Data Center Site Selection in Tennessee

Almost every Tennessee data center buys power from a local power company that resells TVA electricity, so TVA’s rules set the terms: contracts above 5 MW get TVA review, loads above 100 MW need board approval, and a data center rate with a capacity commitment charge applies from October 1, 2026.12 The state’s qualified data center program exempts computer and cooling equipment from sales tax and cuts the sales tax on electricity to 1.5% for projects investing more than $100 million.3 Memphis shows the other side of fast growth: xAI’s gas turbines drew a long air permit fight,4 and its water needs led to a dedicated recycling plant.5

Last reviewed · 8 min read · BlackForge Data Centers

Key takeaways

  • TVA approved a wholesale data center rate class on August 20, 2026; new or expanding loads above 5 MW pay a capacity commitment charge from October 1, 2026, about a 10% average bill impact phased over three years.1
  • Local power companies are the retail counterparty, but TVA reviews contracts over 5 MW and its board must approve requests over 100 MW.2
  • A qualified data center must invest more than $100 million over three years and create 15 jobs at 150% of the state average occupational wage to get sales tax exemptions and a 1.5% rate on electricity.3
  • Shelby County’s July 2025 permit for 15 xAI turbines followed reports of about 35 turbines operating on site, and it set deadlines to remove temporary units.46
  • A Nashville legislator plans to file a bill in 2027 to freeze new data center tax exemptions for three years, so the incentive is a policy risk to track.7
Public data · Power trackerTennessee data center power rules1 utility tracked, from public filings.

01TVA and the local power companies

Tennessee has no retail electricity choice and, for most of the state, no investor-owned utility. The Tennessee Valley Authority generates and transmits power and sells it at wholesale to local power companies, municipal utilities such as Memphis Light, Gas and Water and Nashville Electric Service, and cooperatives such as Middle Tennessee Electric. The local power company signs the retail contract, but for a data center TVA is never far away: contracts larger than 5 MW are reviewed by TVA, and requests above 100 MW require TVA board approval.2

Fig. 1Who sets the terms for a Tennessee data center

  1. 01TVA boardApproves requests above 100 MW and sets wholesale rates
  2. 02TVAGeneration, transmission and review of contracts above 5 MW
  3. 03Local power companyCity utility or co-op; retail contract and distribution
  4. 04Data center campusPays the data center rate class from October 2026
Simplified. The local power company is the retail utility, but TVA reviews and approves large loads.21

That structure has two consequences for site selection. First, the utility service territory still matters, because local power companies differ in distribution capacity, staff experience with large loads and willingness to build substations. Middle Tennessee Electric’s chief executive, for example, has said the co-op must keep encouraging TVA to add generation to serve larger prospects, including data centers.8 Second, a sound load request has to work for both organizations: the local utility’s distribution plan and TVA’s generation and transmission plan. See our large-load interconnection guide for how those studies usually run.

02TVA’s 2026 data center rate

On August 20, 2026, the TVA board approved a new wholesale rate class built for data centers.1 Starting October 1, 2026, new or expanding data center loads above 5 MW fall under a capacity commitment charge attached to TVA’s data center rate schedules, designed to recover the incremental capacity costs those customers create.1 TVA expects the all-in average billing impact for data center customers to be about 10%, phased in over three consecutive fiscal years.1 TVA presented the rate as a way to protect household ratepayers, a theme covered in our guide to data centers and electricity ratepayers.1

The rate arrived alongside fast load growth. A 2026 report found that data center electricity use in the Tennessee Valley grew sevenfold from 2020 to 2025, to 8.3 million MWh, and that the pipeline of demand is about five times TVA’s current data center load.9 TVA is building new gas plants, partly in response to that forecast.9

Fig. 2Data centers on the TVA system

growth in Valley data center use, 2020–20259
7×
Valley data center consumption, 20259
8.3M MWh
pipeline vs. current data center load9
~5×
average bill impact of new rate, phased in1
~10%
Figures from the 2026 rate decision and a 2026 report on Valley demand.19

For underwriting, model the capacity commitment charge as a real cost from the first phase, and treat the 100 MW board step as a schedule item. Our guide to large-load tariffs and electric service agreements explains how charges like this usually interact with minimum bills and ramp schedules.

