Key takeaways
- The bona fide prospective purchaser (BFPP) defense lets a buyer acquire land with known contamination, provided it completes All Appropriate Inquiries before acquisition and meets continuing obligations afterward.61
- Since the 2018 BUILD Act, tenants can also qualify for BFPP protection, which matters for ground leases on former industrial land.6
- A Phase I under ASTM E1527-21 is the usual route to All Appropriate Inquiries; time-sensitive parts must be within 180 days of acquisition and the whole inquiry within one year.78
- State voluntary cleanup programs trade an agreed cleanup for a state release, and federal law generally bars EPA enforcement at eligible sites cleaned up under a qualifying state program, with exceptions.2
- EPA announced nearly $250 million in FY 2026 brownfield grants, but counties warned the program would run out of funding on September 30, 2026 without congressional action, and the main House reauthorization bill had cleared only a subcommittee by mid-2026.916
01Why brownfield liability matters for data center land
Former power plants, mills and industrial parks attract data center developers because they often come with high-voltage service, water, heavy roads and industrial zoning. A 2024 Pacific Northwest National Laboratory pamphlet on converting coal sites to data centers notes that many states run voluntary cleanup programs with flexible cleanup standards to speed remediation for brownfield purchasers.10 The trade-offs are covered in our greenfield vs. brownfield comparison and our guide to repurposing retired power plant and industrial sites.
The legal starting point is that the federal Superfund law, CERCLA, can make a current owner or operator liable for cleanup costs at a contaminated property even if it did not cause the contamination. The protections in this guide exist to break that link for buyers and tenants who investigate first and behave responsibly afterward. EPA describes the BFPP provision as allowing a party to purchase property with knowledge of contamination after performing All Appropriate Inquiries, and still be protected, if it meets the statutory criteria.6
The protections are layered and not interchangeable. The BFPP defense addresses federal CERCLA owner liability. State programs address state cleanup liability. Neither covers everything: EPA’s guidance is an exercise of its enforcement discretion and does not address liability under state law, claims by other federal agencies, or private-party claims.1 A deal on brownfield land needs all three questions answered before the due diligence period ends.
02The bona fide prospective purchaser defense, criterion by criterion
Congress created the BFPP defense in the 2002 Brownfields Amendments, and EPA’s 2019 “Common Elements” guidance explains how EPA reads the criteria shared by BFPPs, contiguous property owners and innocent landowners.1 The criteria split into threshold requirements, which must be met at closing, and continuing obligations, which last as long as the party owns or operates the property.
| Criterion | When | What it means for a data center buyer |
|---|---|---|
| Acquisition after January 11, 2002 | Threshold | Met by almost any current deal1 |
| All Appropriate Inquiries | Before acquisition | A current Phase I by a qualified environmental professional8 |
| No affiliation with a liable party | Threshold | Watch deals with the former operator or its affiliates1 |
| No disposal after acquisition | Continuing | Demolition and grading must not spread or dispose of contamination1 |
| Reasonable steps | Continuing | Stop continuing releases and prevent threatened future releases6 |
| Land use restrictions and cooperation | Continuing | Honor recorded controls; answer EPA information requests and subpoenas1 |
Two features catch buyers off guard. First, a BFPP can still face a windfall lien where EPA has spent unrecovered money cleaning up the site; the lien is capped at the lesser of EPA’s unrecovered costs or the increase in fair market value attributable to the cleanup.1 Second, the continuing obligations apply during construction. A data hall program that cuts into capped soil, dewaters contaminated groundwater or relocates fill without a plan can undermine the defense the buyer worked to establish.
The 2018 BUILD Act amended the BFPP definition to cover tenants directly. EPA describes three paths: the owner is a BFPP; the owner was a BFPP but lost that status through no fault of the tenant; or the tenant independently meets the BFPP criteria.6 Developers that prefer to lease rather than buy should still confirm that the lease terms and their own inquiries satisfy the statute.
03All Appropriate Inquiries and timing
All Appropriate Inquiries (AAI) is EPA’s rule at 40 CFR Part 312 defining what pre-acquisition investigation is needed. EPA recognized ASTM E1527-21 as satisfying AAI effective February 13, 2023, and stopped recognizing the older E1527-13 standard a year later.7 In practice, AAI means a Phase I environmental site assessment completed close to closing.
Timing is where otherwise sound diligence fails. EPA’s fact sheet explains that some parts of the inquiry must be conducted or updated within 180 days before acquisition and the rest within one year.8 The 180-day items include interviews, government records review, the site visit and the lien search. Data center land deals often run long option periods while power is studied, so a Phase I commissioned at signing may be stale at closing.
Fig. 1Securing BFPP status on a brownfield purchase
- 01
Phase I under E1527-21
Records, site visit, interviews, lien search.
- 02
Phase II if needed
Sampling to define the RECs the Phase I found.
- 03
Update before closing
Refresh 180-day components if the Phase I is aging.
- 04
Close and document
Keep the AAI record and affiliation facts on file.
- 05
Meet continuing duties
Reasonable steps, controls, cooperation for as long as you own.
