Key takeaways
- Section 106 is triggered by a federal undertaking; the federal agency runs it and keeps decision-making authority, while the SHPO advises.14
- The process has four steps: initiate, identify historic properties, assess effects, and resolve adverse effects.1
- Historic properties include sites and buildings that meet the National Register criteria and are eligible for listing, not just listed ones.5
- Tribes must be consulted on properties of religious and cultural significance whether those properties are on or off tribal lands.6
- For Corps wetland permits, the Corps has long used its own Appendix C procedures and a narrower “permit area”; we found no final rule on a 2024 proposal to replace them with the ACHP rules.78
- A desktop records check and an early archaeological survey are the best tools for avoiding late surprises.
01What Section 106 is
Section 106 of the National Historic Preservation Act (NHPA) requires federal agencies to take into account the effects of their undertakings on historic properties, under regulations issued by the Advisory Council on Historic Preservation (ACHP) at 36 CFR Part 800.9 It is a process requirement. It does not require that every historic property be preserved, but it does require identification, consultation and a search for ways to avoid, minimize or mitigate adverse effects.10
An undertaking is a project, activity or program funded, permitted, licensed or approved by a federal agency.1 For a data center, the federal agency is usually not the developer’s customer or regulator in any other sense. It is the agency issuing a permit or approval that the project happens to need. That agency makes the decisions; the SHPO’s role is to provide information and recommendations.4 Because the agency cannot finish its permit or funding decision until the review is done, Section 106 can sit on the critical path.
02When a data center triggers Section 106
Most private data center projects on private land have no federal role in the land use approval itself. Section 106 comes in through a related federal action, most often:
- A Clean Water Act Section 404 permit from the U.S. Army Corps of Engineers for wetland or stream impacts.
- Federal funding or loans, including for related utility infrastructure.
- Use of federal land or a federal right-of-way, a live question for federal land offered for AI data centers.
- Federal licensing or approval of related infrastructure, such as some pipelines, power facilities or communications structures.
The same federal nexus often brings NEPA review and Endangered Species Act consultation, and the regulations direct the agency to coordinate Section 106 with NEPA.10 That is why the decision to avoid or accept wetland impacts, covered in wetlands and data center development, has effects well beyond the wetlands themselves. Executive Order 14318, issued in July 2025, directs agencies to speed federal environmental reviews and permits for qualifying data center projects, but it works within these statutes rather than removing them.11
The Corps’ “permit area” and Appendix C
For its regulatory program, the Corps has followed its own procedures in Appendix C to 33 CFR Part 325. They limit review to a “permit area”: the waters directly affected by the permitted work, plus uplands only where the activity would not occur without the permit and is integrally related to and directly associated with the permitted work.7 That can be much narrower than the ACHP’s “area of potential effects.”8 In February 2024 the Corps proposed dropping Appendix C and following 36 CFR Part 800 instead, citing more consistent reviews across its districts.12 That change would generally widen the area a Corps review covers. We could not confirm a final rule as of this review, so ask the Corps district which procedures it is applying.
