Key takeaways
- The GHG Protocol requires dual Scope 2 reporting where contractual data exist: a location-based total using grid-average factors and a market-based total using contracts, certificates or a residual mix.1
- In the U.S., EPA’s eGRID subregion rate for the facility’s location is the usual location-based factor, so the grid region is a site attribute buyers can look up from a zip code.2
- Google’s location-based emissions roughly doubled from 2020 to 2024 while its market-based headline improved, which shows how far the two methods can diverge.67
- California’s SB 253 applies to entities with more than $1 billion in revenue doing business in the state; CARB proposed moving the first Scope 1 and 2 deadline to November 10, 2026, with Scope 3 to follow in 2027.38
- The EU requires data centers with at least 500 kW of installed IT power to report energy and sustainability indicators to a European database by May 15 each year.4
- The GHG Protocol’s proposed Scope 2 revision would add hourly matching and deliverability requirements to market-based claims; consultation feedback was summarized in July 2026.510
01Why a data center’s reported emissions depend on the site
A data center burns little fuel on site in normal operation. Its footprint is dominated by the electricity it buys and by the steel, concrete and servers that go into it. That makes emissions reporting a site question in a way it is not for most buildings: the same building on two grids can report very different numbers.
The GHG Protocol’s Scope 2 Guidance sets the accounting most companies use. A location-based figure applies average emission factors for the grid where consumption occurs, and a market-based figure reflects the electricity a company has contractually chosen, through supplier-specific rates or energy attribute certificates that meet the guidance’s Scope 2 Quality Criteria. Where those contractual data are available, companies are required to report both totals.1 In the U.S., EPA describes its eGRID database as a primary source of emission rates for location-based Scope 2 reporting and recommends using the eGRID subregion where the facility is located.2
The practical point for landowners, developers and utilities is that a hyperscale tenant’s sustainability team will look up the grid factor for a candidate site as readily as its power team looks at substation capacity. A site on a low-carbon grid starts with a lower location-based number, and no contract can change that figure. For the procurement side, see renewable energy procurement and siting.
02Scope 1, 2 and 3 at a data center
The three scopes map onto a data center campus in a fairly predictable way. The table summarizes where each comes from and which ones the site itself influences.
| Scope | Main sources | How the site affects it |
|---|---|---|
| Scope 1 (direct) | Diesel or gas generators, on-site gas turbines or engines, refrigerant leaks | On-site generation and backup fuel choices; generator testing hours set in air permits |
| Scope 2 (purchased energy) | Grid electricity, purchased steam or chilled water | Grid region sets the location-based factor; local clean supply shapes the market-based figure12 |
| Scope 3 (value chain) | Construction materials, servers and chips, transport, end of life | Building size, structure and phasing; less tied to the land itself11 |
Scope 1 is usually small for grid-served sites, but it grows quickly when a campus runs reciprocating engines or turbines as primary or bridge power. That trade-off between speed to power and direct emissions is covered in on-site generation and bridge power, and the permitting side in air permits for data center generators.
Scope 3 is where the largest operators now report most of their footprint. Microsoft’s 2025 report put total emissions about 23.4% above its 2020 baseline, with the company attributing the rise to growth in AI and cloud, while its energy use rose 168% over the same period. Reporting on the report notes that Scope 3 made up just over 97% of Microsoft’s footprint for fiscal 2024 and that its leaders tied the Scope 3 rise mainly to data center construction, the embodied carbon in building materials, and hardware such as semiconductors and servers.1112
Fig. 1Microsoft’s footprint, fiscal 2024
- total emissions vs. 2020 baseline
- +23.4%
- energy use over the same period
- +168%
- share of footprint in Scope 3
- 97%+
03Location-based vs. market-based: the two numbers buyers will see
The two Scope 2 methods answer different questions. The location-based figure shows the emissions of the grid the site actually draws from. The market-based figure shows the effect of purchasing choices, and where a company buys no qualifying instruments it must use residual mix factors instead.1 A residual mix strips out power whose attributes have been claimed by others, so it can differ noticeably from the plain grid average that EPA recommends for the location-based figure.2
The gap can be large. A Policy Review analysis of big tech’s 2025 sustainability reports found Google’s location-based emissions rose from about 5.8 million to over 11.2 million metric tons of CO₂ between 2020 and 2024, while the company’s headline market-based reporting, which counts renewable contracts and certificates, looked far better.6 Google’s own 2025 report said its data center energy emissions fell 12% in 2024 even as data center electricity use rose 27%, crediting efficiency and clean energy contracts totaling more than 8 GW.7
Fig. 2Google location-based emissions, 2020 vs. 2024
- 20205.8
- 202411.2+
million metric tons CO₂
Neither method is wrong; both are part of the standard.1 For site selection, the lesson is that a tenant will carry the location-based figure in its disclosures no matter how much clean energy it buys, and the market-based figure depends on whether clean supply can actually be contracted in that region. Both point back to the grid and the utility service territory.