AAI also governs grant-funded work: recipients of EPA brownfield grants must comply with the AAI rule when they use grant funds to assess properties.8 When the Phase I identifies recognized environmental conditions, the next step is usually a Phase II environmental site assessment, which turns suspicion into data a cleanup program can act on.
04State voluntary cleanup programs
Every state runs some form of voluntary cleanup or brownfield program. The details differ, but the bargain is similar: the applicant investigates and cleans up to standards the state approves, often risk-based standards tied to the planned use, and the state issues a no further action letter, certificate of completion or covenant not to sue.
Federal law gives these programs weight. Under CERCLA section 128(b), EPA’s enforcement under sections 106(a) and 107(a) is generally limited at eligible response sites addressed in compliance with a state response program, subject to specific exceptions, and the state must maintain a public record of sites and their use restrictions.2
Fig. 2Federal defense vs. state release
Self-executing
Federal BFPP defense
- No application or approval
- Depends on AAI and conduct
- Covers CERCLA owner liability
- Can be lost by breaching continuing duties
- Windfall lien still possible
Agency-issued
State VCP certificate
- Application, fees and agency review
- Cleanup to approved standards
- Release from state cleanup liability
- Often recorded and runs with the land
- Supports limits on EPA enforcement
Two examples show the range. In Texas, a party enters the program with a $1,000 application fee and at least a Phase I, and once the certificate of completion issues, non-responsible parties, including future lenders and landowners, are released from liability to the state for cleanup of the covered area.3 In Indiana, a certificate of completion is paired with a covenant not to sue from the governor, which by statute does not release liability to the federal government under federal law.11 Check the program in your state for fees, standards, review times and how use restrictions are recorded.
05EPA brownfield grants and the 2026 funding gap
EPA’s program offers multipurpose, assessment, revolving loan fund and cleanup grants.4 Cleanup grants require a 20 percent cost share, and the applicant must own the site.12 A private data center developer is therefore rarely the direct applicant. The usual route is a partnership in which a county, city, redevelopment authority or nonprofit holds the grant, or a loan from a revolving loan fund.
The 2021 infrastructure law temporarily enlarged the program. Haley & Aldrich reported that the FY 2026 competition offered up to 26 large cleanup grants of up to $4 million each, likely the last round of such large awards, with infrastructure law funds required to be obligated by September 30, 2026.13
Fig. 3EPA brownfield grants, FY 2026
- FY 2026 multipurpose, assessment and cleanup grants
- ~$250M
- state and local recipients
- 190+
- current authorized level
- $200M/yr
- proposed in H.R. 8739 for FY 2027–31
- $123.5M/yr
The National Association of Counties warned that, without congressional action, the program would run out of funding on September 30, 2026.9 In a July 2026 report, the Congressional Research Service counted three reauthorization bills in the 119th Congress: H.R. 6432, H.R. 8739 and S. 347.5 Smart Growth America described the effort as highly partisan, with H.R. 8739 proposing $123.5 million a year, below the current $200 million authorization.14 A House Energy and Commerce subcommittee advanced H.R. 8739 by voice vote as a compromise that would fund the grants through fiscal 2031.16 Haley & Aldrich noted that regular appropriations averaged about $160 million a year over the prior decade.13 With the September 30, 2026 deadline now past, confirm the program’s current funding status with EPA’s regional brownfields office before counting on a grant.
06How this plays out on data center deals
Retired power plant sites show how the pieces fit. The former Cheswick Generating Station in Springdale, Pennsylvania, retired in 2022, was remediated by its owner before a data center developer bought the 47.2-acre site for $14.3 million in November 2025.15 When the seller finishes cleanup before closing, the buyer’s questions shift from “how much will cleanup cost” to “what controls remain and what do they allow.”
Where cleanup is not finished, the structure matters more. Common approaches include:
- Seller completes cleanup and obtains the state certificate before closing, with the price reflecting the delay.
- Buyer enters the state program itself, using its own Phase II data, and takes the cost into the price.
- Seller retains liability through an indemnity backed by escrow, insurance or a creditworthy parent.
- A public partner holds an EPA grant for assessment or cleanup on land it owns or controls, then transfers or leases it.
Federal and state incentives can also help. PNNL notes that brownfields in Opportunity Zones or similar state-designated areas may qualify for financial incentives.10 Brownfield tax credits are state-specific, so confirm them with the state agency and a tax adviser, and see our guide to data center tax incentives.
07What to check before you sign
- 01Pull the state regulatory file: prior investigations, orders, certificates and recorded controls.
- 02Commission a Phase I under ASTM E1527-21 and plan to update it within 180 days of closing.87
- 03Confirm you are not affiliated with any liable party, including through financing or the seller’s affiliates.1
- 04Scope a Phase II for each recognized environmental condition before price and layout are final.
- 05Decide who enters the state program and who holds the certificate.
- 06Write a soil and groundwater management plan for construction so that grading does not breach continuing obligations.
Our due diligence checklist places these steps among power, water and zoning work, and our methodology explains how we weigh them in a screen. If you are weighing a former industrial parcel, you can get a site reviewed before committing to environmental fieldwork. Confirm the liability structure with environmental counsel.
