BlackForge Data Centers

Power & interconnection

What Is a Utility Load Study for a Data Center?

A utility load study is the engineering analysis a utility or transmission planner runs to find out whether the grid can serve a new large load at a specific point, what facilities and upgrades it would need, and when. For data centers it typically covers steady-state, short-circuit and, increasingly, dynamic stability analysis, using the customer’s peak demand, ramp schedule and one-line diagram.1 Studies usually carry a fee or deposit, which at AEP Ohio is estimated at $10,000 to $100,000 depending on size and complexity.2

Last reviewed · 8 min read · BlackForge Data Centers

Key takeaways

  • A load study answers three questions for a specific location: can the grid serve the load, what must be built, and how soon.3
  • Utilities ask for peak demand, a year-by-year ramp, power factor, a one-line diagram and, for larger loads, dynamic models of how the facility behaves.14
  • Many utilities now charge study fees or require deposits; AEP Ohio requires a paid load study for new data center loads of 25 MW or more.2
  • Grid operators are moving from one-at-a-time studies to batch or cluster studies, as ERCOT did with its Batch Zero process, approved in June 2026.5
  • Study results are a snapshot. A queue position, signed agreement and financial commitment are what turn them into a service date.3

01What a load study is, and what it is not

When a developer asks a utility to serve a data center, the utility cannot answer from a map. It has to model the new load on its system, under stressed conditions, and see what breaks. That modeling exercise is the load study. Depending on the utility it may be called a load interconnection study, a facilities study, a system impact study or, in ERCOT, a Large Load Interconnection Study (LLIS).6

A load study sits inside a longer sequence. Before a utility energizes a large load it typically has to screen the request, study the system, choose a constructible solution, complete detailed engineering, obtain permits and regulatory approvals, and then build; Dominion Energy Virginia’s proposed queue process lays out exactly those stages.3 The study is the step that turns a request into an engineering answer, but it is not the commitment itself.

It also differs from a capacity screen. A utility account manager may say informally that a substation “has room.” A study tests that claim against planning criteria, contingencies and every other load and generator already in the queue. Our guide to the large-load interconnection process covers where the study falls in the full path to service, and the glossary entry on interconnection studies defines the common terms.

02What the utility asks you to submit

Study quality depends on input quality. Utilities and their planners ask for more data than many first-time applicants expect, and the requests have grown as data center behavior has come under scrutiny.

  • Location: coordinates of the proposed load and, if known, the substation or line the developer hopes to tap.4
  • Load size and ramp: peak demand, and the MW to be energized each month or year through full build.1
  • Power factor: across loading levels, measured at the high-voltage delivery point.14
  • Electrical design: a preliminary one-line diagram and any reactive devices on site.1
  • Schedule: an estimated project timeline with target in-service dates for each block of load.
  • Dynamic models: in ERCOT, a stability study is required for any load of 75 MW or more, so a dynamic load model or PSCAD model representing the actual load behavior must be submitted with the request.4

The ramp schedule deserves the most care. It drives which years the planner tests, and under newer tariffs it can become the basis for minimum bills. Our guide to load ramp schedules and phased power explains how to build one that holds up.

03What the engineers actually test

NERC’s 2025 Level 2 alert on large loads recommended that transmission planners and planning coordinators use steady-state, dynamic and short-circuit models to assess the reliability impacts of large loads.1 In practice a full study tends to include the following.

Fig. 1Three core analyses in a large-load study

Always

Steady-state

  • Thermal loading of lines and transformers
  • Voltage under normal and outage conditions
  • Tested at peak demand in each ramp year
  • Identifies network upgrades

Short-circuit

  • Fault current at nearby buses
  • Breaker and equipment duty ratings
  • Protection coordination

Large loads

Dynamic stability

  • Voltage and frequency recovery after faults
  • Ride-through or tripping of the load
  • Collective tripping of nearby facilities
  • Needs a validated load model
Simplified summary of the study types NERC recommends for large loads; scope varies by utility and load size.14

Dynamic studies are where data centers differ most from older industrial loads. Since 2022 NERC has analyzed load-loss events in the Eastern and Texas interconnections caused by computational loads disconnecting unexpectedly, events that existing planning studies did not predict.1 The alert recommends that studies explicitly account for the collective tripping of electrically close facilities, which matters at sites near existing data center clusters.1 Expect questions about ride-through, UPS behavior and on-site generation transfer schemes.