04The pending Scope 2 revision: hourly and deliverable
The GHG Protocol is revising the 2015 Scope 2 Guidance. The proposals approved for public consultation keep both the location-based and market-based methods but would require market-based claims to meet hourly matching and deliverability tests, so that clean power is counted only if it is generated in the same hour and could physically reach the load. To ease the transition, the draft includes load profiles for hourly matching, exemption thresholds for smaller organizations, a legacy clause for existing contracts and a phased rollout.5
As of mid-2026, the revision was still a proposal. A summary of consultation feedback was released on July 29, 2026, after a consultation that drew nearly 1,100 participants from 56 countries, according to an energy consultancy’s account; final text and effective dates had not been published.10 Trade coverage of that summary reported substantial opposition among respondents to both hourly matching and deliverability, which left the final shape of the revision unsettled.13
If adopted in something like its proposed form, the change would make the market-based number behave more like the location-based one. Annual certificates bought from a distant region would count for less, and clean supply on the same grid, at the hours the data center runs, would count for more. That favors sites in regions with deep clean supply and room for new contracted projects, and it is the logic behind 24/7 carbon-free energy and hourly matching. Treat it as a direction to plan for, not settled rules.
05Disclosure rules: California, the EU and the SEC
Voluntary reporting is now backed by mandatory rules in some jurisdictions, though the U.S. federal rule is effectively gone. On March 27, 2025, the SEC voted to end its defense of its 2024 climate disclosure rules, which had been stayed during litigation in the Eighth Circuit.14
California SB 253 and SB 261
California’s SB 253 requires U.S. entities with total annual revenue above $1 billion, measured by the lesser of the two prior fiscal years, that do business in California to report emissions; CARB adopted initial regulations in February 2026.3 In June 2026, CARB withdrew that package to make clarifying changes and proposed moving the first Scope 1 and Scope 2 reporting deadline from August 10 to November 10, 2026, while signaling enforcement discretion for good-faith efforts in the first cycle; the revised regulation still needed approval from the Office of Administrative Law.8 Scope 3 reporting is expected to begin in 2027; at a July 2026 workshop CARB staff previewed options for how many Scope 3 categories to require.9 SB 261, the companion climate risk reporting law, was enjoined by the Ninth Circuit on November 18, 2025 pending appeal, and CARB said it would not enforce the January 1, 2026 deadline.15
European Union
The EU’s Omnibus I directive, published in the Official Journal in February 2026, narrowed the Corporate Sustainability Reporting Directive to companies with more than 1,000 employees and net turnover above €450 million, with a separate test for non-EU groups based on €450 million of EU turnover and an EU subsidiary or branch above €200 million.16 Separately, Article 12 of the recast Energy Efficiency Directive requires operators of data centers with at least 500 kW of installed IT power to report energy and sustainability indicators for the prior calendar year to a European database by May 15 each year. The first reports were due by September 15, 2024.4
Fig. 3Three disclosure regimes that touch data centers
Company level
California SB 253
- Over $1 billion revenue, doing business in CA
- Scope 1 and 2 first; proposed due Nov 10, 2026
- Scope 3 expected from 2027
- Covers the whole company, not one site
Company level
EU CSRD (after Omnibus I)
- Over 1,000 employees and €450M turnover
- Non-EU groups: €450M EU turnover test
- Emissions reported within ESRS
- Narrower scope than the original law
Facility level
EU data center scheme (EED Art. 12)
- Data centers of 500 kW IT power or more
- Annual report to EU database by May 15
- Energy and sustainability indicators
- Reported per facility
06What this means for choosing and marketing a site
For a site seller or developer, emissions reporting shows up as a set of questions from the buyer, not as a permit. The most useful facts to have ready are those the buyer cannot change after closing.
