Data Center Site Selection in New York and New England

In New York and New England, a data center connects through a wires utility in a restructured market run by NYISO or ISO-NE and pays into a capacity market whose costs vary by zone. For large loads the two markets now look very different: New York’s queue held 51 large-load projects totaling about 12.7 GW by May 2026,1 while ISO-NE’s first large-load forecast included just one data center, a 200 MW project in formal study.2 In both, scarce land, strong local control, wetlands review and new state rules make the entitlement path as important as the power.

Last reviewed · 10 min read · BlackForge Data Centers

Key takeaways

  • NYISO covers New York State and ISO-NE the six New England states; both run energy and capacity markets, and both received FERC show-cause orders on large-load interconnection in June 2026.3
  • NYISO’s planning forecast assumes only about 2.9 GW of New York’s 12.7 GW large-load queue connects by 2040.1
  • Executive Order 62, signed July 14, 2026, pauses discretionary DEC permits for data centers of 50 MW or more until a statewide environmental review is finished.4
  • ISO-NE’s draft large-load rules would require new loads of 50 MW or more at 69 kV or higher to bring their own new capacity.5
  • Local approvals carry weight: Massachusetts zoning changes generally need a two-thirds vote, and Vermont’s Act 250 can reach commercial projects on as little as one acre.67
  • Former industrial, brownfield and power plant sites are often the most realistic large sites.
Public data · Power trackerLarge-load power tracker39 utilities and their data center power rules, from public filings.

01How power is organized in New York and New England

NYISO operates the grid and wholesale markets for New York State. ISO-NE does the same for Connecticut, Maine, Massachusetts, New Hampshire, Rhode Island and Vermont. Both run energy and capacity markets and plan regional transmission. Most states in the region restructured their electric industries, so utilities typically own transmission and distribution but not most generation, and customers can buy energy from competitive suppliers. Municipal utilities and some cooperatives also serve parts of the region.

NYISO and ISO-NE at a glance
FeatureNYISOISO-NE
FootprintNew York StateSix New England states
Market designEnergy market and capacity market with locational requirementsEnergy market; capacity market moving to a prompt auction
Main internal constraintUpstate to downstate transfer toward New York City and Long IslandWinter fuel supply and a rising winter peak
Who serves the loadTransmission and distribution utility or municipal utilityTransmission and distribution utility or municipal utility
Energy supplyCompetitive supplier or utility default service in most areasCompetitive supplier or utility default service in most areas

For a data center, that means at least three relationships: the wires utility for interconnection and delivery, the ISO for bulk grid review and the market that sets prices, and an energy supplier. Our guide to ISOs, RTOs and utility territories explains the general structure.

02New York: upstate, downstate and the large-load queue

NYISO prices energy by zone, and the divide between upstate and downstate is the main feature of the system. Upstate has significant hydropower, nuclear and other generation and more open land; New York City and Long Island are dense, with high demand and limited room for new generation or transmission. Because transfer capability between them is limited, NYISO sets locational minimum capacity requirements for New York City (Zone J), Long Island (Zone K) and the Lower Hudson Valley G–J Locality, each of which must cover a set share of its own peak with capacity inside the area,8 so capacity tends to cost more downstate.

Large-load requests have surged. New York’s interconnection queue grew from six large-load projects totaling 1,045 MW in 2022 to 51 projects totaling 12,670 MW by May 2026, yet NYISO’s planning forecast assumes only about 2,880 MW of that demand is integrated by 2040.1 Large data center loads are more practical upstate, where land and grid capacity are more available, though fiber and labor may be thinner. Downstate sites are usually smaller, more expensive and focused on latency-sensitive or interconnection-heavy uses.