Fig. 1Corps Appendix C vs. the ACHP’s Part 800
Corps regulatory program
Appendix C (Corps)
- Undertaking is the permitted work, structure or discharge
- Review area is the “permit area”
- Uplands included only if three tests are met
- Lacks Part 800’s tribal consultation provisions
Government-wide rule
36 CFR Part 800 (ACHP)
- Undertaking defined more broadly
- Review area is the area of potential effects
- Can include visual and indirect effects
- Requires consultation with tribes and consulting parties
03The Section 106 process, step by step
| Step | What happens | Who is involved |
|---|---|---|
| Initiate | Agency confirms there is an undertaking, coordinates with NEPA, plans public involvement and identifies consulting parties10 | Federal agency, SHPO or THPO, tribes, local government, applicant |
| Identify | Define the area of potential effects (APE) and identify historic properties within it, through research and field surveys10 | Agency, applicant’s consultants, SHPO, tribes |
| Assess effects | Apply the criteria of adverse effect to each historic property13 | Agency with SHPO or THPO and tribes |
| Resolve | If effects are adverse, consult on avoidance, minimization or mitigation, usually recorded in a memorandum of agreement10 | Agency, SHPO or THPO, consulting parties, sometimes the ACHP |
Review clocks are short in some places and open-ended in others. When an agency submits adequate documentation, the SHPO or THPO generally has 30 days to respond to findings such as “no historic properties affected” or “no adverse effect.”14 If the SHPO or THPO agrees or does not respond within 30 days and no consulting party objects, the agency may proceed on a no-adverse-effect finding.13 The identification steps, by contrast, are carried out “in consultation with” the SHPO and tribes and have no fixed 30-day clock.14
Fig. 2Section 106 review clocks
- SHPO or THPO review of a no-adverse-effect finding
- 30 days
- SHPO or THPO response once consultation starts
- 30 days
- for identifying historic properties
- No fixed clock
The area of potential effects can include more than ground disturbance. Large buildings, substations and transmission lines can have visual effects on historic properties some distance away, such as a historic farmstead, district or battlefield. Archaeological sites, by contrast, are usually affected only where the ground is disturbed. The architectural and visual standards guide covers how local codes handle building appearance.
Historic properties are those listed in or eligible for the National Register of Historic Places. The criteria cover significance in American history, architecture, archeology, engineering and culture, and properties that achieved significance within the past 50 years are ordinarily not considered eligible unless they meet an exception. Archaeological sites are usually judged on whether they have yielded, or may be likely to yield, information important in prehistory or history.5 Eligibility is often the open question, because many archaeological sites and older structures have never been evaluated.
04SHPO, THPO and tribal consultation
Every state has a State Historic Preservation Officer (SHPO) who consults on Section 106 reviews and maintains records of known sites and surveys. On tribal lands, a Tribal Historic Preservation Officer (THPO) may take on the SHPO’s role, and the agency starts consultation with whichever office applies.10
Federal agencies must also consult with Indian tribes and Native Hawaiian organizations that attach religious and cultural significance to historic properties that may be affected, a requirement added to the regulations in 1999.15 That duty applies whether the property is on or off tribal lands, and consultation should be conducted in a manner respectful of tribal sovereignty.6 A tribe’s area of interest can cover regions far from its current reservation. Consultation is government to government between the agency and the tribe; the developer supports it with information and is often asked to meet.
05State and local cultural resource laws
Without a federal nexus, Section 106 does not apply. That does not mean cultural resources are irrelevant. Several kinds of state and local rules can still reach a project:
Fig. 3Cultural resource rules that can reach a site
- 01Federal: Section 106Only with a federal permit, funding, license or land
- 02State reviewState land, state funding or state environmental review laws
- 03State burial and cemetery lawsUsually apply regardless of permits or ownership
- 04Local historic rulesHistoric districts, landmarks, zoning conditions
- 05Site planAvoidance areas and an inadvertent discovery plan
- Unmarked burial and human remains laws, which commonly require work to stop and authorities to be notified if remains are found, regardless of land ownership or permits.
- Cemetery protection laws covering known family or historic cemeteries, which may restrict disturbance and access.
- State environmental review statutes in some states, which can require cultural resource review for state-permitted projects.
- State historic preservation review for projects on state land or using state funding.
- Local historic districts, landmark designations or zoning conditions that address historic resources.
These rules vary widely by state, so confirm them with the SHPO, a cultural resources consultant or counsel. Small family cemeteries are especially common on rural tracts and are easy to miss on maps.
