Key takeaways
- Maryland’s Forest Conservation Act applies to most subdivision, grading and sediment control applications on 40,000 square feet or more, and requires a forest stand delineation and forest conservation plan.14
- Maryland’s 2023 Forest Preservation and Retention law replaced the state’s no-net-loss forest goal with targets for increasing forest and tree canopy, tightened clearing and reforestation rules, and mostly took effect July 1, 2024; counties can adopt stricter local rules.56
- The northern long-eared bat became federally endangered on March 31, 2023, across a 37-state range, which ended the old 4(d) rule flexibility for tree removal.27
- In Virginia and Maryland, projects that may affect the bat have commonly faced an April 1 to November 14 no-clearing window unless further consultation or negative surveys lift it.89
- Local zoning and proffers can stop clearing even when state agencies find no violation, as a 2025 Stafford County, Virginia court fight over timbering near a proposed data center showed.310
01Why tree clearing is a site selection issue
A data center campus needs large, flat, contiguous pads, which on wooded land means clearing most of the trees across the building and yard footprint. Prince William County watershed staff, commenting on a proposed data center corridor in Virginia, wrote that existing data center development showed that extensive mass grading and the nearly wholesale clearing and flattening of large parcels is the norm.11 That scale is why forest rules that barely touch a subdivision can reshape a campus.
The rules come from different authorities and run on different clocks. A state forest conservation law affects how much forest must be retained or replaced, and therefore the buildable acreage. Local ordinances and rezoning conditions affect what may be cut and when a permit issues. Federal wildlife law affects the season in which trees can lawfully come down where listed species may roost. A site can clear all three, or it can lose months to one of them.
Forest cover also shapes local politics. Fairfax County’s Tree Commission told county officials in 2024 that data centers often place far greater stress on environmental factors than other commercial or residential uses because of their size, and recommended ending by-right zoning for them.12 Expect tree loss to come up in community engagement and at rezoning hearings.
02Maryland’s Forest Conservation Act: the leading state model
Maryland’s Forest Conservation Act is the most developed state framework a data center developer is likely to meet. The Maryland Department of Natural Resources describes its purpose as minimizing the loss of forest during land development by making the identification and protection of forests and other sensitive areas part of site planning.1 It applies to any activity requiring an application for a subdivision, grading permit or sediment control permit on an area of 40,000 square feet or more, and DNR’s 2026 model ordinance defines a development project the same way.14
Two documents drive compliance. The forest stand delineation maps existing forest stands, specimen trees and sensitive areas. The forest conservation plan then shows how the project retains forest and handles priority areas such as nontidal floodplains, streams and their buffers, steep slopes and critical habitat.1 Clearing, afforestation and reforestation thresholds depend on the net tract area, the land use category, existing forest cover and the area proposed for clearing.1
Fig. 1Forest Conservation Act review in Maryland
- 01
Applicability
Subdivision, grading or sediment control permit on 40,000 sq ft or more.
- 02
Stand delineation
Map forest stands, specimen trees and sensitive areas.
- 03
Conservation plan
Retain priority areas; set clearing and planting quantities.
- 04
Mitigation
Afforestation or reforestation, or options the program allows.
- 05
Protection
Retained and planted forest protected over the long term.
The Act is administered by DNR’s Forest Service but implemented locally: counties and municipalities with their own programs review plans, and DNR reviews them where no local agency does.1 That local layer matters because local programs can go further than the state minimum, which is why two Maryland sites with the same forest cover can carry different obligations.
03Maryland’s 2023 changes and county variation
In 2023, the General Assembly passed HB 723, “Natural Resources – Forest Preservation and Retention.” According to the legislature’s fiscal note, it replaced the no-net-loss outcome in the state’s forest policy with measured increases in forest and tree canopy acreage, while letting local jurisdictions propose alternative measures that still achieve no net loss within their borders.5 Most provisions took effect July 1, 2024. The law added restrictions on forest clearing, raised the reforestation required when forest is cleared, and grandfathered certain plans approved before July 1, 2024.5
Counties supported the forest goals but asked for flexible, implementable rules, a reminder that much of the burden falls on local review staff.13 Local programs also change on their own schedule. Montgomery County adopted amendments effective April 3, 2023 that raised forest conservation and afforestation thresholds for several zoning categories, and grandfathered projects only if a preliminary or final forest conservation plan had been submitted before that date.6
- Confirm which program reviews the site: county, municipality or DNR.1
- Check whether a plan already approved for the parcel is grandfathered under the 2023 law or a local amendment.56
- Ask how the program treats priority areas such as floodplains, stream buffers and steep slopes, which often overlap with land the project wanted for stormwater or roads.1
These details belong in the due diligence period. A forest conservation plan affects grading, stormwater management and the site plan, so a late surprise can force a redesign. For Maryland context beyond forests, see our Maryland site selection guide.