03New York’s 2026 permit pause and cost rules

New York has moved furthest in the region. Executive Order 62, signed July 14, 2026, pauses discretionary state environmental permits from the Department of Environmental Conservation (DEC) for data centers that can use 50 MW or more until the Department of Public Service finishes a generic environmental impact statement. It reaches only applications DEC had not deemed complete, and it exempts facilities used mainly for manufacturing, research, education or medical care.4

The Legislature passed a stricter bill in June 2026, the Responsible Data Center Development Act, which would set a one-year moratorium at 20 MW and require a statewide environmental impact report;9 it was still awaiting the governor’s decision in September 2026, with inaction by year-end amounting to a pocket veto.10 Separately, the Public Service Commission opened a proceeding in February 2026 so that data centers pay their fair share of the grid upgrades they require.11 See our New York guide and our guide to moratoriums and local restrictions.

04New England: capacity, winter fuel and few large loads

ISO-NE is overhauling its capacity market. Instead of an auction held about three years ahead, it is moving to a prompt auction held shortly before each commitment period, with a second phase adding separate summer and winter obligations; the first auction under the new design is planned for 2028.12 Winter drives the change. ISO-NE’s 2026 forecast has the net winter peak rising from about 20.5 GW in 2026/27 to about 26.4 GW by 2035/36 under typical weather as heating and vehicles electrify, making New England a dual-peaking system.13 Natural gas generation is a large part of the supply mix, and NERC has warned that limited spare pipeline capacity in New York and New England threatens reliability in extreme cold.14

Large loads have barely arrived. ISO-NE’s first large-load forecast counts only projects above 20 MW that have entered formal study and discounts data center proposals by 70%; it found one 200 MW data center in the Boston area and one 85 MW project in Connecticut, adding about 110 MW of peak load in the 2030s.2 That leaves little competition in the queue, but also few precedents for how utilities and regulators will handle a large campus.

Fig. 1New England’s demand outlook

Net winter peak forecast, 2026/27
20.5 GW
Net winter peak forecast, 2035/36
26.4 GW
Large-load peak added in the 2030s
~110 MW
ISO-NE forecasts under typical weather; the large-load figure is after ISO-NE’s discounts for projects that may not be built.132

For a large load, these factors affect long-run energy and capacity costs more than whether a site can connect. The connection question is usually local: substation capacity, line upgrades and the time to permit them in a dense, wetland-rich area. Gas laterals for on-site generation face the same pipeline constraints.

05How large-load interconnection works now

The process starts with the transmission and distribution utility that serves the site. It studies the load, scopes substation and line work, and coordinates with the ISO where the load may affect the bulk system. High-voltage service in the region is commonly at 115, 230 or 345 kV. Because utilities do not own most generation, supply is handled through the market and an energy contract rather than the utility’s own resource plan. See the large-load interconnection process for the general steps.

Both ISOs are now rewriting their rules. On June 18, 2026, FERC issued show-cause orders to all six FERC-jurisdictional RTOs and ISOs, including NYISO and ISO-NE, preliminarily finding that their tariffs may not adequately address large and co-located loads.3 ISO-NE’s draft response would define a large load as 50 MW or more connecting at 69 kV or higher and require new large loads to bring their own new capacity, backed by load forecasts and a cost recovery agreement.5 In New York, the PSC proceeding is setting how upgrade costs are assigned on the utility side.11

Fig. 2Large loads in New York vs. New England

Crowded queue

New York (NYISO)

  • 51 large-load projects, about 12.7 GW, by May 2026
  • Planning forecast: about 2.9 GW connected by 2040
  • EO 62 pauses DEC permits at 50 MW and up
  • PSC proceeding on who pays for upgrades

Few large loads so far

New England (ISO-NE)

  • One 200 MW data center in formal study
  • About 110 MW of added peak in the 2030s
  • Draft rule: 50 MW+ loads bring new capacity
  • Capacity market moving to a prompt auction
Status as of mid-2026, drawn from the sources cited above; rules in both regions are still changing.
  • Ask the utility which substations have room and what upgrades a given load would trigger.
  • Ask which large-load rules will apply when the study starts, and how pending changes could affect cost and timing.
  • Plan for long permitting of any new transmission line, especially across wetlands or developed areas.

