BlackForge Data Centers

Site selection by state

Data Center Site Selection in Wisconsin

Wisconsin has moved quickly from a minor data center market to the home of two of the largest AI campuses in the Midwest, Microsoft’s in Mount Pleasant and the Vantage, Oracle and OpenAI campus in Port Washington.12 For a new site, the decisive questions are which utility serves it and on what terms: in April 2026 the Public Service Commission approved a modified We Energies Very Large Customer tariff that makes large loads pay the full cost of the generation built for them, with a 15-year minimum term.3 The state’s 2023 sales and use tax exemption,4 MISO transmission expansion5 and the Great Lakes water rules6 round out the screen.

Last reviewed · 8 min read · BlackForge Data Centers

Key takeaways

  • We Energies’ Very Large Customer tariff, approved with changes in April 2026, applies to loads from 100 MW, requires a 15-year minimum term and assigns 100% of dedicated resource costs to the customer.3
  • Wisconsin exempts equipment and building materials for WEDC-certified data centers from sales and use tax, with investment minimums of $50–150 million depending on county population.47
  • Wisconsin sits in MISO, which approved a $21.8 billion Tranche 2.1 transmission portfolio in December 2024, including 765 kV lines into the state.5
  • Lake Michigan water is governed by the Great Lakes Compact; communities just west of the basin divide face diversion limits that shape where water-intensive sites can go.6
  • State-level data center rules stalled in 2026: the Assembly passed AB 840, but the Senate adjourned in March without a vote, so local zoning and utility tariffs set most terms.89

01Why Wisconsin is on developers’ maps now

Wisconsin was not a traditional data center market. That changed when Microsoft began building in Mount Pleasant, south of Milwaukee, on land assembled for the earlier Foxconn project. Microsoft has described its Fairwater AI campus there as one of its most powerful, with three buildings and about 1.2 million square feet on 315 acres, and it has pledged a second campus of similar scale, bringing its stated Wisconsin investment to more than $7 billion.1

In October 2025, Vantage Data Centers announced Lighthouse, a roughly $15 billion campus in Port Washington, north of Milwaukee, to host OpenAI and Oracle workloads as part of the Stargate program. It is planned at close to 1 GW across four buildings.210 By early 2026, further billion-dollar proposals were emerging elsewhere in the state while lawmakers and regulators debated who should pay for the power they need.11

The draw is a mix of large industrial parcels near Lake Michigan, a cool climate that suits free cooling, a regulated utility system willing to build generation, and a sales tax exemption that dates to 2023. The constraints are equally real: rising scrutiny from regulators and residents, generation that must be built rather than found, and water rules unlike those in most states. For how these factors compare across the Midwest, see our guide to MISO data center site selection.

02We Energies’ Very Large Customer tariff

We Energies proposed its Very Large Customer (VLC) and Bespoke Resources tariffs in 2025 after several large data center prospects entered its service territory.3 The Public Service Commission of Wisconsin approved them on April 24, 2026, but with substantial changes pushed by intervenors.312 As approved, the framework:

  • Lowers the eligibility threshold to 100 MW, well below the level We Energies proposed, so mid-sized campuses fall under it.3
  • Requires a minimum initial contract term of 15 years.3
  • Drops a proposed capacity-only option under which a customer would have paid for 75% of a generating plant’s cost, leaving a full-benefits model in which the customer pays 100% of the costs of resources built for it.3
  • Adds reporting requirements so the commission and the public can see how the tariff and individual agreements work in practice.3

For site selection, the tariff means that a campus in We Energies territory is effectively paying for new generation and grid upgrades as a condition of service, and committing to it for a long period. That shifts the analysis from “is there spare capacity?” to “can the project carry a dedicated resource portfolio and a 15-year commitment?” Trade press has read the decision as a likely template for other Midwestern commissions.12 Our guide to large-load tariffs and electric service agreements explains the common terms, such as minimum bills, contract demand and exit fees.

