Data Center Site Selection in California and CAISO

Siting a data center in California starts with which of the state’s eight balancing authorities and which utility serve the site; CAISO is the largest, and PG&E now handles transmission-level loads under an interim Rule 30 that requires up-front payment for grid work.12 Permits run through CEQA, local air districts and, for some large campuses, the California Energy Commission.3 State-mapped fault and fire hazard zones and stressed groundwater basins narrow the options.456

Last reviewed · 10 min read · BlackForge Data Centers

Key takeaways

  • CAISO is the largest of eight balancing authorities in California; LADWP, IID, BANC and others operate separately and set their own large-load terms.7
  • The CPUC approved an interim PG&E Rule 30 in July 2025 for transmission-level loads that pay up front for needed transmission work; refunds await a later decision.2
  • Resource adequacy runs on the CPUC’s slice-of-day framework from 2025, with hourly obligations for each month placed on load-serving entities.8
  • SB 57 (2025) ordered a CPUC study of data center cost shifts due January 1, 2027,9 and a September 2026 package led by SB 886 directs the CPUC to set data center tariffs by January 1, 2028.10
  • Alquist-Priolo fault zones, seismic hazard zones, the 2025 fire hazard severity zone maps and groundwater basin status are core screens.45
Public data · Power trackerLarge-load power tracker39 utilities and their data center power rules, from public filings.

01How California’s power system is organized

The California Independent System Operator is the largest balancing authority in the state, covering about 132,000 square miles across portions of all 58 counties and a small part of Nevada; the other seven balancing authorities mainly operate within their own service territories.1 Those seven are the Balancing Authority of Northern California (BANC), the Imperial Irrigation District, the Los Angeles Department of Water and Power, the Turlock Irrigation District, PacifiCorp West, NV Energy and the Western Area Lower Colorado area.7 A Los Angeles site can therefore face a different grid operator than a Santa Clara one. See ISOs, RTOs and utility territories.

Inside CAISO, retail service is split among investor-owned utilities, municipal utilities and community choice aggregators, which buy energy for customers while the investor-owned utility keeps the wires and handles interconnection. The wires utility and the energy supplier can therefore be different entities, and both matter.

Who does what for a California data center
RoleTypical entityWhat it controls
Grid operatorCAISO, or one of seven other balancing authoritiesMarket prices, transmission planning, generator queue
Wires utilityInvestor-owned or municipal utilityInterconnection studies, substation and line work, delivery charges
Load-serving entityUtility or community choice aggregatorEnergy supply and resource adequacy procurement
Land use and CEQA lead agencyCity or county; for some large campuses, the Energy CommissionZoning, discretionary approvals, environmental review
Air permitsLocal or regional air districtBackup generator permits and operating limits

Fig. 1California’s grid and data center rules at a glance

balancing authority areas in California
8
CAISO footprint, in all 58 counties
132,000 sq mi
planning reserve margin, 2025 RA year
17%
deadline for CPUC data center cost study
Jan. 1, 2027
Sources: California Energy Commission (grid figures),17 CPUC (2025 margin)8 and Mayer Brown (SB 57).9

02Resource adequacy and who pays for new load

California does not run a centralized capacity auction. Resource adequacy is handled through state programs: the CPUC sets requirements for the load-serving entities it regulates, and municipal utilities set their own. From the 2025 compliance year the CPUC uses a slice-of-day framework, under which each load-serving entity receives a 24-hour obligation for each of the 12 months and must show capacity for every hour, not only a monthly peak, and it adopted a 17% planning reserve margin for 2025.811

For a large new load, the practical question is who procures its capacity and how fast. Covering a flat, around-the-clock data center profile takes storage, firm resources and solar in combination, and procurement runs on multi-year cycles separate from the substation and transmission work.

Cost allocation is now written into statute. SB 57, as signed in 2025, dropped an earlier proposal for a data center tariff and instead directs the CPUC to assess whether investor-owned utility costs for new data center load shift costs to other customers, with the assessment due by January 1, 2027.9 In September 2026 the governor signed a broader package. SB 886 directs the CPUC to establish data center tariffs by January 1, 2028 so that operators pay the infrastructure upgrade and generation costs of their service, with an early termination fee for customers that leave within 10 years of interconnection or fail to ramp up as planned; AB 2383 adds wildfire mitigation and other distribution-level costs; and SB 887 ends blanket environmental review exemptions for data centers while offering a faster path for projects that meet state water and energy standards.10 The CPUC still has to write the tariffs, so check the status of that proceeding for any specific project.

03Large-load interconnection and PG&E Rule 30

Interconnection runs through the wires utility, which studies the load, scopes the substation and line work and coordinates with CAISO where the bulk grid is affected. Major new lines in California take years to permit and build, so the realistic energization date matters as much as the capacity; see power timelines and interconnection queues.

In November 2024 PG&E applied for Electric Rule 30, a uniform tariff meant to cut the time and cost of transmission-level interconnection applications.12 On July 24, 2025, the CPUC, noting that case-by-case handling of these customers had been slow and resource-intensive, approved an interim Rule 30 available only to applicants that agree to pay up front for necessary transmission infrastructure, with the terms and cost allocation of any refunds left to a future decision.2 Check whether a final decision has replaced the interim terms; see large-load tariffs and electric service agreements.