- Grid region and factor: the eGRID subregion and its current output emission rate, which can be found from the site’s zip code with EPA’s Power Profiler.2
- Utility supply: whether the serving utility offers clean energy tariffs, and whether new wind, solar, storage or firm clean projects can be contracted on the same grid, which matters more if hourly matching is adopted.5
- On-site generation: whether the power plan relies on gas engines, turbines or diesel for more than backup, since that adds Scope 1 emissions and permit limits.
- Construction footprint: building size and structure drive embodied carbon, which large operators now report as part of Scope 3.11
- Reporting exposure: whether the likely tenant is subject to SB 253, the CSRD or facility-level EU reporting.164
Fig. 4Grid carbon vs. clean supply available to contract
Hardest to report well
High location-based figure and little local supply to offset it
Fixable with contracts
High grid factor, but local projects can improve market-based
Good, but tight
Clean grid today; new load may compete for limited supply
Strongest position
Low grid factor and room to add contracted clean supply
Scarce ← Clean supply available to contract locally → Ample
07What to check before you commit
- 01Look up the eGRID subregion for the site and record the current emission rate in the diligence file.
- 02Ask the utility what clean energy tariffs or power purchase agreement structures are available and how renewable energy certificates are retired.
- 03Model Scope 2 both ways, location-based and market-based, for the planned load, and test the market-based case against hourly matching.
- 04If the power plan includes on-site generation, estimate Scope 1 emissions and confirm permit limits early.
- 05Identify which disclosure regimes the end user faces, and when, using the current CARB and EU rules rather than older summaries.
Efficiency still matters: lower PUE reduces purchased electricity and therefore Scope 2 under either method. See PUE and data center energy efficiency. If you want a parcel screened for grid, power and permitting factors that drive these numbers, you can get a site reviewed.
Common questions
What are Scope 1, 2 and 3 emissions for a data center?
Scope 1 is direct emissions on site, such as generator fuel and refrigerant leaks. Scope 2 is emissions from purchased electricity, which the GHG Protocol reports both location-based and market-based.1 Scope 3 covers the value chain, including construction materials and servers, and is the largest share for operators such as Microsoft.11
What is the difference between location-based and market-based emissions?
Location-based emissions use average emission factors for the grid where electricity is consumed; market-based emissions reflect contracts and certificates the company holds, or a residual mix if it holds none.1 In the U.S., the location-based factor usually comes from EPA’s eGRID subregion rate.2
Does California SB 253 apply to data center operators?
It applies to U.S. entities with more than $1 billion in annual revenue that do business in California, which includes many large operators and tenants.3 It is a company-level rule, so it covers all of a company’s facilities, not only those in California. CARB proposed November 10, 2026 for the first Scope 1 and 2 reports.8
Do EU data centers have to report energy use?
Yes. Data centers with at least 500 kW of installed IT power must report energy and sustainability indicators for the prior year to a European database by May 15 each year under the Energy Efficiency Directive.4 National transposition details vary by member state.
Will hourly matching become required?
Not yet. The GHG Protocol proposed adding hourly matching and deliverability requirements for market-based Scope 2 claims, with phase-in and legacy provisions, and released a summary of consultation feedback in July 2026.510 Final requirements and timing were still pending as of October 2026.
