Key takeaways
- The SPCC capacity test is more than 1,320 gallons aboveground or more than 42,000 gallons completely buried; containers under 55 gallons are not counted.1
- Facilities with 10,000 gallons or less aboveground and a clean discharge history can self-certify as qualified facilities; a large data center usually needs a professional engineer’s certification instead.25
- Bulk storage containers need secondary containment for the entire capacity of the largest single container plus sufficient freeboard for precipitation; the common 110% figure is a design convention, not the regulation.36
- Since EPA’s 2015 underground storage tank rule, buried tanks serving emergency generators are no longer deferred from release detection.7
- States add their own layer: Virginia, for example, registers aboveground tanks over 660 gallons and adds pollution prevention and contingency plan duties at 25,000 gallons.4
- Fuel volumes at AI campuses are large: a 2025 Google proposal in Fort Wayne, Indiana sought 179 tanks of 6,000 gallons each, more than 1 million gallons.8
01Why diesel storage is a site question
Most data centers still rely on diesel generators for backup power, and each generator carries fuel in a base (belly) tank, often supplemented by day tanks or bulk tanks. Fuel storage is usually treated as a design detail, but it has site consequences: tank pads and containment take space in the equipment yard, drainage must be designed around possible spills, and setbacks from streams, wells and property lines can constrain where the generator yard goes.
The scale is no longer small. In 2025, Google sought an Indiana permit modification for a Fort Wayne data center to add 179 diesel generators with 179 fuel tanks of 6,000 gallons each, more than 1 million gallons of storage, and generators capable of up to 527.52 MW if all ran.8 The Indiana Department of Environmental Management approved the request in April 2026, taking the site from 34 to 179 backup generators.9 At that size, oil spill rules, state tank programs and fire codes all apply at once, and the air permit for the same generators is a separate track covered in air permits for data center generators.
Fig. 1One proposed AI campus generator fleet
- diesel generators and fuel tanks
- 179
- capacity of each tank
- 6,000 gal
- total diesel storage capacity
- 1M+ gal
- combined generator capacity
- 527.52 MW
How much fuel to store is an engineering and contract decision, set by runtime targets, redundancy such as N+1 or 2N, and refueling assumptions. See backup generators and fuel storage sizing. This guide covers the rules that follow from that choice.
02When the SPCC rule applies
EPA’s SPCC rule, at 40 CFR part 112, applies to non-transportation facilities that meet two tests. The first is capacity: more than 1,320 U.S. gallons of aboveground oil storage, or more than 42,000 gallons of completely buried storage.1 Containers smaller than 55 gallons and permanently closed containers are left out of the count, and completely buried tanks that are subject to the federal underground storage tank technical rules are excluded.1
The second is location: whether the facility could reasonably be expected to discharge oil in harmful quantities to navigable waters or adjoining shorelines. EPA’s guidance says this judgment must be made as if manmade features such as dikes or other structures that might contain oil were absent.1 In practice, a site with drainage ditches, storm sewers or streams nearby will rarely be able to rule itself out, and the determination should be documented by the engineer.
Fig. 2Does a data center need an SPCC plan?
- 01
Count containers
Every oil container of 55 gallons or more, including belly tanks.
- 02
Apply capacity test
Over 1,320 gal aboveground or over 42,000 gal buried?
- 03
Test discharge path
Could oil reach navigable waters, ignoring dikes?
- 04
Check qualified status
10,000 gal or less aboveground and clean history?
- 05
Prepare the plan
Self-certified if qualified; otherwise PE-certified.
Oil-filled electrical gear matters too. EPA defines oil-filled operational equipment as equipment that includes an oil storage container whose oil supports only the function of the device, and it offers an optional alternative to general secondary containment for qualified equipment, conditioned on an inspection or monitoring program and a contingency plan.10 Ask the engineer how on-site transformers are counted and contained in the plan.
03Who certifies the plan, and how often it changes
The rule lets small facilities prepare their own plans. A qualified facility has total aboveground oil storage of 10,000 gallons or less and, in the three years before certification, no single discharge to navigable waters over 1,000 gallons and no two discharges over 42 gallons each within any 12-month period.2 If no aboveground container exceeds 5,000 gallons, it is a Tier I facility and can use the rule’s template; otherwise it is Tier II and self-certifies a full plan.2 EPA notes that some states limit plan certification to professional engineers.2
A campus with dozens of generators will usually exceed 10,000 gallons, so its plan must be reviewed and certified by a licensed professional engineer familiar with the facility.5 The plan must be reviewed at least once every five years, and amended within six months of a change in design, construction, operation or maintenance that materially affects the potential for a discharge; technical amendments also need PE certification.5 For a phased campus, every new building and generator block is likely such a change.
