BlackForge Data Centers

Feasibility, diligence & deals

Due Diligence Periods and Purchase Contingencies for Data Center Land

A due diligence period is the window in a land contract when the buyer can study the site and walk away with its deposit, and purchase contingencies are the conditions (power, zoning, environmental, title) that must be met before closing. For data center land, the standard 30–60 day window is usually too short because utility studies alone can take months, so buyers negotiate longer periods, milestone-based contingencies and paid extensions.1 Recent public deals show extensions tied to power and rezoning conditions are now routine, and that sellers and county boards push back when they run long.23

Last reviewed · 9 min read · BlackForge Data Centers

Key takeaways

  • Treat the diligence period and the contingencies as separate tools: the first is a free look at the whole site, the second keeps specific risks (power, zoning, environmental) open until they are resolved.
  • Tie the power contingency to a utility milestone, not a calendar date alone. Capacity rights usually come from contracts and tariffs, not recorded title, so they need their own diligence.4
  • Federal all appropriate inquiries rules require key Phase I components to be no more than 180 days old at acquisition, so a long diligence period can force an update before closing.5
  • Extension fees are negotiated: some are credited to the price, some are not, and some are split.67 Read the clause, not the term sheet.
  • Long extensions cost goodwill as well as money. A seller or public body that tires of waiting may shorten, condition or refuse the next one.8

01Diligence periods, contingencies and closing conditions

A purchase and sale agreement for development land usually gives the buyer three kinds of protection. The due diligence period (sometimes called a feasibility or inspection period) lets the buyer investigate anything and terminate for any reason, or no reason, before a deadline. Contingencies are narrower: they keep a specific question open, such as rezoning approval or a utility commitment, past the end of that free look. Closing conditions are the things that must be true on the closing date, such as clean title and the seller’s representations still being accurate.

For most commercial land, a 30–60 day diligence period is common. Counsel working on data center deals describe that window as generally inadequate, because utility interconnection studies alone can stretch for months.1 Title and survey review also tends to take longer than on a typical project, because easements, mineral rights and other third-party interests can interfere with a large campus layout.9 The result is that data center contracts often pair a moderate free-look period with longer, milestone-based contingencies for the slow items.

Fig. 1How a land contract moves to closing

  1. 01

    Effective date

    Contract signed; initial deposit into escrow.

  2. 02

    Diligence period

    Free look: title, survey, Phase I, utilities, zoning.

  3. 03

    Deposit goes hard

    Buyer stays in; some or all deposit at risk.

  4. 04

    Contingency periods

    Power, rezoning, permits; paid extensions if needed.

  5. 05

    Closing

    Conditions met; deposits and credited fees applied.

A common structure; names, order and deadlines are negotiated deal by deal. Power and rezoning often run past the free-look period as separate contingencies.1

Neighboring guides cover the documents on either side of this one: letters of intent set the business terms, and option agreements are the main alternative to a contract with contingencies. The broader list of what to investigate is in the site due diligence checklist.

02The power contingency

Power is the contingency that most often decides whether a data center land deal closes. A will-serve letter can give some comfort about current or expected capacity, but it is not a delivery commitment.9 If the utility has to add capacity or build infrastructure to reach the property, the project risks delay or may not be completed at all.9

Two features make power different from other contingencies. First, a site’s utility capacity and service rights usually arise from contracts and tariffs rather than recorded real-property interests, so they do not show up in a title commitment, and a change of ownership may need the utility’s consent or a new agreement.4 Second, large-load tariffs increasingly carry 12- to 19-year minimum-billing terms and exit fees, a liability that also will not appear on a title report.4 A buyer that closes on “power available” without reading the service terms can inherit a long payment obligation.

Public examples show how this plays out. Compass Datacenters extended its diligence period on 280 acres in Milton, Ontario, to evaluate power options, then called off the purchase after it did not receive the electricity allocation it wanted; a broker said the seller had grown tired of waiting for a definitive answer.8 In Ohio, a developer of a proposed $2 billion data center in Oregon asked the city for six more months, citing complications after an electrical study and the need for additional permits.10

  • Define the milestone: a completed load study, a signed facilities or electric service agreement, or written confirmation of a stated MW amount by a stated date.
  • Name who pays for studies and deposits, and what happens to them if the deal terminates.
  • Require the seller to cooperate with utility applications and to assign any existing service rights.
  • Allow the buyer to review the applicable large-load tariff and any contract demand or minimum-bill terms before the contingency lapses.

