Key takeaways
- Start with an IPaC screen of the site and likely utility corridors; official species lists are valid for 90 days, so refresh them on long projects.1
- A federal permit, funding or land creates a federal nexus and Section 7 consultation, which by regulation runs 90 days for formal consultation plus 45 days to deliver a biological opinion.2
- Without a federal nexus, avoiding take is the developer’s responsibility; a Section 10 permit backed by a habitat conservation plan is the path if take cannot be avoided.3
- In July 2026 the Services rescinded the regulatory definition of “harm,” narrowing when habitat loss alone counts as take; the rule is being challenged in court.56
- Bat clearing windows are the most common schedule effect; one northern Virginia county’s published guidance for the northern long-eared bat restricts tree clearing from April 1 to November 14.4
- Critical habitat restricts federal actions; it does not by itself affect private development without a federal nexus.7
01Why species review matters for data center sites
Data center campuses are large, often greenfield, and frequently cleared and graded in one or two big phases. That makes them more likely than a small infill project to touch habitat. They also come with linear pieces, such as transmission lines, gas laterals, water lines and fiber, that cross land the developer does not control.
The Endangered Species Act (ESA) prohibits “take” of listed fish and wildlife, which the statute defines to include harassing, harming, wounding or killing them.5 Listed plants are treated differently, and protection on private land is generally narrower unless a federal nexus or state law applies. The ESA is administered by the U.S. Fish and Wildlife Service (USFWS) for most terrestrial and freshwater species and by the National Marine Fisheries Service (NMFS) for most marine and anadromous species. IPaC does not display species or critical habitat under the sole jurisdiction of NOAA Fisheries, so a site near coastal or anadromous waters may also need a NMFS check.8
The 2026 change to the definition of harm
For decades, the Services defined “harm” to include significant habitat modification or degradation that actually kills or injures wildlife by significantly impairing essential behavior. In a final rule published July 14, 2026, USFWS and NMFS rescinded that definition without replacing it.5 Habitat modification that only indirectly harms wildlife is no longer treated as prohibited take; more direct impacts are needed.9 The rule has a September 2026 effective date, applies prospectively, and was challenged in federal court in Washington State the day it was published.6 Further suits followed, including one by a group of states led by California.10
02Screening with IPaC and state data
The first step is a desktop screen. USFWS’s Information for Planning and Consultation tool (IPaC) lets you draw a project area or upload a shapefile and returns the federally listed species and designated critical habitat that may occur there.118 In most of the continental United States it gives a planning list immediately; proponents, including those with no federal nexus, can then request an official species list, which is valid for 90 days and creates a record in the Service’s tracking system.1 It is a starting list, not a finding: a species on the list may have no suitable habitat on the site, and the list depends on the area you draw.
- Draw the IPaC area around the full campus and the likely utility and road corridors; results can also flag resources just outside the area drawn.8
- Check the state natural heritage program or wildlife agency for state-listed species and known occurrences. State rules and data access vary.
- Compare species habitat needs to what is actually on the site: forest type, streams, wetlands, caves, grassland or open water.
- Note species that are proposed for listing. The tricolored bat, for example, was proposed as endangered in 2022; check its current status in IPaC, since status can change during a long project.12
- Check for bald and golden eagle nests and migratory birds, which fall under separate federal laws (see below).
A qualified biologist then confirms whether suitable habitat is present and whether seasonal surveys are needed. Species work usually runs alongside the Phase I environmental site assessment and the wetland delineation during the due diligence period.
03Section 7 and Section 10: which path applies
How the ESA reaches a project depends on whether there is a federal nexus. For data centers, the most common nexus is a Clean Water Act Section 404 permit from the U.S. Army Corps of Engineers for wetland or stream impacts. Federal funding, federal land, or a federal license for a related facility can also create one, and the same nexus often brings NEPA review.
| Section 7 consultation | Section 10 incidental take permit | |
|---|---|---|
| When it applies | A federal agency authorizes, funds or carries out the action | No federal nexus, and the project is likely to take a listed animal |
| Who leads | The federal action agency, consulting with USFWS or NMFS | The applicant, applying to USFWS or NMFS |
| Key document | Biological assessment; written concurrence or a biological opinion2 | Habitat conservation plan (HCP)3 |
| Possible outcome | Concurrence of no likely adverse effect, or a biological opinion with an incidental take statement | Permit with minimization and mitigation commitments3 |
| Schedule effect | Formal consultation: 90 days plus 45 days for the opinion, extendable2 | Often lengthy; planning, public notice and agency review |
Fig. 1The Section 7 consultation path
- 01
Species list
Official IPaC list for the action area, valid 90 days.
- 02
Effects review
Biological assessment or informal consultation.
- 03
Concurrence
Written “not likely to adversely affect” ends review.
- 04
Formal consultation
90 days unless extended; 60-day cap without applicant consent.
- 05
Biological opinion
Due within 45 days, with any incidental take statement.
