guide covers the region more broadly.

02Public utility districts and who owns the hydro

Much of the Northwest’s hydro belongs to public power: federal dams marketed by the Bonneville Power Administration (BPA), and county public utility districts (PUDs) that own their own projects. A PUD is a consumer-owned utility, so its board weighs data center growth against rates for residential, farm and small business customers. The glossary entry on utility ownership types explains how this differs from an investor-owned utility.

Grant County PUD shows the scale involved. It holds physical rights to 63.31% of the output of the Priest Rapids and Wanapum dams, which together exceed 2,100 MW.6 Its eight data center operators accounted for about 280 average megawatts in 2025, roughly 37% of the district’s average system load of about 757 aMW.6 In August 2024 the PUD reported 75 applications for new or expanded large-load service totaling 2,897 MW of peak demand, with data centers the largest share and Quincy the area of greatest interest.7

Fig. 2Grant PUD large-load requests, August 2024

  • All large-load requests2,897
  • Data center requests1,568
  • Requests in the Quincy area1,578

MW of peak demand

Requests in the queue, not approved service. Grant PUD’s existing average system load was about 757 aMW in 2025, an energy measure rather than peak.76

Utilities that buy most of their power from BPA face a different constraint: they must first confirm they can obtain supply for a large new load. A Snohomish County PUD official put it plainly in 2026, saying that when a very large load request comes in, “we just can’t say yes” without that work.12 A PUD with its own dams and one that relies on BPA can give very different answers to the same request.

03How hydro utilities price and supply new large loads

The common thread among hydro utilities is that legacy hydro is reserved for existing customers, and new large loads pay for the new supply they cause. Grant PUD’s large industrial schedule applies to loads of 10 MW and above, but any load that is or becomes a “New Large Load” under the district’s customer service policies is served under a separate rate schedule.1 The district says its rate strategy is meant to protect residential, small business and agricultural customers, because growth driven largely by the industrial sector, including data centers, requires buying more expensive power.6

Chelan County PUD adopted a large-load framework in 2024 with guiding principles of a neutral-to-positive impact on other customers and stable rates.2 It offers three supply paths:

Fig. 3Chelan PUD’s three large-load supply options

Short-term supply

  • PUD buys wholesale power on the market
  • Resells it to the large-load customer
  • Price follows the market

Customer choice

  • Customer identifies a wholesale source
  • PUD purchases and resells it
  • Customer carries supply sourcing

Board discretion

Negotiated contract

  • Negotiated with the PUD board
  • May include surplus hydropower
  • Terms set contract by contract
Summarized from Chelan PUD’s 2025 description of its framework; contract terms are negotiated case by case.2

The first contract under the framework, approved in June 2025 for Microsoft’s Malaga campus, illustrates the terms in practice: up to 18 MW of surplus hydropower at market-based prices through the end of 2025, with supply for 2026 through 2040 not yet determined, and the customer paying up front for the $86.5 million Jumpoff Ridge substation and related upgrades.13 For a developer, “hydro territory” now means paying for infrastructure and accepting market exposure, not inheriting low legacy rates. See large-load tariffs and electric service agreements for how these terms compare elsewhere.

04Firm hydro, surplus hydro and drought variability

Hydro plants are limited by energy as much as by capacity. A dam can run at full output for hours, but over a season it can only generate what the river delivers. Utilities therefore plan firm commitments around low-water years and sell the remainder as surplus when water is good. The Chelan contract’s “surplus hydropower” wording reflects that distinction: surplus is what remains after firm obligations, and it can shrink in a dry year.13

Dry years are not hypothetical. In November 2024, EIA forecast that U.S. hydropower generation that year would be 13% below the 10-year average and the lowest since 2001, citing extreme and exceptional drought, especially in the Pacific Northwest.4 The Northwest region was forecast at about 101.8 billion kWh, roughly 23% below its 10-year average of 132.8 billion kWh.9

Fig. 4Northwest hydropower: 2024 forecast vs. average

  • 10-year average132.8
  • 2024 forecast101.8

billion kWh

EIA’s late-2024 forecast for its Northwest region, as reported; final 2024 data may differ.94

Regional analysts argue that, with more variable resources and changing hydro operating constraints, the Northwest can no longer assume it has enough capacity to meet all demand.11 The Northwest Power and Conservation Council is building data centers into its next 20-year power plan, and an expert panel told it in 2026 that a data center design standard could cut peak electrical and mechanical energy use by about one-fifth, at some cost in water use.14 For a buyer, drought risk shows up as higher replacement-power costs, curtailment of surplus supply or slower approvals, so ask how the utility treats your load in a critical water year. Our guides to firm vs. interruptible service and drought risk go further.

05New York: NYPA hydropower allocations

New York allocates its low-cost hydro through statutory programs run by the New York Power Authority (NYPA) rather than through a utility tariff. Western New York Hydropower, which combines Expansion Power and Replacement Power, is a 695 MW block from the Niagara plant awarded competitively to businesses within a 30-mile radius of the Niagara Power Project.3 State law defines eligible projects as economic development projects physically located within 30 miles of the Niagara project at Lewiston, with allocations approved by NYPA’s trustees.8

ReCharge New York is statewide and larger: 910 MW, half drawn from firm hydropower at NYPA’s Niagara and St. Lawrence-FDR projects and half procured from market sources.15 Awards are tied to commitments; NYPA’s report gives an example of 6.5 MW in exchange for 65 jobs and a $42 million five-year capital investment.15

NYPA programs relevant to large loads (as of NYPA’s most recent public descriptions)
ProgramSizeWhereBasis of award
Western New York Hydropower (Expansion and Replacement Power)695 MW3Within 30 miles of the Niagara Power Project8Competitive; jobs and investment
ReCharge New York910 MW, half hydro15StatewideJobs and capital investment commitments15

Allocations are sized for industrial users, not gigawatt campuses. In 2023 NYPA’s board approved a roughly 10.7 MW Niagara allocation to an Amazon facility tied to 1,000 jobs, an example of the jobs-per-megawatt logic these programs apply.16 A large data center can treat an allocation as a cost offset for part of its load, while buying the rest at market under New York’s grid rules. Our New York site selection guide covers NYISO and local projects.

