Data Center Site Selection in West Virginia

West Virginia’s pitch to data centers rests on the Power Generation and Consumption Act (House Bill 2014), signed in April 2025, which lets certified high impact data centers of 90 MW or more run on their own behind-the-meter microgrids.12 The same law takes zoning and building permits out of local hands for those projects, which speeds entitlement but has drawn strong local opposition.34 Sites that pair flat, buildable land with gas supply, transmission and water are the ones that can use the program.

Last reviewed · 8 min read · BlackForge Data Centers

Key takeaways

  • HB 2014 was signed on April 30, 2025 and created a statewide certified microgrid program for high impact data centers.1
  • A high impact data center must have a critical IT load of at least 90 MW and be placed in service after July 1, 2025.2
  • Certified projects are exempt from county and municipal zoning, building permits and code enforcement; 2026 bills sought to restore local control.35
  • Microgrid owners may sell 10% of their output into the wholesale market, so a site is still judged by its grid connection.6
  • Coal produced about 88% of the state’s utility-scale generation, and West Virginia exports much of its power to the regional grid.7
  • Appalachian Power’s settled large-load terms call for at least 100 MW, a 12-year initial term and an 80% minimum purchase, pending PSC approval.8

01Why West Virginia is pitching itself to data centers

West Virginia is an energy-producing state looking for new demand. It is the nation’s second-largest coal producer and was the fifth-largest producer of marketed natural gas in 2023, about 95% of it from shale wells.7 Coal-fired plants supplied about 88% of in-state utility-scale generation, and West Virginians use only about three-fifths of the electricity the state generates, so the rest flows to neighboring states on the regional grid.7

Fig. 1West Virginia’s power system at a glance

of utility-scale generation from coal
~88%
of in-state generation used in-state
~3/5
generated in 2024
50.6 TWh
net summer capacity
15,128 MW
Generation and capacity are 2024 figures; the coal share is of utility-scale generation.79

In 2024 the state generated about 50.6 million megawatt-hours from 15,128 MW of net summer capacity.9 For a developer, the attraction is not cheap retail power alone but the chance to build next to gas supply and existing high-voltage infrastructure, and to do it under a state law written for that purpose. The trade-offs are rugged terrain, limited flat land, thinner fiber than the Northern Virginia corridor and a politics of local control that is still being argued. Our PJM site selection guide covers the regional market West Virginia’s utilities sit in, and the Virginia guide covers the market next door.

02HB 2014 and certified microgrid districts

Governor Patrick Morrisey signed House Bill 2014, the Power Generation and Consumption Act, on April 30, 2025, in Point Pleasant, near the planned Monarch campus in Mason County.1 It was a priority bill, passed alongside House Bill 2002, which was meant to simplify and speed up project permitting.1 The law creates a statewide certified microgrid program meant to support new on-site power, use coal and natural gas, and fund capacity to stabilize the grid.1

Legally, the act rebuilt an older program. West Virginia already let certain high impact industrial facilities take renewable power from behind-the-meter generators instead of the regulated utility; the 2025 amendments extended it to high impact data centers and dropped the renewable-only restriction.10 Microgrid owners can sell 10% of the power they generate into the wholesale market.6

Fig. 2Path to a certified high impact data center

  1. 01

    Site and load plan

    Critical IT load of 90 MW or more.

  2. 02

    Petition

    Filed with the Secretary of Commerce.

  3. 03

    Certification

    Microgrid district and high impact data center.

  4. 04

    State permits

    Air, water and other state approvals still apply.

  5. 05

    Build and operate

    Placed in service after July 1, 2025.

Simplified from the Department of Commerce rule process; the rule itself governs the details.211

The Department of Commerce’s rule, released for comment in November 2025, defines a high impact data center as a facility with a critical IT load of 90 MW or more placed in service after July 1, 2025, and sets out how to petition for certification as a microgrid district and a high impact data center.2 In March 2026 the Legislature passed and the governor signed House Bill 4983, which authorizes that rule; it took effect from passage.11 Read the final rule text before scoping a project, since the thresholds in early drafts and press coverage are not always the same. Our microgrids and battery storage guide explains the engineering side.