06Historic places and public opposition: the Digital Gateway
Historic resources matter politically even when no federal review applies. The best-known example is the Prince William Digital Gateway, a proposed data center project of roughly 2,100 acres next to Manassas National Battlefield Park in Virginia.3 The county board approved the rezonings in December 2023, and neighbors and the American Battlefield Trust sued.216
In August 2025 a circuit court judge voided the rezonings, finding that the county’s public notice did not comply with state or county code.2 In March 2026 the Virginia Court of Appeals affirmed that the rezonings were void.16 In July 2026 QTS, one of the project’s developers, walked away from it, leaving those rulings in place.3 The legal defect was procedural, not a historic preservation finding, but the battlefield setting drove the opposition and the litigation. The broader lessons are in contested data center projects.
Fig. 4Prince William Digital Gateway, 2023 to 2026
- 01
Dec 2023
County board approves the rezonings.
- 02
Aug 2025
Circuit court voids them over defective public notice.
- 03
Mar 2026
Court of Appeals affirms the rezonings are void.
- 04
Jul 2026
QTS walks away from the project.
07Archaeological surveys and what they find
Cultural resource work usually starts with a desktop review: SHPO site files, previous surveys, historic maps and aerial imagery, and landform analysis to estimate where sites are likely. The SHPO site files are often restricted to qualified professionals to protect site locations.
If a field survey is needed, archaeologists walk the site and dig shovel tests on a grid, with tighter spacing in high-probability areas such as terraces near streams. Sites that might be eligible for the National Register may need further testing to evaluate them against the criteria.5 Field seasons, ground conditions and vegetation can limit when this work is practical.
Findings typically lead to one of three outcomes: no historic properties affected, avoidance through layout changes such as setting aside a small preserve, or mitigation such as data recovery excavation. Avoidance is usually faster and cheaper. Even with a clean survey, construction plans commonly include an inadvertent discovery plan for unexpected finds.
08How to screen a site for cultural resources
- 01Identify whether any federal nexus is likely, starting with wetlands, federal funding and federal land.
- 02If a Corps permit is likely, ask the district whether it is applying Appendix C or Part 800 and how it will define the review area.7
- 03Have a qualified consultant review SHPO site files and previous surveys for the site and corridors.
- 04Check historic maps and imagery for cemeteries, homesteads and old structures.
- 05Note historic properties nearby, such as battlefields or districts, that could be visually affected by tall buildings or transmission.
- 06Scope any field survey early enough to fit within the diligence period, and keep sensitive areas out of the core building footprint.
Cultural resources sit alongside species, wetlands and floodplain in the environmental part of the site due diligence checklist, and they belong in the broader permitting plan. The endangered species guide covers the parallel ESA review. To have a parcel screened, get a site reviewed.
Common questions
What is Section 106 review?
Section 106 of the National Historic Preservation Act requires federal agencies to consider how their undertakings affect historic properties, meaning sites, buildings and districts listed in or eligible for the National Register.1 The agency initiates review, identifies historic properties, assesses effects and resolves adverse effects in consultation with the SHPO, tribes and others.10 It applies only when a federal agency funds, permits, licenses or approves the project.
Does a private data center need Section 106 review?
Only if there is a federal undertaking. A data center on private land with only local and state approvals usually does not trigger Section 106. A Section 404 wetlands permit, federal funding, federal land or certain federal approvals for related infrastructure can.1 Even without Section 106, state laws on burials, cemeteries or state-permitted projects may still require cultural resource work.
What is the difference between a SHPO and a THPO?
A State Historic Preservation Officer (SHPO) is the state official who consults on Section 106 reviews and maintains the state’s historic and archaeological records. A Tribal Historic Preservation Officer (THPO) performs that role for a tribe on its tribal lands.10 Federal agencies must also consult with tribes that attach religious and cultural significance to affected properties off tribal lands, whether or not those tribes have a THPO.6
How long does Section 106 take?
It depends on what is found. A SHPO or THPO generally has 30 days to review a finding once it has adequate documentation, and a clean “no historic properties affected” or “no adverse effect” finding can conclude quickly.1413 Identification surveys have no fixed review clock, and tribal consultation or negotiating a memorandum of agreement for adverse effects can take many months.
What happens if an archaeological site is found on my property?