Common questions
Can I buy a contaminated site without becoming liable for the cleanup?
Under federal law, yes, if you qualify as a bona fide prospective purchaser: you perform All Appropriate Inquiries before acquisition, are not affiliated with a liable party, and meet continuing obligations such as taking reasonable steps and honoring land use restrictions.61 State liability is a separate question that a state voluntary cleanup program usually addresses.
Does a tenant on a ground lease get the same protection?
Since the 2018 BUILD Act, tenants can qualify for BFPP protection.6 The tenant still needs its own pre-lease inquiry and must meet the continuing obligations, so confirm the structure with counsel.
How old can a Phase I be at closing?
Certain components, including interviews, records review, the site visit and the lien search, must be conducted or updated within 180 days before acquisition, and the full inquiry within one year.8 Long option periods often require an update.
Does a state no further action letter stop EPA from acting?
Generally, EPA’s CERCLA enforcement is limited at eligible sites addressed in compliance with a qualifying state response program, but the statute lists exceptions.2 A state release also may not cover federal claims, as Indiana’s statute states expressly.11
Can a data center developer apply for EPA brownfield grants?
EPA’s grants go to eligible public and nonprofit entities, and cleanup grant applicants must own the site and provide a 20 percent cost share.124 Developers usually benefit through a local government or redevelopment authority partner, subject to future funding, which depends on congressional reauthorization.5
Notes
- 1.U.S. Environmental Protection Agency, “Common Elements and Other Landowner Liability Guidance,” 2019. epa.gov
- 2.U.S. Environmental Protection Agency, “State Response Programs,” n.d. epa.gov
- 3.Texas Commission on Environmental Quality, “Voluntary Cleanup Program,” n.d. tceq.texas.gov
- 4.U.S. Environmental Protection Agency, “Brownfields Multipurpose, Assessment, Revolving Loan Fund, and Cleanup Grant Program,” n.d. epa.gov
- 5.Congressional Research Service, “Federal Brownfields Program: Background and Issues for Congress (R49055),” 2026. everycrsreport.com
- 6.U.S. Environmental Protection Agency, “Bona Fide Prospective Purchasers,” n.d. epa.gov
- 7.Beveridge & Diamond, “EPA Amends All Appropriate Inquiries Standard for Phase I Environmental Site Assessments,” 2022. bdlaw.com
- 8.U.S. Environmental Protection Agency, “All Appropriate Inquiries Fact Sheet,” 2023. epa.gov
- 9.National Association of Counties, “U.S. EPA announces nearly $250 million in FY 2026 Brownfields program grants,” 2026. naco.org
- 10.Pacific Northwest National Laboratory, “Coal to Data Center (PNNL-SA-201505),” 2024. pnnl.gov
- 11.Justia (Indiana Code), “Indiana Code § 13-25-5-18,” 2024. law.justia.com
- 12.U.S. Environmental Protection Agency, “Brownfields Cleanup Grants,” 2021. 19january2021snapshot.epa.gov
- 13.Haley & Aldrich, “EPA Brownfields Funding Has Never Been More Generous: Here’s How to Make the Most of It,” n.d. haleyaldrich.com
- 14.Smart Growth America, “Tell the House to Reauthorize Critical Funding for Brownfields Cleanup and Redevelopment,” 2026. smartgrowthamerica.org
- 15.Data Center Dynamics, “Cheswick power plant site in Springdale, Pennsylvania, sold for $14.3m for data center development,” 2025. datacenterdynamics.com
- 16.E&E News, “House Panel Advances Brownfields, Recycling Bills,” 2026. eenews.net
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Environmental & physical risk
- Can You Build a Data Center in a Floodplain?
- Wetlands and Data Center Development: Delineation, Permits and Buildable Land
- Slope, Soils and Geotechnical Review for Data Center Sites
- Natural Hazard Risk in Data Center Site Selection
- Endangered Species Review for Data Center Sites: What Triggers It and What to Check
- Cultural Resources and Section 106: What Data Center Developers Need to Know
- Stormwater Management for Data Center Campuses: Permits, Ponds and Land Use
- Do Data Center Backup Generators Need an Air Permit?
- NEPA Review for Data Centers: When It Applies and What Changed in 2025
- Seismic Risk and Data Center Site Selection: Hazard Maps, Design Categories and Liquefaction
- Karst, Sinkholes and Data Center Sites: How to Screen and Investigate the Ground
- Tornado and High-Wind Risk for Data Centers: ASCE 7-22 Tornado Loads, Risk Categories and Siting
- Wildfire Risk and Data Center Siting: Hazard Maps, Power Shutoffs and WUI Codes
- Hurricane and Storm Surge Risk for Data Center Sites: SLOSH Maps, Coastal Flood Zones and Grid Outages
- Tree Clearing and Forest Conservation Rules for Data Center Sites
- Climate Change, Future Heat and Data Center Site Risk
- Data Center Emissions and ESG Reporting: What It Means for Site Selection
- Diesel Fuel Storage and SPCC Plans at Data Centers