Mayer Brown reported that PG&E saw a 40% jump in data center hookup requests that would require 3.5 GW, and that Silicon Valley Power, Santa Clara’s municipal utility, raised rates by 5% to cover infrastructure for data center demand.9 Load pockets near major metros can be tightly constrained; inland sites may have more grid room but less fiber and harsher summer heat.

04CEQA, air permits and local approvals

The California Environmental Quality Act applies to discretionary approvals by state and local agencies. Depending on the project and the agency, review may be an exemption, a negative declaration or a full environmental impact report, and CEQA documents can be challenged in court. A site that can be built under existing zoning with ministerial permits faces a different path than one that needs a rezoning or general plan amendment. See the data center permitting process.

For some large Santa Clara campuses, the California Energy Commission rather than the city has been the CEQA lead agency for the backup generating facility. The Laurelwood Data Center, for example, was reviewed under an Energy Commission mitigated negative declaration covering fifty-five 3.0 MW emergency standby diesel generators.3 The Bay Area Air District still issues the generator permits; its authority to construct for seven backup diesel generators at the Great Oaks South facility in San Jose limits them to emergency use plus up to 20 hours a year of testing and maintenance.13

Fig. 2Two entitlement paths for a California campus

Faster

Ministerial path

  • Use allowed under existing industrial zoning
  • Building and grading permits only
  • Little or no CEQA review at the local level
  • Air district permits for generators still required

Slower

Discretionary path

  • Rezoning, general plan amendment or use permit
  • Negative declaration or full EIR
  • Public hearings and possible CEQA litigation
  • Mitigation measures become permit conditions
General patterns; the level of CEQA review depends on the agency and project, and generator permits apply on either path.
  • Air districts set limits on generator emissions and testing hours, and rules differ by district; see air permits for data center generators.
  • The state energy code includes efficiency requirements for computer rooms that affect cooling design.
  • Coastal zone sites face additional review.
  • Farmland under long-term conservation contracts can take years to release for development.

05Seismic, wildfire and other hazards

The California Geological Survey publishes Earthquake Zones of Required Investigation that combine Alquist-Priolo Earthquake Fault Zones for surface fault rupture, under the 1972 Alquist-Priolo Act, with Seismic Hazard Zones for liquefaction and earthquake-induced landslides, under the 1990 Seismic Hazards Mapping Act. Cities and counties rely on them, sellers must disclose when property lies in a mapped zone, and coverage varies by quadrangle.4 See seismic risk for data centers.

Wildfire hazard is mapped in fire hazard severity zones. In 2025 CAL FIRE released updated maps for Local Responsibility Areas, the first major revision in more than a decade, which show moderate, high and very high zones rather than only very high hazard areas; local agencies adopt the maps by ordinance and cannot lower the state’s classifications.514 Utilities may also de-energize lines during high fire risk, which affects how long a campus must run on backup power. See wildfire risk for data centers.

Common California hazard checks
HazardWhat to checkWhy it matters
Surface fault ruptureAlquist-Priolo Earthquake Fault ZonesConstruction across active faults is restricted
Liquefaction and landslideSeismic Hazard Zone maps, geotechnical studyFoundation design and cost
Wildfire2025 fire hazard severity zones, vegetation, accessInsurance, building standards, utility shutoffs
FloodFEMA flood maps, levee-protected areasSome Central Valley land sits behind levees
Sea level riseLow-lying coastal and bay areasLong-term exposure for coastal sites

Fig. 3Sample hazard screen of one inland parcel

Illustrative
  • PassFault ruptureOutside any Alquist-Priolo Earthquake Fault Zone.
  • WatchLiquefactionSouth quarter in a Seismic Hazard Zone; needs geotechnical work.
  • PassFire hazardNot in a mapped moderate, high or very high zone.
  • WatchFlood and leveesLevee-protected area; check levee certification.
  • FailGroundwaterBasin in critical overdraft; no new pumping assumed.
Illustrative sample. Not a real parcel; it shows how state hazard maps feed an early screen.

06Water and climate

Under the Sustainable Groundwater Management Act, the Department of Water Resources identified 21 basins and subbasins in critical overdraft; groundwater sustainability agencies there had to adopt plans by January 31, 2020 and must reach sustainability by January 31, 2040.6 DWR’s first round of plan decisions in 2022 covered 20 basins and 42 plans, which it called the first step in a 20-year effort.15 A site that depends on new pumping in a stressed basin is a weak bet; see water rights and groundwater for data centers.

Water use disclosure is also on the agenda. In 2025 the governor vetoed a bill that would have required data centers to report water use to suppliers before seeking permits, citing reluctance to impose rigid reporting rules on the sector.9 The 2026 package instead requires water-related disclosures before local approval.10 Many municipal systems offer reclaimed water for cooling, and designs that use little water, such as air-cooled chillers or closed-loop liquid cooling, often have an easier path.