03Memphis: xAI, gas turbines and the air permit debate

xAI’s Colossus supercomputer in south Memphis made Shelby County the most visible test of on-site generation for AI campuses. Residents and activists said Colossus ran gas turbines without the right permits, and aerial imagery from April 2025 showed about 35 turbines on site.6 TVA separately approved xAI’s request for more grid power for the facility.10

On July 2, 2025, the Shelby County Health Department, which runs the local air program, approved xAI’s request for 15 permanent gas turbines with advanced controls and set timelines for removing the temporary units.4 The permitted turbines can generate up to about 247 MW.11 The NAACP and other groups appealed the permits, arguing that the temporary turbines should not have been treated as exempt from permitting.12 The episode is a useful reminder that turbines used as bridge power still need air permits, and that the permit hearing is where community opposition concentrates. Our guides to air permits for data center generators and on-site generation cover the permit types.

Fig. 3xAI Memphis power permitting milestones

  • ~35 turbines seen on siteAerial imagery, April 2025
  • 15-turbine permit issuedShelby County Health Department, July 2025
  • Southaven 41-turbine permitMississippi Permit Board, March 2026
051015months from April 2025
Approximate placement of reported events in Memphis and, across the state line, Southaven.6413

xAI has since expanded across the state line in DeSoto County, where Mississippi regulators permitted 41 turbines in March 2026 to power its second Memphis data center; see our Mississippi guide.13 Memphis also illustrates a siting pattern: large industrial sites near TVA plants and transmission attract the biggest loads, which then shape local politics for everyone who follows.

04Water: the Memphis Sand aquifer and reuse

Memphis draws its drinking water from the Memphis Sand aquifer, and early talks between the city, MLGW and xAI focused on limiting the campus’s use of that supply.5 The result is the Colossus Water Recycling Plant, which will take effluent from the city’s T.E. Maxson wastewater treatment facility and treat it with a ceramic membrane bioreactor to deliver up to 13 million gallons per day of reuse water to the Colossus campus and TVA’s Allen combined cycle plant.5 Its designers estimate it will preserve about 5 billion gallons a year of aquifer water.5 xAI broke ground on the plant in 2025.14

Few projects can fund their own treatment plant, but the model is portable: a site near a large wastewater plant can offer reclaimed water for cooling and an easier public story than new groundwater wells. Elsewhere in Tennessee, check municipal water and sewer capacity early and consider closed-loop cooling where supply is tight.

05Nashville and Middle Tennessee

Tennessee has about 60 data centers, and more than a third of them are in the greater Nashville area.15 In a growing metro, sites close to the city tend to suit smaller enterprise and colocation buildings, while large campuses look to surrounding counties for land. Growth is still raising questions: DC BLOX’s plans in Nashville drew scrutiny over what they could mean for electricity costs and environmental impacts.16

For larger projects, the counties around Nashville are where the land is, and they are served by a mix of municipal utilities and cooperatives such as Middle Tennessee Electric, whose leadership has said it expects the region’s growth to continue and will need more TVA generation.8 Confirm which local power company serves each parcel, then test zoning, sewer and transmission. Our zoning guide covers the common paths.

06Sales tax: the qualified data center program

Tennessee’s main data center incentive runs through the sales tax. To qualify, a data center must, over a three-year period, invest more than $100 million in real or tangible property or software used in its operation in Tennessee, and create at least 15 net new full-time jobs paying at least 150% of the state average occupational wage, with minimum health care coverage.3 Qualified centers can buy computers, software, related devices, installation, repair and service contracts, plus backup power and cooling equipment used primarily for the operation, without sales tax, and pay a reduced 1.5% sales tax rate on electricity.3 The Department of Revenue issues a certificate after approving an application.3

Tennessee qualified data center sales tax terms
ItemRequirement or benefit
InvestmentMore than $100 million over three years3
JobsAt least 15 net new full-time jobs at 150% of state average occupational wage3
EquipmentExempt: computers, software, backup power and cooling equipment3
ElectricityReduced 1.5% sales tax rate3
ProcessApplication to the Department of Revenue; certificate on approval3

The 1.5% electricity rate matters more than it looks: for a large campus, electricity is the largest operating cost, so the reduced rate compounds every year. It is also under political pressure. In September 2026, Rep. Aftyn Behn of Nashville said she would file legislation for the 2027 session to stop issuing data center exemptions for three years while the Department of Revenue reports on their cost.7 Compare the program with other states in our sales tax exemptions by state guide.