03Generation and transmission: building the supply

Wisconsin’s data center wave is being served largely by new generation. In May 2025 the PSC unanimously approved about $1.5 billion of We Energies gas plants, an 1,100 MW plant in Oak Creek and a 128 MW plant in the Town of Paris in Kenosha County, with cost caps and other conditions. Demand from the Microsoft campus was a major factor in the case, and the plants are expected online in 2027 and 2028.13

For Port Washington, Vantage has said it is paying for about 2,000 MW of new supply, including wind and solar, while the campus itself needs roughly 1,400 MW.14 That pattern, where the developer funds a portfolio larger than its own load, is what the Bespoke Resources structure was designed to handle.

On the transmission side, Wisconsin is in MISO. MISO’s board approved the $21.8 billion Long Range Transmission Planning Tranche 2.1 portfolio in December 2024, 24 projects with a 765 kV backbone that extends into Wisconsin.5 Those lines still need state siting approval and will take years to build, so they matter for a campus planned for the 2030s more than for near-term power.

Fig. 1Wisconsin’s power buildout in numbers

New We Energies gas capacity approved in 2025
1,228 MW
Approved cost of the two gas plants
$1.5B
MISO Tranche 2.1 portfolio, Dec 2024
$21.8B
New backbone lines into the state
765 kV
Selected figures from the PSC gas plant approval and MISO’s Tranche 2.1 portfolio.135

04The 2023 data center sales tax exemption

2023 Wisconsin Act 19, the state budget, created a sales and use tax exemption for qualified data centers, effective October 1, 2023. It covers tangible personal property used exclusively to develop, construct, renovate or repair a qualified data center, such as servers, networking gear and other hardware, whether or not the property becomes part of the real estate.4

The Wisconsin Economic Development Corporation certifies projects, and the exemption applies only to purchases after WEDC’s certification date. The project must reach a minimum qualified investment within five years of certification, scaled by county population.47

Minimum qualified investment for the Wisconsin exemption
County populationMinimum investment within 5 years
More than 100,000$150 million4
50,001–100,000$100 million4
50,000 or fewer$50 million4

The lower thresholds in small counties give rural sites a modest advantage on paper, though at hyperscale the threshold is rarely the binding issue. Because certification precedes eligibility, sequence matters: apply early, before major equipment orders. Our state-by-state sales tax exemption comparison puts Wisconsin’s program in context, and a tax advisor should confirm eligibility for any specific project.

05Water and the Great Lakes Compact

Much of eastern Wisconsin’s appeal is Lake Michigan, but the Great Lakes Compact bans diversions of basin water outside the basin, with narrow exceptions. The basin boundary near the lake’s southwest shore runs close to the shoreline, so parcels only a few miles inland can sit outside it. Mount Pleasant qualifies as a “straddling community,” one of the exceptions, which is how the Wisconsin DNR in 2018 approved Racine drawing up to 7 million gallons a day for the former Foxconn development.6

Records released by Racine in 2025 put Microsoft’s first-phase peak at about 234,000 gallons per day, or 2.8 million gallons a year, rising to 702,000 gallons per day and 8.4 million gallons a year in later phases.6 Microsoft says more than 90% of its Fairwater facility will use closed-loop liquid cooling, with outside air for the rest and water only on the hottest days.1 For a new site, check three things early: which side of the basin divide the parcel is on, whether the serving water utility has an approved diversion or headroom, and whether the design can stay within those limits. Our guide to municipal water and sewer capacity covers the utility side.

06State legislation and local approvals

In January 2026 the Assembly passed AB 840, 53–44, which would have required closed-loop cooling, annual water-use reporting to the DNR and protections against shifting utility costs to other ratepayers.8 The Senate adjourned its 2025–26 floor session in March 2026 without voting on that bill or a competing Democratic version.9 As of this review, Wisconsin has no statewide data center siting law beyond the tax exemption and PSC tariff authority, which leaves most land-use decisions with villages, cities, towns and counties.

Local processes have drawn close public attention as proposals multiply.11 Expect rezoning, development agreements and tax incremental financing to be negotiated locally, and expect questions about water, noise and electric rates at every hearing. Our guides to community engagement and development agreements cover how to prepare.