Under Section 7, many projects end with informal consultation, often because the project commits to avoidance measures such as timing restrictions. When formal consultation is needed, the regulations set 90 days to conclude it and 45 days to deliver the biological opinion; with an applicant involved, an extension beyond 60 days needs the applicant’s consent.2 Those clocks do not always hold: a 2015 Defenders of Wildlife study, cited in a 2017 House Natural Resources Committee memo, found about 20% of formal consultations from 2008 to 2015 ran past 135 days, not counting late starts or extensions.13 Ask whether a determination key or programmatic consultation covers the species locally.4
Without a federal nexus, there is no consultation requirement, but the prohibition on take still applies, so the usual approach is to design to avoid take and document the analysis. A Section 10 permit is the formal route when take cannot reasonably be avoided; it exempts non-federal permit holders from the take prohibition rather than approving the underlying activity.3 This is why the wetlands review and species review are linked: avoiding a 404 permit can also mean avoiding Section 7, while needing one brings both.
04Seasonal clearing windows and survey timing
The most common way species issues affect a data center schedule is timing. Where listed bats roost in trees, agencies often limit tree clearing to the season when bats are hibernating elsewhere. After the northern long-eared bat was reclassified as endangered in 2023, Prince William County, Virginia, a major data center county, published guidance describing a tree clearing restriction from April 1 through November 14 and directing proponents to complete the USFWS determination key before clearing.4 Federal bat guidance has since been revised and windows vary by species, region and project, so confirm the current window with the USFWS field office; some states set their own.
Fig. 2One bat clearing window, by month
- Clearing allowedJanuary through March 31
- No tree clearingApril 1 through November 14
- Clearing allowedNovember 15 through December
Migratory birds add a second layer. In April 2025 the Interior Department reinstated its 2017 legal opinion that the Migratory Bird Treaty Act prohibits only intentional take, the latest swing in a position that has changed several times, and there is still no permit program for incidental take under the Act.1415 Given that uncertainty, clearing outside the nesting season and avoiding active nests remains a common, conservative practice. Eagle nests are protected under a separate statute and still warrant buffers and agency coordination.
Survey seasons matter just as much: presence or absence surveys for many species are valid only at certain times of year, so missing one can push a decision, and the clearing window after it, by close to a year. The tree clearing and forest conservation guide covers state and local forest removal rules.
05What critical habitat does and does not mean
Critical habitat is a specific area designated as essential to a listed species’ conservation. The legal effect is narrower than many assume. Under Section 7, federal agencies must make sure the actions they authorize, fund or carry out do not destroy or adversely modify critical habitat. USFWS states that designations do not affect activities by private landowners when there is no federal nexus, meaning no federal funding or permit is needed for the activity.7 The take prohibition for the species itself still applies.
Not every species gets it. When it proposed listing the tricolored bat, for example, the Service found designating critical habitat not prudent.12
Critical habitat on or near a site is still a meaningful flag: it signals important habitat, raises the stakes of any federal permit and can draw public attention. Treat it as a reason to plan avoidance, not as an automatic stop or pass.
06Utility corridors and off-site work
The campus parcel is not the only footprint. A new transmission line, substation, gas lateral, water line or fiber route may cross habitat the developer never considered. These are often built by utilities or providers with their own permitting and federal nexus, but delays on them still delay the campus. Executive Order 14318, signed in July 2025, directs agencies to expedite federal reviews for qualifying data center projects, including those with at least $500 million in capital expenditure or more than 100 MW of new load, and for the transmission and other infrastructure serving them.16 It speeds the process but does not waive the ESA.
Screen the likely corridors at the same time as the site. A clean parcel with a transmission route through a known species area has a species question, just one step removed. The site due diligence checklist shows where this fits among other environmental items, and eminent domain and transmission easements covers how those corridors are acquired.
07How to screen a site for endangered species
Fig. 3Sample species screen of one parcel
Illustrative- WatchIPaC official listTwo listed bats and one mussel may occur; list dated this month.
- WatchForest habitat80 wooded acres; clearing limited to the winter window.
- PassStreams and wetlandsLayout avoids the creek; no 404 permit expected.
- PassCritical habitatNone designated on the site or corridors.
- FailTransmission corridorLikely route crosses a known cave area; needs a survey.
- 01Run IPaC on the campus and likely utility corridors and save the official species list; refresh it when it ages past 90 days.1
- 02Check state natural heritage and wildlife agency data for state-listed species and known occurrences.
- 03Have a biologist assess habitat and identify any required surveys and their seasons.
- 04Decide whether a federal nexus is likely, starting with wetlands and streams (jurisdictional determination first).
- 05Map clearing windows and survey seasons against the deal and construction schedule.
- 06Plan avoidance in the layout: buffers on streams, forest blocks, caves or known nests.
When we screen a site, species data is layered with wetlands, floodplain and forest cover, because the same stream corridors and wooded areas usually drive all of them. Confirm conclusions with a qualified biologist and the USFWS field office, or get a site reviewed.
Common questions
Does a private data center project need an Endangered Species Act review?
Formal consultation is required only when there is a federal nexus, such as a Section 404 wetlands permit, federal funding or federal land.2 Without one, the prohibition on take of listed animals still applies, so developers screen the site and design to avoid take. If take cannot be avoided, a Section 10 incidental take permit with a habitat conservation plan is the formal route.3
What is IPaC?
