Key takeaways
- Solid oxide fuel cells (SOFCs) convert natural gas to electricity electrochemically, without combustion; Bloom cites lifetime electrical efficiency of about 54%.2
- The main appeal is speed: Bloom and Oracle described onsite power for an entire data center within 90 days, against multi-year grid timelines.4
- In California, units certified under the state’s distributed generation program are exempt from local air district permits, which shortens permitting compared with engines or turbines.5
- Natural gas fuel cells still emit CO2: Bloom publishes 679–833 lb per MWh, below an average gas plant but far from zero.6
- Gas supply is the siting constraint: a fuel cell campus needs a firm, adequately sized gas lateral, and new pipeline work can set the schedule.7
01How data center fuel cells work
A fuel cell produces electricity through an electrochemical reaction rather than by burning fuel to spin a generator. In a solid oxide fuel cell, a ceramic electrolyte carries oxygen ions that react with hydrogen and carbon monoxide reformed from natural gas inside the unit. The output is direct current, which inverters convert to AC for the facility. The U.S. Department of Energy’s fuel cell office has examined this pairing directly, holding a 2019 workshop on hydrogen and fuel cells for data centers at which presenters examined fuel cells as primary on-site power.8
Most of the capacity being sold for data centers today is solid oxide. Bloom Energy’s Energy Server, the most widely deployed product in this segment, is sold in blocks of roughly 325 kW and scales to hundreds of megawatts by adding units side by side or stacking them.2 Other chemistries exist (molten carbonate, phosphoric acid and proton exchange membrane units), but SOFCs dominate the large-load announcements of 2024–2026.13
- Fuel: pipeline natural gas in almost every current data center project; biogas and hydrogen are possible in some products.2
- Efficiency: Bloom cites about 54% lifetime electrical efficiency, and more than 90% combined efficiency when waste heat is captured.2
- Operation: no combustion, few moving parts and no water consumption in normal operation, which matters in water-stressed sites.4
Fig. 1How a fuel cell plant serves a data center
- 01Gas transmission or LDC mainFirm supply sized for the full plant.
- 02Gas lateral and meteringDedicated line, pressure regulation, metering.
- 03Fuel cell modulesRoughly 325 kW blocks, reforming gas to power.
- 04Inverters and switchgearDC to AC, paralleled into medium voltage.
- 05Data center loadWith or without a grid tie for backup or export.
02Why data centers are turning to fuel cells
The driver is time to power. In many markets a large load waits years for transmission upgrades. AEP, for example, told Ohio regulators it could take 7 to 10 years for transmission to meet full demand in central Ohio, and it proposed on-site fuel cells to let data centers start operating in the meantime.9 Our guide to power timelines and interconnection queues explains why those waits arise.
Fuel cells answer that gap in three ways. They are modular, so capacity can be added as the ramp schedule grows. They are dense: Bloom says its deployments reach about 100 MW per acre, a vendor figure that implies a small footprint for the output.1 And they can be installed quickly once gas and equipment are on hand; Bloom and Oracle said in announcing their 2025 agreement that Bloom would provide onsite power for an entire data center within 90 days.4
Fuel cells can serve as bridge power until a grid connection arrives, as a permanent behind-the-meter source, or as a utility-owned asset on the customer’s site. The last model is new and worth understanding, because it changes who carries the cost and the regulatory approvals.
03Major data center fuel cell deployments
The market changed quickly between late 2024 and early 2026. The deals below are public and well reported; they show the range of ownership models.
| Announced | Parties | What was agreed |
|---|---|---|
| Nov. 2024 | AEP and Bloom Energy | Supply agreement for up to 1 GW; initial 100 MW order for AI data center loads.1 |
| Feb. 2025 | Equinix and Bloom Energy | Expansion taking Equinix’s fuel cell commitments past 100 MW.10 |
| May 2025 | AEP Ohio, AWS and Cologix | Ohio regulators approved utility-owned on-site fuel cells; six-year (AWS) and 15-year (Cologix) contracts.9 |
| July 2025 | Oracle and Bloom Energy | Fuel cells at select Oracle Cloud Infrastructure data centers in the U.S.4 |
| Oct. 2025 | Brookfield and Bloom Energy | Up to $5 billion to deploy Bloom systems at AI data centers.3 |
| Jan. 2026 | AEP subsidiary and Bloom | About $2.65 billion of SOFCs for a plant near Cheyenne, Wyoming, with a 20-year offtake.11 |
The Ohio case is a useful template. AEP Ohio owns the fuel cells, the data center customers pay for them under long-term contracts, and the application stated that other ratepayers would not pay for the system.9 The Wyoming project, by contrast, sits in an unregulated AEP subsidiary that sells all of the output to a single investment-grade customer under a 20-year agreement.11 For a landowner, these are two different counterparties with different approval paths.