Fig. 2Wisconsin data center milestones

  • Sales tax exemption takes effectOct 2023
  • MISO approves Tranche 2.1Dec 2024
  • VLC tariff proposedMar 2025
  • Gas plants approvedMay 2025
  • Port Washington announcedOct 2025
  • AB 840 passes, Senate adjournsJan–Mar 2026
  • PSC approves modified tariffApr 2026
010203040months from Oct 2023
Key policy and project events, plotted from October 2023; each date is cited where it appears in the text above.39

07How to screen a Wisconsin site

  1. 01Identify the electric utility and its large-load terms. In We Energies territory, test the project against the 100 MW threshold, the 15-year term and full cost responsibility.3
  2. 02Find the nearest 345 kV substation and ask whether MISO Tranche 2.1 projects change the picture for your timeline.5
  3. 03Map the Great Lakes basin divide and the water utility’s approved supply before assuming lake water is available.6
  4. 04Confirm county population to know the sales tax investment threshold, and plan WEDC certification ahead of purchases.4
  5. 05Read local zoning and any recent data center ordinances; with no statewide siting law, local rules govern.9
  6. 06Check wetlands, floodplain and farmland status; much of southeast Wisconsin’s available acreage is agricultural.

A desktop screen can answer most of these before an option is signed. If you want a second opinion on a parcel, you can get a site reviewed.

Common questions

Does Wisconsin have a data center sales tax exemption?

Yes. Since October 1, 2023, property used exclusively to build or equip a WEDC-certified qualified data center is exempt from sales and use tax.4 The project must reach $50–150 million of investment within five years, depending on county population.7

What is the We Energies Very Large Customer tariff?

It is a rate framework for customers of 100 MW or more, approved with modifications by the PSC in April 2026. Customers sign for at least 15 years and pay the full cost of generation and other resources built to serve them.3

Is Wisconsin in MISO or PJM?

Wisconsin utilities are in MISO, which runs the wholesale market and regional transmission planning. MISO’s $21.8 billion Tranche 2.1 plan includes 765 kV lines into the state.5

Can a data center in Wisconsin use Lake Michigan water?

Only within the limits of the Great Lakes Compact. Sites outside the basin generally cannot receive lake water unless they qualify for an exception, such as a straddling community like Mount Pleasant.6 Confirm with the water utility and the DNR.

Did Wisconsin pass a data center law in 2026?

No. The Assembly passed AB 840 in January 2026, but the Senate adjourned in March without a vote.89 Check for new proposals in the next session.

Notes

  1. 1.W.Media, “Microsoft unveils its largest AI data center yet; to spend US$7 billion on Wisconsin facility,” 2025. w.media
  2. 2.Data Center Dynamics, “OpenAI, Oracle, and Vantage plan Stargate Wisconsin data center, expected to be close to a gigawatt,” 2025. datacenterdynamics.com
  3. 3.Clean Wisconsin (via Urban Milwaukee), “State regulators make substantial modifications to We Energies AI data center tariff plan,” 2026. urbanmilwaukee.com
  4. 4.Wisconsin Department of Revenue, “Qualified Data Center,” n.d. revenue.wi.gov
  5. 5.American Public Power Association, “MISO board approves historic transmission plan to strengthen grid reliability,” 2024. publicpower.org
  6. 6.Wisconsin Examiner, “Racine releases records showing Microsoft data center would use 8 million gallons of water per year,” 2025. wisconsinexaminer.com
  7. 7.Wisconsin Economic Development Corporation, “Data Center Sales and Use Tax Exemption,” 2023. wedc.org
  8. 8.Wisconsin Examiner, “Assembly passes GOP bill to regulate data centers in Wisconsin,” 2026. wisconsinexaminer.com
  9. 9.Spectrum News 1, “Wisconsin Senate adjourns without a vote on data centers,” 2026. spectrumnews1.com
  10. 10.BizTimes Milwaukee, “OpenAI and Oracle will run Port Washington data center as part of Stargate project,” 2025. biztimes.com
  11. 11.WUWM Milwaukee Public Media, “As Wisconsin weighs who should pay, another possible billion-dollar data center emerges,” 2026. wuwm.com
  12. 12.Data Center Knowledge, “Wisconsin’s Data Center Tariff Signals a New Regulatory Baseline,” 2026. datacenterknowledge.com
  13. 13.WUWM Milwaukee Public Media, “We Energies natural gas plants approved by Public Service Commission,” 2025. wuwm.com
  14. 14.TMJ4 News, “Vantage data center energy costs: who pays the bill in Port Washington, Wisconsin,” n.d. tmj4.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Related guides

More in Site selection by state