Climate varies widely. Coastal areas have mild temperatures that favor economization for much of the year. Inland valleys and deserts are hot in summer, which raises cooling loads and peak demand.

07Land and fiber

Land near the established data center markets, especially Santa Clara and the wider Bay Area, is expensive and rarely available in large, contiguous blocks, so redevelopment of industrial and brownfield sites is common. Larger tracts are more available inland, at the cost of distance from fiber hubs and, often, more complex agricultural and water issues.

Fiber is strong in the major metros, with subsea cable landings along the coast and long-haul routes along the main interstate corridors. Developers who need large power blocks and lower land costs often compare California sites with neighboring markets such as Nevada.

08A California site checklist

Most California screens turn on three questions: who serves the site, whether the use needs discretionary approval, and whether the parcel sits in a mapped hazard zone or stressed basin.

  1. 01Confirm the balancing area, the wires utility and the load-serving entity.
  2. 02Ask how large loads are studied and charged today, including Rule 30 terms in PG&E territory.
  3. 03Ask who procures resource adequacy for the load and on what timeline.
  4. 04Determine whether the project needs discretionary approval, what level of CEQA review is likely, and whether the Energy Commission would be lead agency.
  5. 05Check the local air district’s generator rules and testing-hour limits.
  6. 06Screen fault zones, seismic hazard zones, fire hazard severity zones and flood or levee exposure.
  7. 07Confirm water source, groundwater basin status and recycled water availability.

For an outside screen, you can get a site reviewed.

CalculatorIT load to grid demand →CalculatorCooling water use →

Common questions

Does CAISO cover all of California?

No. CAISO is the largest of eight balancing authority areas in California, but LADWP, the Imperial Irrigation District, BANC, the Turlock Irrigation District and others operate separately.7 Those utilities set their own terms for large loads, so identifying the balancing area and serving utility is one of the first steps for any site.

What is CEQA and does it apply to data centers?

The California Environmental Quality Act requires agencies to evaluate environmental effects before making discretionary approvals. A data center needing a rezoning or use permit will usually go through CEQA review, and the California Energy Commission has been lead agency for the backup generating facilities of some large Santa Clara campuses.3 Projects allowed by right may face lighter local review, though air district permits still apply.

How do wildfire risks affect California data center sites?

CAL FIRE’s 2025 maps for Local Responsibility Areas show moderate, high and very high fire hazard severity zones, which affect building standards and insurance.5 Utilities may also de-energize lines during high fire risk, which can lengthen how long a campus runs on backup power and affects generator sizing, fuel storage and air permits.

Are backup generators hard to permit in California?

They can be. Air districts limit emissions and non-emergency hours; the Bay Area Air District’s permit for one San Jose facility allows emergency use plus up to 20 hours a year of testing and maintenance.13 Check district rules early and compare diesel, gas and battery options before the design is fixed.

Notes

  1. 1.California Energy Commission, “Who Is Responsible for Transmission,” n.d. energy.ca.gov
  2. 2.California Public Utilities Commission, “CPUC Streamlines Electric Grid Connections for High-Energy Users Like Data Centers and EV Chargers,” 2025. webproda.cpuc.ca.gov
  3. 3.CEQAnet, “Laurelwood Data Center (MECP1 Santa Clara 1, LLC), Land Use Permit Number PLN2019-13742,” n.d. ceqanet.lci.ca.gov
  4. 4.California Geological Survey, “Earthquake Zones of Required Investigation, Dublin Quadrangle,” n.d. conservation.ca.gov
  5. 5.City of Cathedral City, “CAL FIRE Releases Updated 2025 Fire Hazard Severity Zone Maps for Local Responsibility Areas,” 2025. discovercathedralcity.com
  6. 6.California Department of Water Resources, “Critically Overdrafted Basins,” n.d. water.ca.gov
  7. 7.California Energy Commission, “Balancing Authority Areas,” 2025. catalog.data.gov
  8. 8.California Public Utilities Commission, “Fact Sheet on RA D.24-06-004 on Track 1 of RA OIR R.23-10-011,” 2024. cpuc.ca.gov
  9. 9.Mayer Brown, “Efforts to Regulate California Data Centers Falter, For Now,” 2025. mayerbrown.com
  10. 10.Mayer Brown, “California’s Governor Signs Nation’s Most Comprehensive Data Center Laws, Reshaping Regulation of Energy, Water and Land Use,” 2026. mayerbrown.com
  11. 11.Ascend Analytics, “California’s Slice of Day Framework: Understanding Impacts on Resource Adequacy and Resource Value,” n.d. ascendanalytics.com
  12. 12.Stoel Rives, “CPUC Weighs Cost Recovery for Interconnection of Large Load, Including Data Centers,” 2025. stoel.com
  13. 13.CEQAnet, “Great Oaks South Backup Generating Facility (SV18), State Clearinghouse ID 2020100431,” n.d. ceqanet.lci.ca.gov
  14. 14.Napa County, “2025 Fire Hazard Severity Zone Maps,” 2025. napacounty.gov
  15. 15.California Natural Resources Agency, “DWR Takes Next Steps Towards Groundwater Sustainability,” 2022. resources.ca.gov

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.