Fig. 2Scale of recent fuel cell deals
- AEP supply agreement with Bloom, Nov. 2024
- 1 GW
- Brookfield commitment to Bloom systems3
- $5 billion
- AEP fuel cell purchase for a Wyoming plant
- $2.65 billion
- Offtake term for the Wyoming facility
- 20 years
04Gas supply, footprint and site layout
A fuel cell plant is only as reliable as its gas supply. A data center running on fuel cells as its primary source needs gas around the clock, so the buyer will look for firm transportation and a dedicated lateral sized for the full build, not interruptible service from a local distribution main. Our guides to natural gas pipeline access and firm gas transportation cover how to judge that.
New pipe can be the long pole. For AEP’s central Ohio fuel cell project, a gas utility agreed to build, own and operate a new pipeline to the site, with service targeted for October 2026 when the deal was announced in August 2025.7 That is a gas lateral project with its own easements and approvals, separate from the electric side.
- Land: fuel cells are compact, but the site still needs room for gas metering, inverters, switchgear, access roads and maintenance clearances.
- Layout: modules are typically placed outdoors on pads near the electrical yard. Stacking options reduce footprint further.2
- Maintenance: stacks degrade over time and are replaced on a schedule, so access for heavy equipment matters for the life of the plant.
- Grid tie: many designs keep a utility connection for backup or eventual transition; confirm the utility’s rules for parallel operation early.
05Air permitting and emissions
Because there is no combustion, fuel cells emit very little nitrogen oxide, carbon monoxide or particulate matter. California’s Air Resources Board certifies qualifying units under its Distributed Generation Certification Program, which state law exempts from local air district permit requirements; Bloom’s 325 kW natural gas ES-6.5 unit was certified in 2024 under Executive Order DG-058, with NOx limited to 0.07 lb per MWh.5 Certification is not itself a permit, and the owner still has to meet other applicable rules. Other states treat fuel cells differently, so confirm with the state air agency whether a permit, registration or exemption applies. Our guide to air permits for data center generators covers the combustion alternatives.
Carbon dioxide is another matter. A natural gas fuel cell oxidizes the carbon in the fuel, so CO2 output follows efficiency. Bloom publishes emission rates of 679–833 pounds of CO2 per MWh for its natural gas units, against its own reference figures of about 970 pounds for an average gas plant and 2,260 pounds for an average coal plant.6 That is a meaningful reduction from the average fleet, but it is in the range of modern combined-cycle gas generation, not near zero.
Fig. 3CO2 emissions per MWh, published figures
- Bloom fuel cell (low)679
- Bloom fuel cell (high)833
- Average gas plant970
- Average coal plant2,260
lb CO2 per MWh
06Costs and trade-offs against other options
Fuel cells generally cost more per MWh than grid power in markets with ample capacity, and their economics depend heavily on gas price, financing structure and incentives. The case for them is speed and certainty, not cheapness. Bloom has positioned its partnerships around this: the Brookfield deal is explicitly about on-site, behind-the-meter power for AI facilities facing grid congestion.3 In announcing it, Bloom claimed capital costs on par with gas turbines and 15–20% lower fuel use; treat those as vendor figures to test against quotes. The same coverage noted that hydrogen remains too costly for most deployments, so nearly all units run on natural gas, and that an Amazon contract for Bloom fuel cells at three Oregon data centers had been cancelled the year before.3 Deals can change, so diligence should cover the counterparty and the contract, not just the technology.
Fig. 4Fuel cells vs. engines and turbines on site
Fast, dense, quiet
Fuel cells (SOFC)
- No combustion, low NOx
- Modular 325 kW blocks
- About 100 MW per acre (vendor figure)
- Stack replacements over life
Reciprocating engines
- Mature, many suppliers
- Fast start and load following
- Combustion air permits
- Noise mitigation needed
Gas turbines
- Large unit sizes
- Long lead times for many models
- Combustion air permits
- Lower cost per MW at scale
The comparison with engines and turbines is covered in more depth in our guide to gas turbines vs. reciprocating engines, and the broader choice in grid power vs. on-site generation. Fuel cells are rarely the only answer on a large campus; many designs pair them with batteries, engines or a later grid connection.
07What to check if fuel cells are part of the plan
- 01Confirm gas: which pipeline or distribution utility can deliver firm volume to the site, at what pressure, and how long a new lateral would take.
- 02Ask the electric utility how it treats on-site generation: parallel operation, standby charges, and whether it offers a utility-owned model like AEP Ohio’s.
- 03Check the state air rules for fuel cells, and whether local zoning treats a fuel cell plant as an accessory use or a power plant.
- 04Reserve land for pads, metering, inverters and future expansion, and keep heavy-equipment access to every row.
- 05Plan the end state: whether fuel cells remain primary, become backup, or are replaced by a grid connection once transmission arrives.
