Key takeaways
- National Wetlands Inventory maps are a screening tool only; they omit many small and forested wetlands and do not define regulatory jurisdiction.3
- A field delineation using the 1987 Corps manual and its regional supplements decides where wetlands actually are.4
- The 2026 nationwide permits took effect March 15, 2026 and run to March 15, 2031; NWP 39 now lists data centers and keeps its half-acre limit and pre-construction notification.1
- The federal definition of “waters of the United States” is still being rewritten as of October 2026, with a supplemental proposal issued in September 2026.5
- Federal mitigation rules prefer mitigation bank credits, then in-lieu fee credits, then permittee-responsible projects.6
- States can regulate wetlands the federal program no longer reaches, and some have expanded or narrowed their programs since 2023.78
01Why wetlands matter for data center sites
A data center campus needs large, contiguous, level pads. Wetlands and streams interrupt exactly that. A few scattered acres of wetland in the wrong place can cut a 300-acre tract into pads that no longer fit a hyperscale building, and a stream through the middle can force crossings for roads, fiber, water and medium-voltage duct banks.
Wetlands also carry schedule risk. Individual permits are discretionary, involve outside agencies and the public, and often require compensatory mitigation.26 That makes wetland acreage one of the most important subtractions in any buildable acreage estimate, alongside floodplain, slopes and tree conservation rules.
02How wetlands are identified
Desktop screening comes first. Useful sources include the U.S. Fish and Wildlife Service National Wetlands Inventory (NWI), the USGS National Hydrography Dataset for streams, NRCS soil survey data showing hydric soils, aerial imagery across wet and dry years, and LiDAR for low areas and drainage patterns. These layers point to likely problems but do not set boundaries. The U.S. Fish and Wildlife Service describes NWI maps as reconnaissance-level products drawn from high-altitude imagery, so small and forested wetlands are often missed, and it says the data should not be read as showing the extent of wetlands regulated under any federal, state, tribal or local law.3
A wetland delineation is the field step. A qualified wetland scientist walks the site and applies the 1987 Corps of Engineers Wetlands Delineation Manual together with the regional supplement for that part of the country.4 The supplements adapt the national manual to regional differences in climate, soils and vegetation, and delineating a wetland is a separate question from whether it is federally regulated.4 An area is generally a wetland when it has all three parameters:
- Hydrophytic vegetation: plants adapted to saturated conditions dominate.
- Hydric soils: soils that formed under saturation, with characteristic color and texture indicators.
- Wetland hydrology: evidence of flooding, ponding or a high water table during the growing season.
The delineator flags the boundary, a surveyor locates the flags, and streams are mapped and classified as perennial, intermittent or ephemeral. Seasonal conditions matter: some indicators are hard to read outside the growing season or during drought. Indicator lists and wetland plant lists are updated periodically, so the delineation should use current versions.4
Fig. 1From desktop screen to a usable wetland boundary
- 01
Desktop screen
NWI, streams, hydric soils, imagery and LiDAR.
- 02
Field delineation
Vegetation, soils and hydrology tested in the field.
- 03
Survey
Flags located and mapped on the site plan base.
- 04
JD request
Approved or preliminary determination from the Corps.
- 05
Layout and permit path
Avoid features, or size the nationwide or individual permit.
03Which wetlands are regulated
Not every wetland is federally regulated. Section 404 of the Clean Water Act covers “waters of the United States,” and in Sackett v. EPA (2023) the Supreme Court limited federal reach to wetlands with a continuous surface connection to those waters.10 The agencies proposed a new definition in November 2025 that would require surface water at least during the wet season, then issued a supplemental proposal in September 2026 that adds options, including requiring perennial surface water for a continuous surface connection.105 As of early October 2026 no final rule had been issued, and commentators expect litigation over the final version, so check the current rule with the Corps district before relying on a non-jurisdictional finding.
| Option | What it does | When it is useful |
|---|---|---|
| Approved jurisdictional determination (AJD) | Corps decision on which features are federally regulated; appealable | When some features may be non-jurisdictional and that changes the layout; generally valid for five years9 |
| Preliminary jurisdictional determination (PJD) | Treats delineated features as if jurisdictional; not a final decision11 | When the plan will avoid most features anyway and speed matters |
| No Corps request | Relies on the consultant’s delineation alone | Early screening only; not enough to support a permit or a purchase decision |
The five-year life of an AJD can be cut short if new information warrants a revision, because wetland boundaries change over time.9 An expired determination generally has to be redone before development, so time the jurisdictional determination against the purchase and permit schedule.
State law is the second layer. Sackett limits federal permitting authority but does not limit state authority, and many states had their own wetland permit programs before 2023.7 Since then, New Mexico and Colorado have enacted new laws to cover waters the federal program no longer reaches, while North Carolina, Tennessee, Louisiana and Indiana have reduced protections.8 States also review federal permits through Section 401 water quality certification, and local governments may add stream buffers or conservation overlays. A feature the Corps does not regulate can still be off limits.