03Local control limits and the property tax split

The most consequential feature for entitlement is preemption. Under the law, certified high impact data centers and microgrids are not subject to county or municipal zoning or land use ordinances, and not subject to local building permits, inspections or code enforcement.3 A project that qualifies does not go through a local rezoning at all.

The bill also redirects property tax. As proposed, property taxes from high impact data centers would be split as follows:4

Proposed distribution of high impact data center property taxes under HB 2014.[^4]
RecipientShare
Fund to reduce personal income tax50%
Host county or counties30%
All counties, per capita10%
Economic Enhancement Grant Fund (water, wastewater)5%
Electric Grid Stabilization Fund (utility coal and gas plants)5%

Local officials objected to both the lost revenue and the lost zoning and permitting authority, and residents gathered more than 2,000 petition signatures against the bill.41 In January 2026 legislators introduced Senate Bill 658 and House Bill 4509 to restore local control over these projects and certain power facilities.5 Check the current status of those bills, and the enacted tax distribution, with counsel before relying on either. Preemption removes a hearing, but it does not remove opposition, which now shows up in state permit appeals instead. See our guides on community engagement and property taxes.

04Coal country sites and on-site gas generation

The two best-known projects show what West Virginia sites look like in practice. Both are built around natural gas generation rather than utility service.

Fig. 3Two West Virginia data center power projects

Ohio River

Monarch, Mason County

  • 2,380 acres north of Point Pleasant
  • Along W.Va. 62, the river and CSX rail
  • 2 GW initial generation, 8 GW planned
  • Acquired by Nscale in 2026

Highlands

Ridgeline, Tucker County

  • Gas plant to fuel a data center
  • Between the towns of Davis and Thomas
  • Air permit issued after 1,600+ comments
  • Permit upheld on appeal in 2026
Status as reported through 2026; each point is sourced in the paragraphs below.

Monarch was announced by Fidelis New Energy and 8090 Industries and is expected to generate 8 GW from natural gas when fully built.12 The 2,380-acre campus sits along W.Va. 62, the Ohio River and CSX tracks north of Point Pleasant, and starts with 2 GW of generation plus battery storage sized for AI load swings.13 Nscale acquired the project in 2026.14 River frontage, rail and gas access are the features to look for on similar Ohio Valley parcels, along with the floodplain mapping that comes with river land.

Tucker County shows the other side. The Department of Environmental Protection approved an air permit for Fundamental Data’s proposed Ridgeline gas plant and data center between Davis and Thomas after receiving more than 1,600 comments.15 Tucker United, the West Virginia Highlands Conservancy and the Sierra Club appealed, and the Air Quality Board upheld the permit in 2026.16 With local zoning preempted, state air permits became the main venue for opposition.

Former coal plant and mine land can offer transmission, rail, water and industrial history, but reclaimed mine ground needs careful geotechnical investigation, and legacy environmental conditions call for a Phase I ESA. Our onsite generation and natural gas guide covers the generation questions.

05Utility service, PJM and large-load terms

Most of West Virginia is served by Appalachian Power (an AEP company) or by FirstEnergy’s Mon Power and Potomac Edison, and all of them sit inside PJM. A project that wants grid service, or a grid backstop for a microgrid, deals with both the utility’s tariff before the West Virginia Public Service Commission and PJM’s planning and capacity market. See PJM capacity prices and data centers.

Appalachian Power asked the Commission for large-load terms, and Google objected to the proposed contract length and minimum purchase obligation.8 The PSC’s consumer advocate proposed a compromise modeled on Google’s agreement with Indiana Michigan Power, and Appalachian Power, Google and a group of manufacturers then reached a settlement.8 Its main terms:

  • A minimum contract capacity of 100 MW at an individual site.8
  • An initial contract term of at least 12 years.8
  • A commitment to buy at least 80% of the power the customer expects to use.8
  • Approval by the Public Service Commission before the terms take effect.8

Confirm the approved version with the utility. These terms matter even for microgrid projects, since a project that sells 10% of its output to the wholesale market or wants standby service still needs an interconnection.6 Our guide to large-load tariffs and electric service agreements explains minimum bills and exit fees.