03Zoning and entitlement contingencies

If the land is not zoned for a data center, the buyer will usually want a contingency that lasts through final, unappealable approval of a rezoning, special use permit or site plan, with the seller’s cooperation in signing applications. Diligence should also cover pending changes: counsel advise reviewing proposed ordinances, state and local proceedings, utility commission dockets and any moratorium in effect, not just today’s zoning map.1 One national firm now frames site selection as “power-plus-permission,” with regulatory, political and community risk weighed alongside power access.11

Approvals themselves can carry deadlines that interact with the purchase contract. When Coweta County, Georgia, rezoned 326.6 acres for the Project Peach data center in 2025, one condition required the developers to obtain a power purchase contract within six months, a window that ended October 15, 2025, with the possibility of reverting the land to rural conservation zoning if the condition went unmet.2 The board later granted 12 more months on a 4–1 vote, after the developer said its work with Georgia Power had slowed because the end user was not yet determined.2

Large assemblies add their own timing risk. Developers of the 1,034-acre Project Cardinal campus in Yorkville, Illinois, asked the city in 2026 to extend a July 1 deadline to acquire all parcels to December 31, 2027, citing “unforeseen circumstances.”12 For process detail, see zoning for data centers and the permitting process.

04Environmental contingencies and the 180-day clock

The environmental contingency usually lets the buyer commission a Phase I ESA and, if it finds recognized environmental conditions, a Phase II, and terminate if the results are unacceptable. Its timing is shaped by federal rules. To qualify for CERCLA landowner liability protections, a buyer must complete all appropriate inquiries within one year before acquisition, and five components must be conducted or updated within 180 days of acquisition: interviews with owners and occupants, searches for environmental cleanup liens, government records review, visual inspection of the property and adjoining properties, and the environmental professional’s declaration.5

Fig. 2Maximum age of Phase I components at acquisition

  • Overall inquiry1 year
  • Owner and occupant interviews180
  • Cleanup lien search180
  • Government records review180
  • Site visit180
  • EP declaration180

days before acquisition

Under 40 CFR 312.20, the overall inquiry may be up to one year old, but five components must be no more than 180 days old.5

The practical point: a data center contract with a long power or rezoning contingency can easily run past 180 days, so the Phase I will need an update before closing. Budget for it. The assessment should also follow ASTM E1527-21, which EPA recognized as meeting the all appropriate inquiries standard effective February 13, 2023.13

05Deposits, going hard and extension fees

Earnest money is usually refundable during the diligence period and becomes nonrefundable, or “goes hard,” once that period ends without a termination notice.14 Deadlines are strict: a termination notice delivered a day late can cost the deposit, so the notice method and time zone in the contract matter.

When the buyer needs more time, the usual currency is an extension fee. Buyer-side counsel describe paying extension fees smaller than the deposit, often nonrefundable but credited against the price, so the main deposit can stay refundable if a contingency fails.15 How fees are credited varies widely in practice. In one 2006 amendment, a $200,000 nonrefundable extension fee was applied in full to the purchase price.6 In a 2007 amendment, a $120,000 nonrefundable fee was split, with $70,000 credited at closing and $50,000 not.7

Fig. 3Three ways extension fees are treated

Buyer-friendly

Credited

  • Nonrefundable once paid
  • Applied to price at closing
  • Lost only if the deal fails
  • Common ask for long power waits

Split

  • Nonrefundable once paid
  • Part credited, part kept
  • Splits the cost of delay
  • Often a negotiated compromise

Seller-friendly

Not credited

  • Nonrefundable once paid
  • Pure price of more time
  • Raises the all-in land cost
  • Rises with each extension
Patterns seen in public contract amendments and practitioner commentary; the clause in each contract controls.67

Public sellers add another layer. When Sabey asked Butte-Silver Bow, Montana, for a one-year extension of a February 11 closing deadline on 606 acres it had agreed to buy for just over $1.2 million, citing ongoing surveys, civil drawings and power negotiations with NorthWestern Energy, the council voted 9–3 to grant six months instead.163

06How long is long enough

There is no standard length. The right period is the time it takes to answer the questions that would make the buyer walk away, and on data center land those are usually power and entitlement. A buyer should map the expected duration of each item before agreeing to dates, then decide which can fit in the free look and which need their own contingency.

Fig. 4Illustrative contract schedule for a powered site

Illustrative
  • Diligence periodTitle, survey, Phase I, desktop utility review
  • Utility load studyRuns as a power contingency
  • RezoningApplication, hearings, appeal period
  • Paid extensionIf the study or approval slips
  • Phase I updateRefresh 180-day components
  • Closing
051015months
Illustrative example only. Actual utility study and rezoning durations vary widely; confirm them with the utility and county before setting contract dates.