Fig. 2The layers that can regulate one wetland
- 01Federal Section 404Corps permit where the feature is a water of the United States
- 02State 401 certificationWater quality review of the federal permit
- 03State wetland programsCan reach features outside federal jurisdiction
- 04Local rulesStream buffers, overlays and setbacks
- 05Buildable layoutWhat remains after every layer is applied
04Section 404 permits: nationwide versus individual
If a project must discharge fill into regulated wetlands or streams, it needs a Section 404 permit. The Corps uses two main paths.
| Nationwide permit (general permit) | Individual permit | |
|---|---|---|
| Scope | Small impacts below set acreage and linear-foot limits; NWP 39 caps loss at half an acre | Larger or more complex impacts |
| Process | Pre-construction notification to the Corps for many activities, including NWP 39 | Full application, public notice and comment period |
| Alternatives analysis | Limited | Must show the project is the least environmentally damaging practicable alternative2 |
| Federal reviews | ESA and historic preservation still apply where triggered | NEPA, ESA Section 7 and NHPA Section 106 as part of the Corps decision |
| Relative timeline | Shorter | Substantially longer and less predictable |
The Corps issued its current nationwide permits on January 8, 2026: 56 reissued permits and one new one, effective March 15, 2026 and expiring March 15, 2031.1 NWP 39, for commercial and institutional developments, now names data centers, including AI and machine learning facilities, as an example of a covered use. The rule also clarifies that acreage limits cannot be stacked by using more than one NWP for a single and complete project. Corps districts and states add regional conditions, and some replace NWPs with state programmatic general permits, so check the current terms for the district before assuming a project fits.
Fig. 3Key numbers in Corps wetland permitting, 2026
- nationwide permits in the 2026 rule
- 57
- NWP 39 limit on loss of waters
- 0.5 acre
- expiration of the 2026 NWPs
- March 2031
- typical validity of an approved JD
- 5 years
An individual permit is judged under EPA’s Section 404(b)(1) Guidelines, which bar a discharge if a practicable alternative would have less adverse impact on the aquatic ecosystem. Every applicant must evaluate non-aquatic sites and layouts, and practicability accounts for cost, technology and logistics in light of the project purpose.2 An individual permit also creates a federal nexus: NEPA review by the Corps, endangered species consultation under ESA Section 7 if listed species may be affected, and cultural resources review under Section 106. Each can add surveys and time, which is why a single wetland crossing can drive the permitting process for an entire campus.
05Avoid, minimize, then mitigate
Federal permitting follows a mitigation sequence. Applicants are expected to avoid impacts first, minimize the ones they cannot avoid, and then compensate for what remains. The 2008 Corps and EPA compensatory mitigation rule applies equivalent standards to all three mitigation mechanisms and sets a preference among them:6
- 01Mitigation bank credits purchased from an approved bank serving the same watershed, preferred because the bank’s plan and assurances are in place before credits are sold.6
- 02In-lieu fee program credits, where a sponsor collects fees and takes on the obligation to carry out restoration.
- 03Permittee-responsible mitigation, where the developer restores or creates wetlands on or off site and monitors them, with projects designed under a watershed approach ranked first within this group.
The choice affects schedule as well as cost. A 2018 retrospective by the rule’s lead author found that permit processing times were roughly cut in half when bank or in-lieu fee credits were used instead of traditional off-site permittee-responsible mitigation.12 Credit availability and price depend on the watershed. In some areas credits are plentiful; in others they are scarce, which can make even a modest impact expensive or slow.
06Where wetlands fit in site diligence
For screening, use desktop layers from the GIS data sources to estimate wetland and stream acreage and flag tracts where features cut through the likely building area. Before closing, commission a field delineation, survey the boundaries and decide whether to request a jurisdictional determination. Leave time in the due diligence period for seasonal fieldwork and Corps review, which can run for months.
- Ask whether any prior delineation or JD exists for the tract, and whether an AJD is still within its five-year life.
- Confirm which nationwide permits and regional conditions the Corps district applies, and whether state general permits replace them.
- Check the state wetland program, since a feature outside federal jurisdiction may still need a state permit.
- Price mitigation credits in the watershed before assuming an impact is affordable.
Wetlands, floodplain and steep slopes tend to line up along the same drainage corridors. Review them together with floodplain constraints and the site due diligence checklist so the buildable area is measured once, not three times with overlapping deductions. If you want a second look at a tract, get a site reviewed.
Common questions
Can you build a data center on land with wetlands?
Yes, as long as the buildings, substation, roads and utilities can be laid out around the wetlands or the impacts can be permitted. Many campuses avoid wetlands entirely by leaving them in open space or buffers. If fill is unavoidable, the project needs a Section 404 permit from the Army Corps of Engineers where the feature is federally regulated, state water quality approval and usually compensatory mitigation.