A site with strong gas and weak near-term electric capacity is exactly where fuel cells help. If you want an outside view of both, you can get a site reviewed.
Common questions
Can a data center run entirely on fuel cells?
Yes, technically. Fuel cells can serve as the primary source with no grid connection, provided gas supply is firm and the plant has enough redundant modules. Several 2025–2026 agreements describe behind-the-meter fuel cell power for whole AI facilities.311
Do fuel cells use water?
Solid oxide fuel cells from Bloom do not consume water in normal operation, which Oracle highlighted when announcing its deployment.4 Cooling the data center itself is a separate water question.
Are natural gas fuel cells carbon free?
No. They emit CO2 because they oxidize the carbon in natural gas. Bloom publishes 679–833 pounds per MWh for its natural gas units, well below coal and below an average gas plant, but in the range of efficient gas generation.6
Do fuel cells need an air permit?
It depends on the state. California exempts units certified under its Distributed Generation Certification Program from local air district permits.5 Elsewhere, check with the state air agency early.
Notes
- 1.Bloom Energy (Business Wire), “Bloom Energy Announces Gigawatt Fuel Cell Procurement Agreement with AEP to Power AI Data Centers,” 2024. businesswire.com
- 2.Bloom Energy, “Bloom Energy Server Brochure 2025,” 2025. bloomenergy.com
- 3.Data Center Dynamics, “Bloom Energy signs $5bn partnership with Brookfield to deploy fuel cell tech across AI data centers,” 2025. datacenterdynamics.com
- 4.Oracle and Bloom Energy (Business Wire), “Oracle and Bloom Energy Collaborate to Deliver Power to Data Centers at the Speed of AI,” 2025. businesswire.com
- 5.California Air Resources Board, “Executive Order DG-058 (Distributed Generation Certification),” 2024. ww2.arb.ca.gov
- 6.Bloom Energy, “How Bloom Reduces Emissions (technical note),” n.d. bloomenergy.com
- 7.Pipeline & Gas Journal, “Hope Utilities to Build Ohio Gas Pipeline for Data Center Project,” 2025. pgjonline.com
- 8.U.S. Department of Energy, Hydrogen and Fuel Cell Technologies Office, “In-Rack Direct DC Powering of Servers with Solid Oxide and Proton Exchange Membrane Fuel Cells (H2@Scale Data Center Workshop),” 2019. energy.gov
- 9.WOSU Public Media, “State utility officials approve AEP Ohio’s building onsite energy generators at two data centers,” 2025. wosu.org
- 10.Bloom Energy (Business Wire), “Bloom Energy Expands Data Center Power Agreement with Equinix Surpassing 100MW,” 2025. businesswire.com
- 11.American Electric Power, “Form 10-K for fiscal year 2025,” 2026. sec.gov
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Power & interconnection
- How Much Power Does a Data Center Need?
- Transmission Voltage and Data Centers: 69 kV to 765 kV
- Substation Proximity and Capacity for Data Center Sites
- How the Large-Load Utility Interconnection Process Works
- Power Timelines: Why “When” Matters as Much as “Where”
- ISOs, RTOs and Utility Territories in Data Center Siting
- What Is Powered Land?
- Load Ramp Schedules: How to Phase Power for a Data Center Campus
- Redundant Utility Feeds and Dual Substations for Data Centers
- Large-Load Tariffs and Electric Service Agreements, Explained
- Transmission Upgrades for Data Centers: Who Pays for Them?
- Co-Locating Data Centers With Power Plants
- Nuclear and Small Modular Reactors: Siting Considerations for Data Centers
- Renewable Energy Procurement and How It Affects Data Center Siting
- What Is a Utility Load Study for a Data Center?
- Firm vs. Interruptible Electric Service for Data Centers
- Flexible Data Center Loads and Demand Response
- Texas Senate Bill 6: What It Means for Data Centers and Large Loads
- PJM Capacity Prices and Data Center Load Growth
- Contribution in Aid of Construction (CIAC) and Line Extensions for Data Centers
- Transformer and Switchgear Lead Times for Data Centers
- Substation Configurations for Data Center Campuses: Ring Bus, Breaker-and-a-Half and Double Bus
- Electricity Rates and Power Costs for Data Center Sites
- Power Purchase Agreements for Data Centers: Physical, Virtual and Sleeved
- 24/7 Carbon-Free Energy and Hourly Matching for Data Centers
- NERC Reliability Standards and Large Data Center Loads: Ride-Through, Load Loss and Registration
- From Signed Agreement to Energization: The Data Center Power Timeline
- Hydropower and Data Center Siting: Public Power, Allocations and Drought Risk
- Geothermal Power for Data Centers: Enhanced Geothermal, Clean Tariffs and Siting in the West
- Surplus Interconnection Service and Retired Power Plant Sites: How Existing Grid Rights Get Reused