Notes
- 1.Greenhouse Gas Protocol, “GHG Protocol Scope 2 Guidance,” 2015. ghgprotocol.org
- 2.U.S. Environmental Protection Agency, “Using eGRID to Determine Emissions,” 2025. epa.gov
- 3.Greenberg Traurig, “CARB Adopts Initial Climate Disclosure Reporting Regulations to Implement SB 253 and SB 261,” 2026. gtlaw.com
- 4.Government of Ireland, “Data Centre Energy and Sustainability Performance Reporting Obligations,” n.d. gov.ie
- 5.Greenhouse Gas Protocol, “Upcoming Scope 2 Public Consultation: Hourly Matching and Deliverability,” 2025. ghgprotocol.org
- 6.Internet Policy Review, “Not Greenwashing, but Still… A Closer Look at Big Tech’s 2025 Sustainability Reports,” 2025. policyreview.info
- 7.AI Magazine, “What Does Google’s 2025 Environmental Report Say About AI?,” 2025. aimagazine.com
- 8.Hogan Lovells, “CARB Pushes SB 253 Reporting Deadline to November,” 2026. hoganlovells.com
- 9.Debevoise & Plimpton, “CARB Previews Proposed SB 253 Reporting Requirements for 2027 and Beyond,” 2026. debevoise.com
- 10.NUS Consulting Group, “GHG Protocol Scope 2 Consultation Feedback,” 2026. nusconsulting.com
- 11.Sustainability Magazine, “Microsoft’s 2030 Plan Revealed as Emissions Rise by 23.4%,” 2025. sustainabilitymag.com
- 12.DatacenterDynamics, “Microsoft Emissions Up 23% Since 2020, Blames AI Data Centers,” 2025. datacenterdynamics.com
- 13.Trellis, “What’s Next for GHG Protocol’s Electricity Rule Revision,” 2026. trellis.net
- 14.U.S. Securities and Exchange Commission, “SEC Votes to End Defense of Climate Disclosure Rules,” 2025. sec.gov
- 15.Harvard Law School Forum on Corporate Governance, “California Climate Disclosure Law SB 261 Implementation Halted: Ninth Circuit Grants Injunction Pending Appeal,” 2025. corpgov.law.harvard.edu
- 16.Herbert Smith Freehills Kramer, “Omnibus I Update: CSRD and CSDDD Amendment Directive Published in the Official Journal,” 2026. hsfkramer.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Environmental & physical risk
- Can You Build a Data Center in a Floodplain?
- Wetlands and Data Center Development: Delineation, Permits and Buildable Land
- Slope, Soils and Geotechnical Review for Data Center Sites
- Natural Hazard Risk in Data Center Site Selection
- Phase I Environmental Site Assessments for Data Center Land
- Endangered Species Review for Data Center Sites: What Triggers It and What to Check
- Cultural Resources and Section 106: What Data Center Developers Need to Know
- Stormwater Management for Data Center Campuses: Permits, Ponds and Land Use
- NEPA Review for Data Centers: When It Applies and What Changed in 2025
- Seismic Risk and Data Center Site Selection: Hazard Maps, Design Categories and Liquefaction
- Karst, Sinkholes and Data Center Sites: How to Screen and Investigate the Ground
- Tornado and High-Wind Risk for Data Centers: ASCE 7-22 Tornado Loads, Risk Categories and Siting
- Wildfire Risk and Data Center Siting: Hazard Maps, Power Shutoffs and WUI Codes
- Hurricane and Storm Surge Risk for Data Center Sites: SLOSH Maps, Coastal Flood Zones and Grid Outages
- Brownfield Cleanup Programs and Liability Protections for Data Center Sites
- Phase II Environmental Site Assessments for Data Center Land: When You Need One and What It Costs
- Tree Clearing and Forest Conservation Rules for Data Center Sites
- Climate Change, Future Heat and Data Center Site Risk
- Diesel Fuel Storage and SPCC Plans at Data Centers
Guide 20 of 21 in Environmental & physical risk · all 242 guides · glossary · calculators