06Land, wetlands and local approvals

Large, flat, contiguous tracts are scarce. Terrain, forests, wetlands and dense development break up the land, and assembling 150 acres or more often means multiple owners. Local control is strong, particularly in New England towns, where decisions may involve planning boards, conservation commissions and town meeting. In Massachusetts, adopting or amending a zoning bylaw generally takes a two-thirds vote of town meeting or the city council.6 Vermont’s Act 250 adds state land-use review for commercial projects on 10 or more acres, or on one acre or more in towns without both permanent zoning and subdivision bylaws.7

Fig. 3Approval layers for a New England site

  1. 01Federal permitsSection 404 for wetland fill; NEPA review if there is a federal nexus.
  2. 02State permitsAir permits for generators, water withdrawals and discharges.
  3. 03State land-use reviewWhere it applies, such as Vermont’s Act 250.
  4. 04Conservation commissionWetland resource areas, buffer zones and riverfront areas.
  5. 05Town zoningPlanning board review; bylaw changes may need a town meeting vote.
Simplified; the bodies and thresholds vary by state and town, and the local layers often decide feasibility.6715
  • New York: a state court annulled DEC’s 2025 freshwater wetlands regulations in April 2026 on SEQRA grounds, and DEC did not appeal. The 2022 amendments to the Freshwater Wetlands Act still stand, so confirm with DEC which wetlands it currently regulates before relying on a map.16
  • Massachusetts: the Wetlands Protection Act regulations cover a 100-foot buffer zone around wetland resource areas and a 200-foot riverfront area along perennial rivers and streams, reviewed by the local conservation commission.15
  • State environmental review laws, such as New York’s SEQRA, apply to many state and local approvals, and other states add their own wetland rules on top of federal Section 404 jurisdiction.
  • Noise from cooling equipment and generators is a common concern in communities where homes sit close to industrial land.

Former industrial sites, brownfields and retired power plants are often the most realistic large sites, because they already have transmission, industrial zoning and sometimes water. Our guides to repurposing industrial and power plant sites and wetlands and data center development cover what to check.

07Climate, water, hazards and fiber

The cool climate supports many hours of economizer cooling and keeps peak cooling loads moderate. Water is generally available from rivers, lakes and municipal systems, though withdrawals and discharges need permits, and small towns may lack the capacity for large evaporative loads.

  • Nor’easters, ice storms and heavy snow that stress overhead lines and site access.
  • Coastal flooding and storm surge in low-lying areas, and inland river flooding.
  • Occasional hurricanes and tropical storms reaching the region.

The New York metro is one of the largest network interconnection hubs in the country, with subsea cable landings nearby and dense metro fiber, and Boston is a second hub. Upstate and northern New England sites rely on long-haul routes along interstate, rail and power line corridors, so route diversity is the main question away from the metros. Latency-tolerant loads can move inland if diverse fiber is available. See internet exchange points and carrier hotels and long-haul and subsea fiber routes.

08A New York and New England site checklist

  1. 01Confirm the ISO zone, the wires utility and the energy supply options.
  2. 02In New York, check whether the project needs discretionary DEC permits and whether its load crosses Executive Order 62’s 50 MW threshold.4
  3. 03Ask the utility about substation headroom, upgrades and how pending FERC and state large-load rules would apply.3
  4. 04Read local zoning, the approval bodies and any town meeting vote requirements.
  5. 05Map state and federal wetlands, buffer zones and riverfront areas across the buildable area.
  6. 06Compare brownfield, industrial and retired power plant sites with greenfield options, and confirm diverse fiber.

For a neighboring market under different rules, see site selection in PJM. For an independent read on a specific tract, you can get a site reviewed.

CalculatorIT load to grid demand →CalculatorCooling water use →

Common questions

What is the difference between NYISO and ISO-NE?

NYISO operates the grid and wholesale markets for New York State; ISO-NE does the same for the six New England states. Both run energy and capacity markets, but New York sets locational capacity requirements for its downstate zones,8 while ISO-NE is replacing its three-year forward auction with a prompt auction, the first planned for 2028.12 New York’s main constraint is upstate-to-downstate transfer; New England’s is winter fuel supply.