04Local tree ordinances, zoning and proffers
Outside Maryland, tree rules usually come from local zoning and land development codes rather than a statewide act. They take several forms: canopy retention or replacement requirements, specimen tree protection, buffer and landscaping standards, limits on commercial timbering in certain zones, and conditions attached to a rezoning. In Virginia, those conditions are often proffers that run with the land.
A 2025 dispute in Stafford County, Virginia shows how these local tools work. The county sued and obtained an emergency order halting timbering on land tied to a proposed 1,042-acre data center campus, alleging that the clearing violated A-2 Rural Residential zoning, where commercial tree cutting is prohibited, and a proffer meant to preserve trees unless their removal is essential.3 The state Department of Wildlife Resources found no violation of state environmental laws, and the Department of Forestry said it does not issue logging permits.3 After a hearing, the judge agreed that the clearing violated both the zoning ordinance and the associated proffers.10
State forestry agencies can also weigh in on rezonings without having permit authority. The Virginia Department of Forestry told Prince William County that a proposed data center corridor next to Conway Robinson Memorial State Forest would have a negative impact on forest resources.11 Comments like that feed directly into rezoning conditions on buffers, tree save areas and replanting.
05Bat and bird timing restrictions on clearing
For many wooded sites in the eastern half of the country, the binding constraint is not how many trees can be cut but when. The U.S. Fish and Wildlife Service published a final rule reclassifying the northern long-eared bat from threatened to endangered on November 30, 2022, and the change took effect March 31, 2023, after a 60-day delay so the Service could finish tools and guidance for landowners and industry.27 The species’ range covers 37 states, and the reclassification removed the 4(d) rule that had limited tree removal restrictions mainly to areas near known hibernacula and roost trees.2
Guidance used in Virginia and Maryland says that projects with a “may affect” or “likely to adversely affect” finding face a no-clearing window from April 1 to November 14 unless further consultation is conducted with the Service or the Army Corps of Engineers, and recommends running the Service’s rangewide determination key for every project.89 Negative acoustic or mist-net surveys can lift the restriction; one Virginia summary reports that negative results remain valid for five years for the Service, with a summer acoustic survey window of May 15 to August 15.9 A 2024 draft Service consultation framework was expected to narrow the restriction to the pup season (May 15 to July 31 in those states) in most cases; check whether it has been finalized before relying on it.9
Fig. 2Bat-related clearing windows in Virginia and Maryland
- Default no-clearing windowApril 1 to November 14 for may-affect projects
- Pup season (draft guidance)May 15 to July 31
- Summer acoustic surveysMay 15 to August 15
A second bat may add to this. The Service proposed listing the tricolored bat as endangered across parts of 39 states and the District of Columbia, citing white-nose syndrome as the main threat.14 Check its current status on the Service’s species pages before setting a clearing schedule. Our endangered species guide covers IPaC screening, Section 7 and Section 10.
Migratory birds are a moving target. On April 11, 2025, Interior’s Acting Solicitor restored the earlier legal opinion that the Migratory Bird Treaty Act prohibits only intentional take, with an exception for actions within the Southern District of New York, where a court had vacated that opinion in 2020.15 Harvard’s regulatory tracker notes that Interior later announced a review of wind energy bird mortality that appears to be in tension with that reading.16 Many state and local permits still impose nesting season clearing limits, so ask the reviewing agency.
06What to check on a wooded site
Forest and timing rules rarely kill a site outright, but they change acreage, cost and schedule. A short screen during the option period avoids most surprises.
Fig. 3Sample tree and forest screen of one parcel
Illustrative- WatchState forest lawForest conservation plan required; local thresholds are stricter.
- WatchPriority forestStream buffer forest along the west line must be retained.
- PassZoning and proffersIndustrial zoning; no tree save proffer recorded.
- FailBat habitatMay-affect finding; no clearing April through mid-November.
- WatchBird nesting limitsCounty grading permit adds a spring nesting condition.
- 01Map forest cover and estimate how much of it falls inside the planned pads, roads and yards, then net out retention requirements in your gross vs. buildable acreage math.
- 02Identify the reviewing program and pull its current ordinance, thresholds and grandfathering rules.16
- 03Read the zoning and any recorded proffers or conditions for tree save areas, buffers and timbering limits.3
- 04Run IPaC and the bat determination key early, and decide whether surveys or consultation are worth starting before closing.89
- 05Build the clearing window into the construction timeline so grading does not slip a full season.
If you want a second set of eyes on how forest cover affects a specific parcel, you can get a site reviewed.
Common questions
Does Maryland’s Forest Conservation Act apply to a data center?
Usually, yes. The Act applies to activities that need a subdivision, grading or sediment control permit on 40,000 square feet or more, which covers essentially every data center campus.1 The project will need a forest stand delineation and a forest conservation plan, reviewed by the county or municipal program or by DNR where there is no local program.1
When can trees be cleared on a site with northern long-eared bat habitat?