Sellers will resist open-ended dates. The usual compromise is a firm outside date with a fixed number of paid extensions, each available only if the buyer shows progress, such as a filed application or a pending utility study. The Milton, Butte and Coweta examples all show the same pattern: time was granted, but less than requested or with conditions attached. For how these timelines fit the wider search, see how long site selection takes.

07What to negotiate before you sign

  1. 01Diligence period long enough for title, survey, Phase I and a desktop power and zoning screen, with clear access rights for borings and surveys.
  2. 02A power contingency tied to a named utility milestone and MW amount, plus review of the service agreement and tariff terms.
  3. 03An entitlement contingency that runs through final approval and any appeal period, with seller cooperation on applications.
  4. 04An environmental contingency, and a plan to update the Phase I if closing falls more than 180 days after the site visit.
  5. 05Extension rights: how many, how long, what each costs, whether fees are credited and what progress must be shown.15
  6. 06Termination mechanics: notice method, deadline time, and what happens to deposits, studies and utility applications.

Every one of these is a negotiated term, so have a real estate attorney draft the contract and confirm power assumptions with the utility in writing. A pre-contract screen of power, zoning and buildable acreage helps set realistic dates before money goes hard; you can get a site reviewed or see our methodology.

Common questions

How long is a typical due diligence period for data center land?

Commercial land contracts often use 30–60 days, but data center counsel describe that as generally inadequate because utility studies can take months.1 Many deals use a moderate free-look period and then separate power and zoning contingencies that run longer, with paid extensions.

What is a power contingency in a land purchase contract?

It is a condition that lets the buyer terminate if the utility cannot commit a stated amount of power by a stated date. Because capacity rights usually come from utility contracts and tariffs rather than recorded title, the contingency should also give the buyer time to review service terms such as minimum bills and exit fees.

Are extension fees refundable?

Usually not, but whether they are credited to the purchase price varies. Public contract amendments show fees credited in full and fees split between credited and uncredited portions.67 Buyer-side counsel generally push for credited fees.15

Does a Phase I ESA expire during a long contingency period?

For CERCLA liability protection, the inquiry must be within one year of acquisition and five components, including the site visit and records review, must be within 180 days.5 A long contract often needs a Phase I update shortly before closing.

What happens if a rezoning condition has a deadline?

The approval may lapse or the county may move to revert the zoning if the condition is not met. In Coweta County, Georgia, a six-month power contract condition on the Project Peach rezoning was extended by 12 months on a 4–1 vote.2

Notes

  1. 1.Levenfeld Pearlstein, “Data Center Real Estate Development in a Fragmented Regulatory Environment,” n.d. lplegal.com
  2. 2.The Newnan Times-Herald, “Commissioners grant Project Peach additional 12 months for power purchase contract,” 2025. times-herald.com
  3. 3.The Eastern Progress, “B-SB council OK’s six-month extension on data center land deal,” n.d. easternprogress.com
  4. 4.Kidder Mathews, “When Power Becomes the Property: The Real Estate Behind the AI Data Center Boom,” n.d. kidder.com
  5. 5.Electronic Code of Federal Regulations, “40 CFR 312.20, All appropriate inquiries,” n.d. ecfr.gov
  6. 6.Justia (CECO Environmental Corp. contract filing), “Amendment to Purchase Agreement,” 2006. contracts.justia.com
  7. 7.Justia (Silverleaf Resorts, Inc. contract filing), “Amendment to Purchase Agreement,” 2007. contracts.justia.com
  8. 8.Green Street News, “A deal for 280 acres in Milton by Compass Datacenters is now off,” n.d. greenstreetnews.com
  9. 9.Morgan Lewis, “Key Considerations in the Acquisition of Undeveloped Data Center Land,” 2025. morganlewis.com
  10. 10.13abc (WTVG), “Data center developer asks for six-month extension in Oregon,” 2026. 13abc.com
  11. 11.Nixon Peabody, “Data Center Siting Strategies,” 2026. nixonpeabody.com
  12. 12.Shaw Local, “Developers of Project Cardinal data center in Yorkville ask for 18-month extension to purchase land,” 2026. shawlocal.com
  13. 13.Winston & Strawn, “It’s Official: EPA Approves Phase I Standard ASTM E1527-21 as Meeting All Appropriate Inquiry, Effective February 13, 2023,” n.d. winston.com
  14. 14.A.CRE (Adventures in CRE), “The Earnest Money Deposit,” n.d. adventuresincre.com
  15. 15.Becker & Poliakoff, “Simple Protections for Buyers in Commercial Real Estate Contract Negotiations,” n.d. beckerlawyers.com
  16. 16.Montana Right Now, “Sabey seeks extension on land deal for locating huge data center in Butte,” n.d. montanarightnow.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Related guides

More in Feasibility, diligence & deals