06Contracting for hydro without moving to it

Hydro can also follow a data center by contract. In July 2025, Brookfield and Google announced a framework for up to 3,000 MW of U.S. hydroelectric capacity, starting with 20-year power purchase agreements for the Holtwood and Safe Harbor plants in Pennsylvania, 670 MW in all, to support Google’s operations across PJM.10 The framework targets plants that will be relicensed, overhauled or upgraded to extend their lives, focusing first on PJM and MISO.10

Deals like this decouple the clean-energy claim from site location: the buyer gets hydro attributes in the same grid region without needing a dam next door. They do not change the physical constraints at the site, which still needs utility service, transmission and capacity. See power purchase agreements for data centers and 24/7 carbon-free energy for how these contracts count toward clean energy goals.

07What to check at a hydro-region site

  1. 01Identify the serving utility and whether it owns hydro, buys from BPA or another wholesaler, or is an investor-owned utility.12
  2. 02Read its large-load policy: which rate schedule applies to new large load, and whether legacy hydro is available at all.1
  3. 03Ask what supply backs your contract after any short-term term ends, and who bears market price risk.13
  4. 04Ask how your service is treated in a low-water year, and whether any portion is surplus or interruptible.4
  5. 05Budget for customer-funded substations and upgrades, which hydro PUDs increasingly require.13
  6. 06In New York, check distance to the Niagara Power Project and whether a jobs and investment commitment for an allocation fits the project.815

Water for cooling is a separate question from water for power, and it can matter as much in dry years; see data center water requirements. If you want an outside view of whether a hydro-region parcel can actually be served, you can get a site reviewed.

Common questions

Is hydropower cheaper for data centers?

Existing hydro is among the lowest-cost power, but new large loads often do not get it. Grant PUD serves new large loads under a separate rate schedule, and Chelan PUD’s framework relies on market or negotiated supply.12 The low rates associated with hydro regions mostly belong to existing customers.

Why are so many data centers in Quincy, Washington?

Quincy sits in Grant County PUD territory, which owns rights to most of the output of two large Columbia River dams.6 Data centers already account for about 37% of the district’s load, and Quincy drew the most large-load interest in its 2024 queue.67

Can a drought cut power to a data center?

Firm service is planned to hold through low-water years, but surplus supply and prices can change. EIA forecast 2024 U.S. hydro output at its lowest since 2001 because of Northwest drought.4 Ask the utility how your contract is treated in a critical water year.

Can data centers get NYPA hydropower?

Yes, through competitive programs. Western New York Hydropower is limited to projects within 30 miles of the Niagara Power Project, and ReCharge New York is statewide; both tie awards to jobs and investment.815

Can a data center buy hydropower in another region?

Yes, by contract. Google’s 2025 framework with Brookfield covers up to 3,000 MW of U.S. hydro, beginning with 20-year agreements for two Pennsylvania plants in PJM.10 The site still needs its own utility service.

Notes

  1. 1.Grant County Public Utility District, “2026 Rate Schedule 15,” 2026. grantpud.org
  2. 2.Chelan County Public Utility District, “Commissioners consider powering data center in a way that protects reliability, rates,” 2025. chelanpud.org
  3. 3.New York Power Authority, “Economic Development,” n.d. nypa.gov
  4. 4.U.S. Energy Information Administration, “Drought conditions reduce hydropower generation, particularly in the Pacific Northwest,” 2024. eia.gov
  5. 5.U.S. Energy Information Administration, “Washington State Profile and Energy Estimates,” n.d. eia.gov
  6. 6.Grant County Public Utility District, “Data Center FAQs,” n.d. grantpud.org
  7. 7.Grant County Public Utility District, “Commission Recap 8-27-2024,” 2024. grantpud.org
  8. 8.New York State Senate, “New York Economic Development Law Section 189-A,” n.d. nysenate.gov
  9. 9.Industrial Info Resources, “EIA Forecast: 2024 U.S. Hydropower Generation to Reach Lowest Level Since 2001,” 2024. industrialinfo.com
  10. 10.Brookfield Renewable (press release via Seeking Alpha), “Brookfield and Google Sign Hydro Framework Agreement to Deliver up to 3,000 MW of Homegrown Energy in the United States,” 2025. seekingalpha.com
  11. 11.Renewable Energy World, “Will data centers disrupt power system adequacy in the U.S. Pacific Northwest?,” n.d. renewableenergyworld.com
  12. 12.The Everett Herald, “Snohomish County PUD plans for potential large load customers,” 2026. heraldnet.com
  13. 13.Chelan County Public Utility District, “PUD commissioners approve power contract for Microsoft data center,” 2025. chelanpud.org
  14. 14.Northwest Power and Conservation Council, “Expert panel addresses data center energy efficiency, load flexibility, and water impacts in Pacific Northwest,” 2026. nwcouncil.org
  15. 15.New York Power Authority, “2024 Report to Governor and Legislative Leaders on Power Programs for Economic Development,” 2025. nypa.gov
  16. 16.Renewable Energy World, “NYPA approves hydropower allocations to Amazon, Micron, others,” 2023. renewableenergyworld.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Related guides

More in Power & interconnection