BlackForge Data Centers

Environmental & physical risk

Phase II Environmental Site Assessments for Data Center Land: When You Need One and What It Costs

A Phase II environmental site assessment samples soil, groundwater or soil gas to confirm or rule out the contamination a Phase I flagged, following a scientific, plan-driven process described in ASTM E1903-19.12 It is needed when a Phase I finds recognized environmental conditions that could affect price, liability or layout, and it typically takes about 6–12 weeks.3 Public sources put costs from roughly $10,000 to more than $100,000, depending on the number of areas, media and analyses.4

Last reviewed · 8 min read · BlackForge Data Centers

Key takeaways

  • A Phase II is targeted: it tests specific concerns from the Phase I, not the whole property.1
  • ASTM E1903-19 builds the work around a conceptual site model and a sampling rationale, then checks the model against the data.2
  • PFOA and PFOS have been CERCLA hazardous substances since July 2024, a designation EPA kept in 2025 and the D.C. Circuit upheld in August 2026, which pulls PFAS into many scopes.57
  • Results are usually screened against risk-based values such as EPA’s Regional Screening Levels; exceeding a screening level calls for a closer look, not automatically for cleanup.89
  • Plan on about 6–12 weeks, and make sure the due diligence period and site access rights allow for drilling permits, lab time and a second round if needed.310

01What a Phase II ESA is

A Phase I ESA is a records review, site visit and interviews. It identifies where contamination may be but does not test for it. A Phase II ESA is the follow-up investigation: it collects and analyzes samples to verify the presence or absence of suspected contamination in the potential source areas the Phase I identified.1

The governing practice is ASTM E1903-19, issued in November 2019.2 It covers hazardous substances, pollutants, petroleum products and certain other substances, and it describes a process based on the scientific method intended to characterize conditions in an objective, representative and reproducible way.2 Unlike the Phase I standard, E1903 does not prescribe a fixed checklist. The scope is negotiated between the user and the environmental professional and documented in a statement of objectives.

That flexibility cuts both ways. A Phase II can be a few soil borings around one farm fuel tank or a multi-month program across a former industrial plant. The questions a buyer brings to it, and the decisions it must support, determine its size.

02When data center land needs a Phase II

The usual trigger is a Phase I finding of a recognized environmental condition that matters to the deal. On data center land, common triggers include:

  • Underground or aboveground fuel tanks at farmsteads, equipment yards or former fuel stations.
  • Former industrial, rail, landfill or power generation use, including ash and fill areas on retired plant sites.
  • Old electrical equipment, chemical storage or burn and dump areas.
  • Upgradient sources such as dry cleaners or industrial plants where vapor or groundwater could migrate onto the site.
  • Historical use of firefighting foam, plating, paper or textile processes, or landfills, which raise PFAS questions.5

PFAS deserve a specific mention. EPA’s rule designating PFOA and PFOS as CERCLA hazardous substances took effect on July 8, 2024, and practitioners note that the designated substances should now be evaluated in Phase I reports to preserve CERCLA defenses, which can lead to Phase II soil and groundwater testing.5 EPA announced on September 17, 2025 that it would retain the designation, and on August 18, 2026 the D.C. Circuit denied the petitions challenging it.67

Fig. 1Deciding whether a Phase I finding needs sampling

Minor ← Effect on the project → Major

Targeted screening

Weak evidence near a planned building or pond: a few borings to close it out.

Phase II before pricing

Strong evidence where it would change layout, cost or liability.

Document and monitor

Weak evidence in an area left undeveloped; note it in the record.

Scope by deal terms

Strong evidence in a minor area; sample or carve out with an indemnity.

Weak ← Strength of Phase I evidence → Strong

A way to frame the decision, not a rule; counsel and the environmental professional should agree on scope.

03How the ASTM E1903 process works

E1903 organizes a Phase II as a sequence of questions and tests. The conceptual site model, a working picture of where contaminants came from, how they move and who or what could be exposed, is built before sampling and revised afterward.2 The sampling plan is tailored to the concerns from the Phase I and to the property’s characteristics, and it includes protocols for field handling, sample preservation and transport so the data hold up.1

Fig. 2The Phase II process under ASTM E1903-19

  1. 01

    Define the question

    Statement of objectives tied to Phase I findings.

  2. 02

    Review information

    Prior reports, site history, geology and utilities.

  3. 03

    Conceptual site model

    Sources, pathways and receptors for each area.

  4. 04

    Sampling plan

    Locations, media, analyses and rationale.