07How to screen a Tennessee site

  1. 01Identify the local power company and ask how it coordinates large loads with TVA.2
  2. 02Model the capacity commitment charge from October 2026 and plan for TVA board approval above 100 MW.12
  3. 03Confirm the project can meet the $100 million and 15-job thresholds before counting on the sales tax benefits.3
  4. 04If on-site generation is in the plan, scope the air permit with the state or local air program early.4
  5. 05Check water and sewer capacity, and look for reuse water near large treatment plants.5
  6. 06Run the physical screens: floodplain, karst and slope in Middle and East Tennessee, and buildable acreage.

Tennessee competes with Alabama, Kentucky and Georgia for the same projects, and the Southeast guide compares them. If you want an outside read on a specific parcel, you can get a site reviewed.

CalculatorIT load to grid demand →CalculatorCooling water use →CalculatorLand for a load →

Common questions

Who supplies power to data centers in Tennessee?

Local power companies, municipal utilities and cooperatives, deliver the power and sign the retail contract, and they buy it wholesale from TVA. TVA reviews contracts above 5 MW and its board must approve requests above 100 MW.2

What is TVA’s new data center rate?

Approved on August 20, 2026, it applies a capacity commitment charge to new or expanding data center loads above 5 MW from October 1, 2026.1 TVA expects an average bill impact of about 10%, phased in over three fiscal years.1

Does Tennessee exempt data centers from sales tax?

Yes, for qualified data centers that invest more than $100 million over three years and create at least 15 jobs paying 150% of the state average occupational wage.3 They get exemptions on computers, software, backup power and cooling equipment, and a 1.5% sales tax rate on electricity.3 A 2027 proposal would pause new exemptions for three years.7

Why was xAI’s Memphis data center controversial?

Residents and activists said turbines ran without proper permits, with about 35 seen on site in April 2025.6 The Shelby County Health Department then permitted 15 permanent turbines and set deadlines to remove temporary ones, a decision the NAACP and others appealed.412

How do Memphis data centers handle water?

xAI is building the Colossus Water Recycling Plant to supply up to 13 million gallons per day of treated wastewater to its campus and TVA’s Allen plant, reducing use of the Memphis Sand aquifer.514

Notes

  1. 1.WSMV, “TVA approves 10% rate spike for data centers to protect household rate payers,” 2026. wsmv.com
  2. 2.Yahoo News, “TVA keeps an eye on data center proposals,” n.d. yahoo.com
  3. 3.Tennessee Department of Revenue, “Sales Tax for Data Centers, Headquarters and Call Centers,” n.d. tn.gov
  4. 4.Action News 5, “Health dept. grants permit for xAI turbines,” 2025. actionnews5.com
  5. 5.Gresham Smith, “Colossus Water Recycling Plant,” n.d. greshamsmith.com
  6. 6.Inside Climate News, “In South Memphis, Elon Musk’s Colossus Operated Gas Turbines Without Appropriate Permits, Residents and Activists Claim,” 2025. insideclimatenews.org
  7. 7.Tennessee Lookout, “Nashville lawmaker proposes pause on data center tax exemptions,” 2026. tennesseelookout.com
  8. 8.Capital Analytics, “Chris Jones, President & CEO, Middle Tennessee Electric,” n.d. capitalanalyticsassociates.com
  9. 9.WSMV, “New report warns of rising electricity costs in TN as demand for data centers grow,” 2026. wsmv.com
  10. 10.Renewable Energy World, “TVA approves Elon Musk’s controversial data center plan for more power,” n.d. renewableenergyworld.com
  11. 11.TechCrunch, “xAI gets permits for 15 natural gas generators at Memphis data center,” 2025. techcrunch.com
  12. 12.Tennessee Lookout, “NAACP, others appeal xAI turbine permits for Memphis data center,” n.d. tennesseelookout.com
  13. 13.Mississippi Free Press, “Mississippi permit board grants xAI’s request for 41 Southaven gas turbines to power Memphis data center,” 2026. mississippifreepress.org
  14. 14.Daily Memphian, “‘This is what progress looks like,’ xAI breaks ground on water recycling plant,” 2025. dailymemphian.com
  15. 15.WPLN, “Tennessee has 60 data centers. Nashville probably has more than you think,” n.d. wpln.org
  16. 16.WPLN, “What DC BLOX’s murky plans in Nashville signal for electricity costs, environmental impacts,” n.d. wpln.org

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.