What is a wetland delineation?
A wetland delineation is a field survey by a qualified wetland scientist that identifies and flags the boundaries of wetlands and streams on a property. It applies the 1987 Corps manual and the regional supplement, looking for hydrophytic vegetation, hydric soils and wetland hydrology.4 The flagged lines are surveyed and mapped, and the result supports site planning and any jurisdictional determination or permit application.
Does a data center qualify for a nationwide permit?
It can. The 2026 version of NWP 39, for commercial and institutional developments, names data centers as an example, keeps a half-acre limit on the loss of waters and requires pre-construction notification.1 Impacts above the limits, or in districts with stricter regional conditions, need an individual permit.
How long does a Section 404 permit take?
It depends on the permit type, the Corps district’s workload and what other reviews are triggered. Nationwide permits for small impacts are usually faster. Individual permits involve public notice, an alternatives analysis and often Endangered Species Act and historic preservation consultation, so they take substantially longer and are less predictable. Using bank or in-lieu fee credits has been found to shorten processing compared with permittee-responsible mitigation.12
Are National Wetlands Inventory maps accurate enough for site selection?
They are useful for early screening but not for decisions. NWI maps are reconnaissance-level products drawn from aerial imagery; they often miss small or forested wetlands and do not set regulatory boundaries.3 Combine NWI with hydric soils data, stream mapping, LiDAR and multi-year imagery for screening, then rely on a field delineation before committing to a site plan or purchase price.
Notes
- 1.Sidley Austin LLP, “U.S. Army Corps of Engineers Finalizes 2026 Nationwide Permit Reissuance and Modifications,” 2026. environmentalhealthsafetybrief.sidley.com
- 2.U.S. Army Corps of Engineers (EPA archive), “Plantation Landing Resort, Inc. Permit Elevation Guidance on the Section 404(b)(1) Guidelines,” n.d. epa.gov
- 3.U.S. Fish and Wildlife Service, “Wetlands Data Limitations, Exclusions and Precautions,” n.d. fws.gov
- 4.Minnesota Board of Water and Soil Resources, “Delineation Manuals,” n.d. bwsr.state.mn.us
- 5.U.S. Environmental Protection Agency, “WOTUS Supplemental Notice of Proposed Rulemaking Fact Sheet,” 2026. epa.gov
- 6.U.S. Army Corps of Engineers and U.S. Environmental Protection Agency, “Compensatory Mitigation for Losses of Aquatic Resources; Final Rule,” 2008. govinfo.gov
- 7.National Agricultural Law Center, “States’ Wetlands Permitting Statutes,” n.d. nationalaglawcenter.org
- 8.E&E News, “Three years after Sackett, state wetland laws a mixed bag,” 2026. eenews.net
- 9.Williams Mullen, “Are Jurisdictional Determinations Valid Only Five Years?,” n.d. williamsmullen.com
- 10.Bracewell LLP via Mondaq, “Federal Agencies Propose Additional Revisions to the Definition of Waters of the United States,” 2026. mondaq.com
- 11.Mondaq, “Army Corps Rolls Out Guidance to Help Determine Jurisdiction,” 2016. mondaq.com
- 12.Ecosystem Marketplace, “How the 2008 Mitigation Rule Cut the Cost of Environmental Compliance and Built a Restoration Economy,” 2018. ecosystemmarketplace.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Environmental & physical risk
- Slope, Soils and Geotechnical Review for Data Center Sites
- Natural Hazard Risk in Data Center Site Selection
- Phase I Environmental Site Assessments for Data Center Land
- Cultural Resources and Section 106: What Data Center Developers Need to Know
- Do Data Center Backup Generators Need an Air Permit?
- Seismic Risk and Data Center Site Selection: Hazard Maps, Design Categories and Liquefaction
- Karst, Sinkholes and Data Center Sites: How to Screen and Investigate the Ground
- Tornado and High-Wind Risk for Data Centers: ASCE 7-22 Tornado Loads, Risk Categories and Siting
- Wildfire Risk and Data Center Siting: Hazard Maps, Power Shutoffs and WUI Codes
- Hurricane and Storm Surge Risk for Data Center Sites: SLOSH Maps, Coastal Flood Zones and Grid Outages
- Brownfield Cleanup Programs and Liability Protections for Data Center Sites
- Phase II Environmental Site Assessments for Data Center Land: When You Need One and What It Costs
- Tree Clearing and Forest Conservation Rules for Data Center Sites
- Climate Change, Future Heat and Data Center Site Risk
- Data Center Emissions and ESG Reporting: What It Means for Site Selection
- Diesel Fuel Storage and SPCC Plans at Data Centers
Guide 2 of 21 in Environmental & physical risk · all 242 guides · glossary · calculators