It depends on the site’s significance and the project’s permits. Many sites do not meet the National Register criteria5 and need no further action. Significant sites are often avoided through layout changes, or mitigated through data recovery if a federal undertaking requires it. If human remains are found, state laws usually require work to stop and authorities to be notified, regardless of any federal involvement.
Notes
- 1.Washington State Department of Archaeology and Historic Preservation, “Section 106,” n.d. dahp.wa.gov
- 2.WTOP News, “Judge voids Digital Gateway rezoning in Prince William County,” 2025. wtop.com
- 3.W.Media, “QTS walks away from 2,100-acre Digital Gateway project in Northern Virgina,” 2026. w.media
- 4.State Historical Society of Iowa, State Historic Preservation Office, “Review & Compliance,” n.d. culture.iowaeda.com
- 5.eCFR, National Archives, “36 CFR 60.4 Criteria for evaluation,” n.d. ecfr.gov
- 6.U.S. Department of Housing and Urban Development, “Notice CPD-12-006: Process for Tribal Consultation in Projects That Are Reviewed Under 24 CFR Part 58,” 2012. adeca.alabama.gov
- 7.Legal Information Institute, Cornell Law School, “33 CFR Appendix C to Part 325: Procedures for the Protection of Historic Properties,” n.d. law.cornell.edu
- 8.Beveridge & Diamond, “Army Corps of Engineers Proposes to Rescind Its Specific Approach to Historic Properties,” 2024. bdlaw.com
- 9.National Park Service, “Advisory Council on Historic Preservation Regulations Implementing Section 106,” n.d. nps.gov
- 10.eCFR, National Archives, “36 CFR Part 800, Subpart B: The Section 106 Process,” 2026. ecfr.gov
- 11.Executive Office of the President (GovInfo), “Executive Order 14318: Accelerating Federal Permitting of Data Center Infrastructure,” 2025. govinfo.gov
- 12.U.S. Army, “Proposed rule on protection of historic properties,” 2024. army.mil
- 13.eCFR, National Archives, “36 CFR 800.5 Assessment of adverse effects,” 2026. ecfr.gov
- 14.Advisory Council on Historic Preservation, “30-Day Review Timeframes: When are They Applicable in Section 106 Review?,” n.d. achp.gov
- 15.Advisory Council on Historic Preservation, “ACHP Consultation Procedures Pursuant to Executive Order 13175,” 2021. achp.gov
- 16.American Battlefield Trust, “Virginia Court of Appeals Deals Blow to Data Center Complex Threatening Manassas Battlefield,” 2026. battlefields.org
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Environmental & physical risk
- Can You Build a Data Center in a Floodplain?
- Slope, Soils and Geotechnical Review for Data Center Sites
- Natural Hazard Risk in Data Center Site Selection
- Phase I Environmental Site Assessments for Data Center Land
- Stormwater Management for Data Center Campuses: Permits, Ponds and Land Use
- Do Data Center Backup Generators Need an Air Permit?
- Seismic Risk and Data Center Site Selection: Hazard Maps, Design Categories and Liquefaction
- Karst, Sinkholes and Data Center Sites: How to Screen and Investigate the Ground
- Tornado and High-Wind Risk for Data Centers: ASCE 7-22 Tornado Loads, Risk Categories and Siting
- Wildfire Risk and Data Center Siting: Hazard Maps, Power Shutoffs and WUI Codes
- Hurricane and Storm Surge Risk for Data Center Sites: SLOSH Maps, Coastal Flood Zones and Grid Outages
- Brownfield Cleanup Programs and Liability Protections for Data Center Sites
- Phase II Environmental Site Assessments for Data Center Land: When You Need One and What It Costs
- Tree Clearing and Forest Conservation Rules for Data Center Sites
- Climate Change, Future Heat and Data Center Site Risk
- Data Center Emissions and ESG Reporting: What It Means for Site Selection
- Diesel Fuel Storage and SPCC Plans at Data Centers
Guide 7 of 21 in Environmental & physical risk · all 242 guides · glossary · calculators