  5. 05

    Field sampling

    Borings, wells or soil gas probes; chain of custody.

  6. 06

    Validate and report

    Test the model against the data; state conclusions.

Simplified from summaries of the standard’s sections on scope, assessment activities, interpretation and reporting.21

Regulatory context shapes the scope. Site-specific state and federal requirements often influence the extent of the investigation, so a Phase II intended to support entry into a state cleanup program may need more samples, specific methods or a state-approved laboratory.1 If the property may end up in a voluntary cleanup program, tell the consultant at the start; see our guide to brownfield cleanup programs and liability protections.

04Sampling methods and what the results are compared to

Common Phase II sampling approaches
MediumTypical methodUsed for
SoilDirect-push or drilled borings with samples at set depthsTank areas, spills, fill, stained ground
GroundwaterTemporary or permanent monitoring wellsPlumes from on-site or upgradient sources
Soil gasSoil gas probes; sub-slab samples under buildingsVolatile chemicals and vapor intrusion11
MaterialsSamples of fill, ash, sediment or residuesFormer industrial and plant sites

Sampling design matters as much as the number of samples. EPA’s quality guidance describes judgmental sampling, where locations are chosen by professional knowledge, and systematic or grid sampling, where points follow a set pattern from a random start and can be used to delineate boundaries and search for hot spots.12 Most data center Phase IIs use judgmental locations around known features, and add a grid only where the source is diffuse, such as a fill area.

Vapor needs its own logic. EPA’s 2015 vapor intrusion guide recommends developing a conceptual site model when vapor-forming chemicals lie beneath or near buildings and weighing multiple lines of evidence, including groundwater and soil gas data. It also notes that petroleum hydrocarbons degrade rapidly under aerobic conditions, which limits their potential for vapor intrusion.11

Laboratory results are then screened. EPA’s Regional Screening Levels are generic, risk-based values for residential and industrial soil and tap water, calculated at a target cancer risk of 1E-06 and target hazard quotients of 1.0 and 0.1.8 Practitioners describe them as values EPA relies on to help determine whether remediation is necessary.9 Many states publish their own screening levels. A data center is an industrial or commercial use, so industrial values often apply, but using them may require a recorded land use restriction.

05Costs and timing

Costs scale with the number of areas of concern, the media sampled, the analyte list and whether wells are needed. Oklahoma’s brownfields program puts Phase II costs at $10,000 to more than $100,000 for sites not enrolled in its program.4 An environmental consultancy describes $10,000 to $30,000 as the usual range, stretching to $100,000 or more on complex sites.13 PFAS analysis, multiple groundwater rounds and large assemblages push toward the top.

Fig. 3Published Phase II cost ranges

  • Typical scope (consultancy)$10k–$30k
  • Complex scope (consultancy)up to $100k+
  • State program range$10k–$100k+
0255075100USD thousands
Ranges from a state brownfields program and a consultancy; site-specific quotes vary widely.413

On timing, the City of Longmont, Colorado estimates 6–12 weeks to complete a Phase II.3 Fieldwork itself is often a few days. One public contract in South Bend, Indiana, for example, called for drilling and sampling within two calendar days, laboratory analysis within 14 days of sampling, and a draft report within 14 days after the lab results.14 Drilling permits, where required, add time and cost and should be built into the schedule.10

Fig. 4Illustrative Phase II schedule

Illustrative
  • Scope, access, permits
  • FieldworkBorings, wells, soil gas
  • Laboratory analysis
  • Draft report
  • Review and final
02.557.510weeks
Illustrative example for a single-round investigation; a second groundwater round or PFAS work can add weeks.

06What the results mean for a land deal

A Phase II usually ends in one of four places: no significant impact, so the condition is closed in the record; limited impact that can be managed during construction; impact that needs more delineation; or contamination that calls for a cleanup program, a price change, an indemnity or walking away.

Finding contamination does not by itself end federal protection. EPA’s bona fide prospective purchaser provision allows a party to acquire property with knowledge of contamination, provided it performs All Appropriate Inquiries and meets continuing obligations such as taking reasonable steps to stop continuing releases and prevent threatened ones.15 Knowledge does change what those reasonable steps are, so the construction plan should reflect the Phase II data.

For data center sites, the Phase II often shapes layout as much as price. Large building pads, deep utility trenches, stormwater ponds and substation foundations all disturb soil. Mapping impacted areas lets the design team keep data halls and ponds off them, plan soil handling and dewatering, and decide whether vapor mitigation is needed in occupied spaces. Coordinate the Phase II with the geotechnical investigation, since both involve borings and can sometimes share mobilization.