| Threshold | What it triggers |
|---|---|
| Over 1,320 gal aboveground, or over 42,000 gal buried | SPCC plan required, if a discharge to navigable waters is reasonably expected1 |
| 10,000 gal or less aboveground | May qualify to self-certify (Tier I or Tier II)2 |
| Any container over 5,000 gal | Tier II rather than Tier I, if otherwise qualified2 |
| 1 million gal or more | Facility Response Plan, if one of the substantial harm criteria also applies11 |
A separate Facility Response Plan applies at 1 million gallons or more when the facility also lacks adequate secondary containment, has had a reportable discharge of 10,000 gallons or more in the past five years, or could harm a drinking water intake or sensitive environments; a lower 42,000-gallon trigger applies only to facilities that transfer oil over water to or from vessels.11 Few data centers approach that volume, but the largest AI campuses now can.8
04Secondary containment and tank design
For bulk storage containers, 40 CFR 112.8(c)(2) requires a secondary means of containment for the entire capacity of the largest single container plus sufficient freeboard to contain precipitation.3 Containers can be protected individually or share a common collection area designed into site drainage, and permanently manifolded tanks can be treated as one container for sizing.3
The familiar 110% sizing rule is not in the regulation. EnSafe notes it is a remnant of design practice from before the 2002 rule amendments, and that EPA considered but did not adopt a 25-year, 24-hour storm as the freeboard standard; in high-rainfall regions such as the Gulf Coast, a 110% basin may still lack enough freeboard.6 Engineers should size uncovered containment to local rainfall, which ties into the campus stormwater design and any NPDES permit for releasing accumulated rainwater.
Most generator belly tanks are factory-built double-wall steel units. UL 142 covers standard double-wall tanks for flammable and combustible liquids, while UL 2085 tanks add fire-resistant construction that earns a two-hour rating and are treated as protected tanks.12 Installation then follows the fire code and the NFPA 30 and NFPA 110 editions the local authority has adopted, which govern items such as venting and placement. UK permit filings show the same approach at hyperscale: an Amazon application for a data center at Didcot describes containerized, self-bunded belly tanks sized to hold 110% of their contents.13
05Underground tanks, state programs and fire codes
The SPCC rule is only the federal floor. Three other layers often apply to the same fuel.
Fig. 3Rules that can apply to the same diesel tank
- 01Federal SPCC rulePlan, containment, inspections (40 CFR part 112)
- 02Federal UST ruleBuried tanks: release detection, including generator tanks
- 03State tank programRegistration, pollution prevention, contingency plans
- 04Fire codeNFPA 30, tank listing, venting, location
- 05Site permit conditionsAir permit, stormwater and local approvals
Underground storage tanks
EPA’s 1988 underground storage tank rule deferred tanks storing fuel solely for emergency generators from release detection, because they were often at remote, rarely visited sites. The 2015 revisions removed that deferral, since improved monitoring methods made release detection practical.7 Buried tanks therefore bring federal or state UST obligations, while aboveground tanks fall under SPCC and state AST rules.
State aboveground tank rules
States vary widely. Virginia, for example, requires registration of facilities with more than 1,320 gallons of oil in aggregate or any individual tank over 660 gallons, and applies pollution prevention and oil discharge contingency plan requirements at 25,000 gallons in a tank or in aggregate.4 The University of Virginia’s compliance office notes that emergency generator base or belly tanks are excluded from Virginia’s aggregate calculation, which can keep a generator-only site below the higher tiers.14 Check the specific state program early, because thresholds, exclusions and inspection duties differ.
06Fuel choice: renewable diesel and storage
Some operators are replacing fossil diesel with hydrotreated vegetable oil (HVO), a renewable diesel. Kao Data moved the generators at its Harlow, U.K. campus to HVO, starting by replacing 45,000 liters of diesel and planning for more than 750,000 liters at full build-out.15 A 2025 Rolls-Royce and Microsoft paper on Singapore data centers found HVO two to three times as costly as fossil diesel and cited supply and feedstock consistency as barriers.16
For spill and tank rules, HVO is still an oil stored in the same tanks, so the SPCC and state requirements do not go away. Its main effects are on Scope 1 emissions reporting and on fuel management, such as supplier claims about reduced microbial growth during long idle periods.15 For the reporting side, see data center emissions and ESG reporting.
07What to check at the site stage
- 01Estimate total aboveground fuel and oil capacity at full build-out, not just phase one, including belly tanks, day tanks, bulk tanks and oil-filled equipment.
- 02Map drainage paths from the generator yard to the nearest stream, ditch or storm sewer, assuming no containment, to inform the navigable waters determination.
- 03Confirm the state tank program’s registration and plan thresholds and any exclusions for generator tanks.
- 04Decide between aboveground and buried bulk storage early, since buried tanks bring UST release detection duties.
- 05Size containment and freeboard to local rainfall and route accumulated water through the stormwater design.
- 06Coordinate tank locations with the fire code official, the air permit and the site plan review.
A Phase I environmental site assessment of the land will also look for old tanks and past releases, which can complicate a new tank farm. If you want a parcel screened for drainage, setbacks and permitting factors before design starts, you can get a site reviewed.
Common questions
Do data center generator belly tanks count toward SPCC capacity?