Can a data center buy power from a competitive supplier in the Northeast?

In most of New York and New England, yes. Most states in the region restructured their electric industries, so the local utility handles delivery and interconnection while customers can buy energy from competitive suppliers or take default service. Municipal utility areas are usually an exception. Delivery charges, interconnection costs and capacity costs still apply regardless of supplier.

Is New York pausing data center development?

Partly. Executive Order 62 pauses discretionary DEC permits for data centers that can use 50 MW or more until a statewide environmental review is complete, but it does not reach applications DEC had already deemed complete or facilities used mainly for manufacturing, research, education or medical care.4 A separate 20 MW moratorium bill passed in June 2026 and was still awaiting the governor’s decision in September.10

Why are large data center sites hard to find in New England?

Large, flat, contiguous tracts are scarce because of terrain, forest, wetlands and existing development, and towns control land use closely; in Massachusetts a zoning bylaw change generally needs a two-thirds vote.6 ISO-NE’s first large-load forecast found only one data center in formal study, a 200 MW project in the Boston area.2 Former industrial sites and retired power plants are often more realistic than greenfield land.

Is upstate New York a good place for a data center?

It can be. Upstate has more land and grid capacity than downstate, significant hydropower and nuclear generation, and a cool climate that supports economizer cooling. Tradeoffs include a crowded large-load queue, thinner fiber in places, distance from metro hubs and the state permit pause for projects of 50 MW or more.14 Each site needs its own check of substation capacity, zoning, wetlands and fiber diversity.

Notes

  1. 1.Regional Plan Association, “Reviewing NYISO’s Power Trends Report,” 2026. rpa.org
  2. 2.ISO New England (ISO Newswire), “ISO-NE establishes forecast framework for data centers, other ‘large loads’,” 2026. isonewswire.com
  3. 3.Akin Gump Strauss Hauer & Feld, “FERC Issues Landmark Show Cause Orders on Large Load Interconnection,” 2026. akingump.com
  4. 4.DLA Piper, “Executive Order pauses DEC permits for data centers in New York,” 2026. dlapiper.com
  5. 5.ISO New England, “Large Loads Integration Proposal Information Summary,” 2026. iso-ne.com
  6. 6.Commonwealth of Massachusetts, “Mass. General Laws c.40A § 5,” n.d. mass.gov
  7. 7.State of Vermont, Act 250 program, “1-Acre and 10-Acre Municipalities,” n.d. act250.vermont.gov
  8. 8.New York State Reliability Council, “Locational Minimum Installed Capacity Requirements Determination Process,” n.d. nysrc.org
  9. 9.Mintz, “New York Legislature Passes First-in-the-Nation Data Center Moratorium, Awaiting Governor’s Signature,” 2026. mintz.com
  10. 10.FingerLakes1.com, “Pressure builds on Hochul to sign broader data center bill,” 2026. fingerlakes1.com
  11. 11.Office of the Governor of New York, “Governor Hochul Announces PSC Proceeding on Her Plan to Ensure Data Centers Pay Their Fair Share for Energy Grid Upgrades,” 2026. governor.ny.gov
  12. 12.ISO New England, “Capacity Auction Reforms Key Project,” n.d. iso-ne.com
  13. 13.ISO New England (ISO Newswire), “ISO-NE forecast shows steady increase in regional electricity use through 2035,” 2026. isonewswire.com
  14. 14.Utility Dive, “Lack of Northeast gas pipeline capacity poses ‘severe threats to reliability’ in cold weather: NERC,” n.d. utilitydive.com
  15. 15.Massachusetts Department of Environmental Protection, “310 CMR 10.00: Wetlands Protection Act Regulations,” n.d. mass.gov
  16. 16.Hodgson Russ, “New York Court Annuls DEC’s Part 664 Freshwater Wetlands Regulations: Update on DEC Jurisdiction and Regulatory Status,” 2026. hodgsonruss.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.