IPaC, the Information for Planning and Consultation tool, is a U.S. Fish and Wildlife Service website that returns the federally listed species and critical habitat that may occur in a project area you draw.11 An official species list is valid for 90 days.1 A biologist then checks whether suitable habitat actually exists and whether surveys are needed.
What changed with the 2026 “harm” rule?
In July 2026 USFWS and NMFS rescinded the regulatory definition of harm, so significant habitat modification on its own is no longer treated as take unless it more directly kills or injures wildlife.9 The rule has a September 2026 effective date, applies prospectively and faces several lawsuits, including one by a group of states.610 Section 7 consultation and state laws still apply.
Can you build on land designated as critical habitat?
Sometimes. Critical habitat mainly restricts federal actions, which must avoid destroying or adversely modifying it. USFWS says designations do not affect private activities that need no federal funding or permit, though the take prohibition still applies.7 A project needing a federal permit in critical habitat should expect closer review.
Why are tree clearing restrictions common on data center sites?
Where listed bat species may roost in trees, wildlife agencies often recommend or require clearing only during the season when bats are not present; one northern Virginia county’s guidance for the northern long-eared bat describes no clearing from April 1 to November 14.4 Because campuses often clear large wooded areas, these windows can control when grading starts, so confirm them with the biologist and agency early.
Notes
- 1.U.S. Fish and Wildlife Service, Eastern North Carolina Ecological Services, “Project Planning and Consultation,” n.d. fws.gov
- 2.Legal Information Institute, Cornell Law School, “50 CFR § 402.14 Formal consultation,” n.d. law.cornell.edu
- 3.U.S. Fish and Wildlife Service, “Habitat Conservation Plans,” n.d. fws.gov
- 4.Prince William County, Virginia, “Endangered Status of the Northern Long-eared Bat: What Developers and Landowners Need to Know,” n.d. pwcva.gov
- 5.Federal Register (GovInfo), “Federal Register Volume 91, Number 133 (Tuesday, July 14, 2026),” 2026. govinfo.gov
- 6.Bracewell, “FWS and NMFS Rescind Endangered Species Act Regulatory Definition of Harm,” 2026. bracewell.com
- 7.U.S. Fish and Wildlife Service, “Critical Habitat,” n.d. fws.gov
- 8.U.S. Fish and Wildlife Service, “IPaC resource list,” n.d. ipac.ecosphere.fws.gov
- 9.O’Melveny & Myers, “Trump Administration Rescinds the Regulatory Definition of Harm Under the Endangered Species Act, Narrowing the Act’s Reach,” 2026. omm.com
- 10.New York State Office of the Attorney General, “California et al. v. Doug Burgum et al., Complaint,” 2026. ag.ny.gov
- 11.U.S. Fish and Wildlife Service, “IPaC Instructions,” n.d. fws.gov
- 12.U.S. Fish and Wildlife Service, “Endangered Species Status for Tricolored Bat,” n.d. fws.gov
- 13.U.S. House Committee on Natural Resources, “Hearing Memo: Oversight Hearing on 03.28.17,” 2017. naturalresources.house.gov
- 14.Hunton Andrews Kurth, The Nickel Report, “The Pendulum Swings Back Again on Prohibition of Incidental Take Under the Migratory Bird Treaty Act,” 2025. hunton.com
- 15.Harvard Law School Environmental and Energy Law Program, “Regulatory Tracker: Migratory Bird Treaty Act,” 2025. eelp.law.harvard.edu
- 16.Executive Office of the President (GovInfo), “Executive Order 14318: Accelerating Federal Permitting of Data Center Infrastructure,” 2025. govinfo.gov
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Environmental & physical risk
- Can You Build a Data Center in a Floodplain?
- Slope, Soils and Geotechnical Review for Data Center Sites
- Natural Hazard Risk in Data Center Site Selection
- Phase I Environmental Site Assessments for Data Center Land
- Stormwater Management for Data Center Campuses: Permits, Ponds and Land Use
- Do Data Center Backup Generators Need an Air Permit?
- Seismic Risk and Data Center Site Selection: Hazard Maps, Design Categories and Liquefaction
- Karst, Sinkholes and Data Center Sites: How to Screen and Investigate the Ground
- Tornado and High-Wind Risk for Data Centers: ASCE 7-22 Tornado Loads, Risk Categories and Siting
- Wildfire Risk and Data Center Siting: Hazard Maps, Power Shutoffs and WUI Codes
- Hurricane and Storm Surge Risk for Data Center Sites: SLOSH Maps, Coastal Flood Zones and Grid Outages
- Brownfield Cleanup Programs and Liability Protections for Data Center Sites
- Phase II Environmental Site Assessments for Data Center Land: When You Need One and What It Costs
- Climate Change, Future Heat and Data Center Site Risk
- Data Center Emissions and ESG Reporting: What It Means for Site Selection
- Diesel Fuel Storage and SPCC Plans at Data Centers
Guide 6 of 21 in Environmental & physical risk · all 242 guides · glossary · calculators