Generally yes: the rule counts aboveground oil containers of 55 gallons or more, and a generator base tank is such a container.1 Have the engineer confirm how each tank and piece of oil-filled equipment is counted, because state programs can treat belly tanks differently, as Virginia does.14
Can a data center self-certify its SPCC plan?
Only if it is a qualified facility, meaning 10,000 gallons or less of aboveground oil storage and no qualifying discharges in the prior three years.2 Larger facilities need a plan certified by a professional engineer, and some states require PE certification in all cases.25
Is 110% secondary containment required?
The federal rule requires containment for the entire capacity of the largest single container plus sufficient freeboard for precipitation, not a fixed percentage.3 The 110% figure is a common design practice that may not be enough where heavy rainfall is frequent.6
How often does an SPCC plan need to be updated?
It must be reviewed at least every five years and amended within six months of any change that materially affects the potential for a discharge.5 On a phased campus, adding buildings and generators will usually require amendments.
Do underground diesel tanks for generators need leak detection?
Yes, under EPA’s 2015 revisions, emergency generator UST systems are no longer deferred from release detection requirements.7 Many states run their own approved UST programs, so check the state rules as well.
Notes
- 1.U.S. Environmental Protection Agency, “SPCC Guidance for Regional Inspectors, Chapter 2: Applicability,” 2014. 19january2021snapshot.epa.gov
- 2.U.S. Environmental Protection Agency, “Is My Facility a “Qualified Facility” under the SPCC Rule?,” n.d. epa.gov
- 3.U.S. Environmental Protection Agency, “Secondary Containment for Each Container under SPCC,” n.d. epa.gov
- 4.Virginia Administrative Code, “9VAC25-91: Facility and Aboveground Storage Tank (AST) Regulation,” n.d. law.lis.virginia.gov
- 5.J. J. Keller & Associates, “Oil SPCC Plan Review and Amendment,” n.d. jjkellercompliancenetwork.com
- 6.EnSafe, “SPCC Plans: Are You Providing Sufficient Freeboard for Secondary Containment?,” n.d. ensafe.com
- 7.U.S. Environmental Protection Agency, “Emergency Power Generator UST System Requirements,” 2022. epa.gov
- 8.21Alive News, “IDEM Hosts Public Hearing on Proposed Diesel Generator Expansion at Fort Wayne Google Data Center,” 2025. 21alivenews.com
- 9.21Alive News, “IDEM Approves Google’s Request for Additional Diesel Generators at Fort Wayne Data Center,” 2026. 21alivenews.com
- 10.U.S. Environmental Protection Agency, “Secondary Containment for Oil-Filled Operational Equipment,” n.d. 19january2021snapshot.epa.gov
- 11.U.S. Environmental Protection Agency, “40 CFR Part 112, Appendix C, Attachment C-II: Certification of the Applicability of the Substantial Harm Criteria,” 2013. epa.gov
- 12.University System of Georgia, “Generator Fuel Storage Systems,” n.d. usg.edu
- 13.Environment Agency, “Didcot Data Centre Permit Application: Non-Technical Summary,” 2025. consult.environment-agency.gov.uk
- 14.University of Virginia Pollution Prevention, “State Regulated ASTs,” n.d. pollutionprevention.virginia.edu
- 15.Cambridge Network, “The Road to Net Zero: Kao Data Becomes First UK Data Centre to Transition from Diesel to Renewable HVO Fuel,” n.d. cambridgenetwork.co.uk
- 16.Rolls-Royce Power Systems and Microsoft, “Unlocking the Potential of Low Carbon Fuels,” 2025. mylearning.rolls-royce.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Environmental & physical risk
- Can You Build a Data Center in a Floodplain?
- Wetlands and Data Center Development: Delineation, Permits and Buildable Land
- Slope, Soils and Geotechnical Review for Data Center Sites
- Natural Hazard Risk in Data Center Site Selection
- Endangered Species Review for Data Center Sites: What Triggers It and What to Check
- Cultural Resources and Section 106: What Data Center Developers Need to Know
- NEPA Review for Data Centers: When It Applies and What Changed in 2025
- Seismic Risk and Data Center Site Selection: Hazard Maps, Design Categories and Liquefaction
- Karst, Sinkholes and Data Center Sites: How to Screen and Investigate the Ground
- Tornado and High-Wind Risk for Data Centers: ASCE 7-22 Tornado Loads, Risk Categories and Siting
- Wildfire Risk and Data Center Siting: Hazard Maps, Power Shutoffs and WUI Codes
- Hurricane and Storm Surge Risk for Data Center Sites: SLOSH Maps, Coastal Flood Zones and Grid Outages
- Brownfield Cleanup Programs and Liability Protections for Data Center Sites
- Phase II Environmental Site Assessments for Data Center Land: When You Need One and What It Costs
- Tree Clearing and Forest Conservation Rules for Data Center Sites
- Climate Change, Future Heat and Data Center Site Risk
Guide 21 of 21 in Environmental & physical risk · all 242 guides · glossary · calculators