07Practical steps for buyers and landowners

  1. 01Secure access rights for drilling and well installation in the option or purchase agreement, including restoration duties.
  2. 02Size the diligence period for a 6–12 week Phase II plus one possible follow-up round.3
  3. 03Ask the consultant for a written statement of objectives, the conceptual site model and the sampling rationale for each area.2
  4. 04Decide early whether PFAS analysis is in scope, given the CERCLA designation.5
  5. 05Agree on which screening levels apply and whether the results may be submitted to a state program.
  6. 06Ask for a schedule that separates permits, fieldwork, lab time and reporting.14

Our guide to due diligence periods and purchase contingencies covers how to build environmental time into a contract, and our methodology explains where environmental screening fits in a site review. If a parcel’s Phase I raised questions, you can get a site reviewed to see whether power, water and layout justify the cost of sampling. Confirm scope and conclusions with a qualified environmental professional and counsel.

Common questions

What is the difference between a Phase I and a Phase II ESA?

A Phase I reviews records, inspects the site and interviews people to identify likely contamination, without sampling. A Phase II collects and analyzes soil, groundwater or soil gas samples to verify whether the suspected contamination is present.1

Is a Phase II required to buy land?

No law requires one for every purchase. It is triggered by Phase I findings, lender requirements or the buyer’s own risk tolerance, and the scope is agreed between the user and the environmental professional under ASTM E1903.2

How much does a Phase II environmental site assessment cost?

Published ranges run from about $10,000 to more than $100,000.413 The number of areas, wells, analytes and sampling rounds drives the cost, so get a quote tied to a written sampling plan.

How long does a Phase II take?

A common planning estimate is 6–12 weeks.3 Fieldwork is often a few days, but permits, laboratory turnaround and report review take most of the time, and a second groundwater round can extend it.1410

Should a Phase II test for PFAS?

Where site history suggests firefighting foam, plating, paper or textile operations, or landfills, increasingly yes, because PFOA and PFOS are CERCLA hazardous substances and practitioners recommend evaluating them in due diligence.57 Confirm the analyte list and laboratory methods with your consultant.

Notes

  1. 1.Intertek, “ASTM E1903: Phase II Environmental Site Assessments (ESA),” n.d. intertek.com
  2. 2.ASTM International, “ASTM E1903-19: Standard Practice for Environmental Site Assessments: Phase II Environmental Site Assessment Process,” 2019. store.astm.org
  3. 3.City of Longmont, Colorado, “Definitions of Assessments, Surveys and Plans,” 2024. longmontcolorado.gov
  4. 4.Oklahoma Corporation Commission, “Brownfields Fact Sheet: Phase II Environmental Site Assessment,” n.d. oklahoma.gov
  5. 5.Trinity Consultants, “Rule Affects Due Diligence for Property Transactions and Liability for Historic and Future Releases of PFAS,” n.d. trinityconsultants.com
  6. 6.Bergeson & Campbell, “EPA Will Retain CERCLA Hazardous Substance Designation for PFOA, PFOS, Will Develop CERCLA Section 102(a) Framework Rule,” 2025. lawbc.com
  7. 7.Jones Day, “D.C. Circuit Upholds EPA Designation of PFOA and PFOS Under CERCLA,” 2026. jonesday.com
  8. 8.U.S. Environmental Protection Agency, “Regional Screening Levels (RSLs): Generic Tables,” n.d. epa.gov
  9. 9.Jenner & Block, “U.S. EPA Updates Regional Screening Levels to Add Five New PFAS Chemicals,” n.d. jenner.com
  10. 10.Millman National Land Services, “Phase 2 Environmental Site Assessments,” n.d. millmanland.com
  11. 11.U.S. Environmental Protection Agency, “OSWER Technical Guide for Assessing and Mitigating the Vapor Intrusion Pathway From Subsurface Vapor Sources to Indoor Air,” 2015. 19january2017snapshot.epa.gov
  12. 12.U.S. Environmental Protection Agency, “Selecting a Sampling Design,” n.d. epa.gov
  13. 13.Fehr Graham, “Phase II Environmental Site Assessment Cost,” n.d. fehrgraham.com
  14. 14.City of South Bend, Indiana, “Phase II environmental site assessment scope of services (public records document),” n.d. docs.southbendin.gov
  15. 15.U.S. Environmental Protection Agency, “Bona Fide Prospective Purchasers,” n.d. epa.gov

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Related guides

More in Environmental & physical risk