06How to screen a West Virginia site

  1. 01Decide early whether the project will seek certification as a high impact data center (90 MW or more of critical IT load) or take utility service.2
  2. 02Map gas pipelines, transmission and the serving utility, and check PJM interconnection timing for any grid tie.
  3. 03Measure truly buildable acreage: slopes, mine history, floodplain along the rivers and access roads.
  4. 04Plan for state permits, especially air permits for on-site generation, and for public comment and appeals.1516
  5. 05Track 2026 bills on local control and any changes to the certification rule.511
  6. 06If taking utility service, model the Appalachian Power or FirstEnergy large-load terms at your ramp.8

The site due diligence checklist and the buildable acreage tool cover the general items. If you hold or are evaluating land in West Virginia, you can get a site reviewed.

Common questions

What is West Virginia’s HB 2014?

House Bill 2014, the Power Generation and Consumption Act, was signed on April 30, 2025.1 It created a certified microgrid program that lets high impact data centers run on their own behind-the-meter generation, sell 10% of output into the wholesale market and skip local zoning and building permits.63

What counts as a high impact data center in West Virginia?

Under the Department of Commerce rule, a facility with a critical IT load of 90 MW or more placed in service after July 1, 2025.2 Certification is by petition to the Secretary of Commerce, under a rule authorized by House Bill 4983 in 2026.11

Can West Virginia counties block a data center?

Not through zoning, if the project is a certified high impact data center or microgrid, because the law exempts those projects from county and municipal zoning, permits and code enforcement.3 Bills to restore local control were introduced in 2026, so confirm the current law.5 State permits, such as air permits, can still be contested.16

Does a West Virginia data center have to use coal power?

No. The microgrid program was described as supporting coal and natural gas, and the 2025 amendments removed the old renewable-only limit, but the law does not require a particular fuel.110 The largest announced projects plan natural gas generation.1215

Is West Virginia in PJM?

Yes. Appalachian Power, Mon Power and Potomac Edison all operate within PJM, so grid-connected projects face PJM interconnection and capacity costs as well as state tariffs. The state is a net power exporter, using about three-fifths of what it generates.7

Notes

  1. 1.West Virginia Watch, “Morrisey signs priority bill meant to incentivize data centers, microgrids locating in WV,” 2025. westvirginiawatch.com
  2. 2.The Parkersburg News and Sentinel, “Site certification rules released for data center microgrid law,” 2025. newsandsentinel.com
  3. 3.West Virginia Center on Budget and Policy, “HB 2014 Fact Sheet,” 2025. wvpolicy.org
  4. 4.West Virginia Center on Budget and Policy, “HB 2014 Would Preempt Local Control, Divert Millions Annually in Local Property Tax Revenue for Schools and Public Safety to Fund Income Tax Cuts,” 2025. wvpolicy.org
  5. 5.West Virginia Legislature, “Senate Bill 658 (2026 Regular Session), Bill History,” 2026. bills.wvlegislature.gov
  6. 6.pv magazine USA, “West Virginia’s new law bets big on microgrids,” 2025. pv-magazine-usa.com
  7. 7.U.S. Energy Information Administration, “West Virginia State Energy Profile,” n.d. eia.gov
  8. 8.West Virginia Public Broadcasting, “Data Center Deal Struck Between Appalachian Power, Google,” n.d. wvpublic.org
  9. 9.U.S. Energy Information Administration, “West Virginia Electricity Profile,” n.d. eia.gov
  10. 10.Hogan Lovells, “West Virginia expands microgrid access for high impact data centers,” 2025. hlc.com
  11. 11.West Virginia Legislature, “House Bill 4983 (2026 Regular Session), Bill History,” 2026. bills.wvlegislature.gov
  12. 12.West Virginia Public Broadcasting, “Utility-Scale Microgrid Coming To Mason County,” n.d. wvpublic.org
  13. 13.The Herald-Dispatch, “Fidelis ready to proceed on Mason County data center site,” n.d. herald-dispatch.com
  14. 14.The Weirton Daily Times, “W.Va. officials praise latest changing of hands of Fidelis Mason County data center project,” 2026. weirtondailytimes.com
  15. 15.The Inter-Mountain, “DEP approves air quality permit for proposed Tucker County power plant,” 2025. theintermountain.com
  16. 16.The Inter-Mountain, “Tucker power plant’s air permit upheld,” 2026. theintermountain.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.