It depends on the project’s effect determination and the local Fish and Wildlife Service office. Guidance in Virginia and Maryland describes an April 1 to November 14 no-clearing window for projects that may affect the bat, unless consultation or negative surveys change it.89 Confirm the window for your site through IPaC and the field office.
Can a landowner timber a site before seeking a data center rezoning?
Sometimes, but it carries real risk. In Stafford County, Virginia, a court halted timbering on land tied to a proposed data center and later found that the clearing violated the zoning ordinance and proffers, even though state agencies found no violation of state environmental law.310 Check zoning, proffers and forestry exemptions with counsel first.
What did Maryland change in 2023?
The 2023 Forest Preservation and Retention law replaced the no-net-loss forest goal with targets for increasing forest and canopy, added clearing restrictions, raised reforestation requirements, and took effect mostly on July 1, 2024, with grandfathering for some earlier approved plans.5 Counties can also amend their own programs, as Montgomery County did in April 2023.6
Do migratory bird rules limit tree clearing?
Federal enforcement policy has changed several times. In April 2025, Interior restored the view that the Migratory Bird Treaty Act covers only intentional take, outside one federal judicial district.15 State and local permits may still carry nesting season limits, so confirm with the permitting agency.
Notes
- 1.Maryland Department of Natural Resources, “Forest Conservation Act,” n.d. dnr.maryland.gov
- 2.Mayer Brown, “Reclassification of the Northern Long-Eared Bat May Impact Project Development,” 2023. mayerbrown.com
- 3.Potomac Local News, “County Slaps Brakes on Timbering Near Proposed Data Center Site,” 2025. potomaclocal.com
- 4.Maryland Department of Natural Resources, “Model FCA Ordinance, 2026 Update,” 2026. dnr.maryland.gov
- 5.Maryland Department of Legislative Services, “Fiscal and Policy Note: HB 723, Natural Resources – Forest Preservation and Retention,” 2023. mgaleg.maryland.gov
- 6.Wetland Studies and Solutions, “Changes to MoCo Forest Laws Impact Development,” 2023. wetlands.com
- 7.U.S. Fish and Wildlife Service, “News Release: Service Extends Effective Date of Northern Long-Eared Bat Reclassification,” n.d. fws.gov
- 8.Prince William County, Virginia, “Endangered Status of the Northern Long-eared Bat: What Developers and Landowners Need to Know,” n.d. pwcva.gov
- 9.Wetland Studies and Solutions, “Batty April 2024,” 2024. wetlands.com
- 10.FXBG Advance, “Clearcutting on Hartwood District Parcels Was in Violation of Stafford Zoning Ordinance, Judge Rules,” 2025. fxbgadvance.com
- 11.Prince William Times, “State Forestry Officials Raise Concerns About Data Centers Near Conway Forest, Manassas Battlefield,” n.d. princewilliamtimes.com
- 12.Fairfax County Tree Commission, “Tree Commission Letter on Data Centers,” 2024. fairfaxcounty.gov
- 13.Maryland Association of Counties, “Counties Support Forest Conservation, Urge Implementable, Flexible Solutions,” 2023. conduitstreet.mdcounties.org
- 14.U.S. Fish and Wildlife Service, “Endangered Species Status for Tricolored Bat,” n.d. fws.gov
- 15.Hunton Andrews Kurth, “The Pendulum Swings Back Again on Prohibition of Incidental Take Under the Migratory Bird Treaty Act,” 2025. hunton.com
- 16.Harvard Law School Environmental and Energy Law Program, “Regulatory Tracker: Migratory Bird Treaty Act,” n.d. eelp.law.harvard.edu
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Environmental & physical risk
- Can You Build a Data Center in a Floodplain?
- Slope, Soils and Geotechnical Review for Data Center Sites
- Natural Hazard Risk in Data Center Site Selection
- Phase I Environmental Site Assessments for Data Center Land
- Cultural Resources and Section 106: What Data Center Developers Need to Know
- Do Data Center Backup Generators Need an Air Permit?
- NEPA Review for Data Centers: When It Applies and What Changed in 2025
- Seismic Risk and Data Center Site Selection: Hazard Maps, Design Categories and Liquefaction
- Karst, Sinkholes and Data Center Sites: How to Screen and Investigate the Ground
- Tornado and High-Wind Risk for Data Centers: ASCE 7-22 Tornado Loads, Risk Categories and Siting
- Wildfire Risk and Data Center Siting: Hazard Maps, Power Shutoffs and WUI Codes
- Hurricane and Storm Surge Risk for Data Center Sites: SLOSH Maps, Coastal Flood Zones and Grid Outages
- Brownfield Cleanup Programs and Liability Protections for Data Center Sites
- Phase II Environmental Site Assessments for Data Center Land: When You Need One and What It Costs
- Climate Change, Future Heat and Data Center Site Risk
- Data Center Emissions and ESG Reporting: What It Means for Site Selection
- Diesel Fuel Storage and SPCC Plans at Data Centers
Guide 18 of 21 in Environmental & physical risk · all 242 guides · glossary · calculators