The output is a list of facilities: the interconnection itself (a tap, a new substation or switching station), any network upgrades to lines or transformers, and the earliest dates those can be in service. Who pays for those upgrades is covered in transmission upgrades and cost allocation.

04Study phases and how long they take

Most utilities run large-load requests through stages that move from screening to firm engineering. Dominion Energy Virginia’s proposed queue process, filed with the State Corporation Commission, describes four: project initiation (submission, viability screening and queue placement), project feasibility (system studies and selection of a constructible solution), project development (detailed engineering, permitting and regulatory approvals) and project execution (final design, construction and energization).3

Fig. 2From load request to energization

  1. 01

    Initiation

    Submission, viability screen and queue placement.

  2. 02

    Feasibility

    System studies; choose a constructible solution.

  3. 03

    Development

    Detailed engineering, permits, regulatory approvals.

  4. 04

    Execution

    Final design, construction and energization.

Stages in Dominion Energy Virginia’s proposed large-load queue process; other utilities use similar sequences under different names.3

Timing is set less by engineering hours than by the queue. Dominion reported roughly 70 GW of large-load delivery points in its queue, nearly three times its all-time system peak of 24.7 GW set in January 2025.3 About 25 GW had projected connection dates through 2031, and about 45 GW was still under study.3

Fig. 3Dominion Energy Virginia large-load queue

large-load delivery points in queue
~70 GW
all-time system peak, January 2025
24.7 GW
assigned dates through 2031
~25 GW
still under study
~45 GW
Figures as reported in Dominion’s queue-process filing; the vast majority of requests are tied to data centers.3

Texas shows the shift toward group studies. ERCOT’s Planning Guide Section 9 sets out the LLIS procedures, report and follow-up steps for new or modified large loads.6 On June 18, 2026, the PUCT approved PGRR 145 and its companion NPRR 1325, with key provisions taking effect in July 2026.5 Together they create a one-time “Batch Zero” process that sorts pending requests by study maturity and commitment and studies them together in two phases.7 See power timelines and interconnection queues for how queue position translates into a date.

05Study fees, deposits and early commitments

Load studies used to be free or nearly so. That has changed as speculative requests have piled up. AEP Ohio, under its data center tariff, requires new data centers or expansions of 25 MW or more to complete an intake form and pay a load study fee it estimates at $10,000 to $100,000.2 Some cooperatives work through a sequence of agreements instead: Tri-County Electric Cooperative in Texas starts requests of 2 MW or more with a large load service request, then requires a reimbursable services agreement, a construction development agreement and an electric service agreement at later milestones.8

Fees are the small part. The bigger commitment comes after the study, when the customer signs a service agreement that may include long terms, minimum bills and collateral. Georgia’s Public Service Commission in January 2025 approved rules for new Georgia Power customers above 100 MW that allow contract terms of up to 15 years, minimum billing and PSC review of the contracts.9 Our guide to large-load tariffs and electric service agreements covers those terms.

The cost of a study filters the queue. After AEP Ohio’s tariff took effect, its reported data center pipeline fell from more than 30 GW of requests to about 13 GW.10 Expect any request you file to be treated as a real project, with the obligations that follow.

06How to read the results

A study report usually gives a point of interconnection, a scope of work, a cost estimate (often with a wide range at early stages) and an in-service date that depends on equipment procurement and permitting. Read it for four things:

  1. 01The date for each phase of your ramp, not only the first block of load.
  2. 02Upgrades that depend on someone else’s project, such as a new line another customer is funding.
  3. 03Conditions on service, such as reduced firm capacity or curtailment until upgrades are complete. See firm vs. interruptible power.
  4. 04How long the results stay valid, and what changes (load size, location, ramp) would trigger a restudy.

07Before you request a study

A load study is not the first step in site screening. It is expensive in time, and it commits you to a load profile. Before filing, it pays to know which utility serves the parcel, which substations and lines are realistic taps, and whether public planning data already shows constraints. Our guides to power capacity data sources and utility will-serve letters cover that groundwork.

  • Confirm the serving utility and whether an RTO or ISO process also applies.
  • Fix a credible peak load and ramp, and a target power factor.
  • Prepare a preliminary one-line and, for large loads, a plan for dynamic models.14
  • Ask the utility for its current fee, deposit, study scope and expected duration in writing.2
  • Budget for what follows the study: agreements, collateral and upgrade costs.

If you are deciding which parcels deserve a study request, BlackForge can get a site reviewed against nearby transmission, substations and published constraints before you commit.

Common questions

How much does a utility load study cost for a data center?

It varies by utility and load size. AEP Ohio estimates its data center load study fee at $10,000 to $100,000 depending on size and complexity.2 Some cooperatives instead use a reimbursable services agreement, so the applicant pays for engineering and study work as it is performed.8

How long does a data center load study take?

The engineering itself can take a few months, but total time depends on the queue and whether the utility studies requests individually or in batches. Dominion Energy Virginia reported about 45 GW of large-load requests still under study, and ERCOT’s Batch Zero process, approved in June 2026, studies pending Texas requests as a group.35 Ask the utility for its current expected duration in writing.

What is the difference between a feasibility study, a system impact study and a facilities study?

The names vary by utility. Generally a feasibility or screening study gives a quick view of whether service is possible, a system impact study models the effect on the grid and identifies upgrades, and a facilities study designs and estimates the specific equipment. Dominion’s proposed process groups system studies under a feasibility stage and detailed engineering under development.3

Why do utilities want dynamic models of my data center?

Because data centers have disconnected from the grid in large groups during faults, in events that existing planning studies did not predict.1 NERC recommends dynamic and short-circuit studies alongside steady-state analysis, and in ERCOT any load of 75 MW or more needs a stability study.14

Does a completed load study reserve capacity for my project?

Usually not by itself. Capacity is typically held only once you sign a service agreement and post the required collateral, and terms vary by utility and state. Georgia’s 2025 rule, for example, ties large-load contracts to longer terms and minimum bills.9 Confirm with the utility what, if anything, your study result reserves.

Notes

  1. 1.North American Electric Reliability Corporation, “NERC Alert Level 2: Large Loads,” 2025. nerc.com
  2. 2.AEP Ohio, “Data Center Tariff,” n.d. aepohio.com
  3. 3.Data Center Dynamics, “Dominion files large load connection queue plan with state regulators,” n.d. datacenterdynamics.com
  4. 4.CenterPoint Energy Houston Electric, “CEHE Load Interconnection Data Request Form,” n.d. centerpointenergy.com
  5. 5.Sheppard Mullin, “PUCT Approves Batch Zero Framework That Will Provide a Pathway for Large Load to Connect to the Grid and Receive Electricity,” 2026. sheppard.com
  6. 6.Electric Reliability Council of Texas, “Planning Guide Section 9: Large Load Additions at New or Modification of Existing Load Interconnection(s),” 2026. ercot.com
  7. 7.Willkie Farr & Gallagher, “ERCOT Approves Implementing New Batch Zero Process for Large Load Interconnections,” 2026. willkie.com
  8. 8.Tri-County Electric Cooperative, “Large Load Requests,” n.d. tcectexas.com
  9. 9.Capitol Beat News Service (The Current GA), “Georgia PSC passes rule for data centers’ power usage,” 2025. thecurrentga.org
  10. 10.Data Center Dynamics, “AEP Ohio slashes data center pipeline by more than half - report,” n.d. datacenterdynamics.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Related guides

More in Power & interconnection