Key takeaways
- Consumers Energy’s tariff for loads of 100 MW or more requires a 15-year minimum term, 80% minimum billing demand and collateral, with up to five years to ramp.28
- DTE’s Saline Township contracts run at least 19 years, and the data center must be curtailed before other customers in an emergency.91
- DTE reported 2.4 GW of executed data center agreements and a further 5–6 GW pipeline in mid-2026; its general large-load tariff was still pending.105
- The enterprise data center exemption requires a $250 million investment and 30 jobs at 150% of the regional median wage, certified by the Michigan Strategic Fund through 2029.3
- Many townships adopted temporary data center moratoriums in 2026, and a Senate bill would require water permits above 550,000 gallons a day.611
01How Michigan compares for data center siting
Michigan’s pitch combines two large regulated utilities that are actively seeking data center load, a renewed tax exemption, a cool climate and access to Great Lakes water. Natural gas supplied about 45% of the state’s net generation in 2024, more than four times its share a decade earlier, and renewables supplied 12%, led by wind.12 DTE Electric and Consumers Energy, the state’s two largest utilities, have both set terms meant to make large loads pay their own way.12
The constraints are local. Township boards control zoning, and many paused data center applications in 2026 while they wrote rules.6 Water use, often hidden behind nondisclosure agreements with local governments, became a statewide political issue.13 For the wholesale market and planning context, see our MISO guide; for nearby comparisons, see Ohio, Indiana and Wisconsin.
Fig. 1DTE’s data center load, mid-2026
- executed data center agreements
- 2.4 GW
- Saline Township campus
- 1,383 MW
- further pipeline opportunities
- 5–6 GW
02Consumers Energy and DTE large-load terms
Consumers Energy’s large-load tariff
On November 6, 2025, the Michigan Public Service Commission (MPSC) approved terms of service between Consumers Energy and large data centers in Case No. U-21859, aiming to capture grid benefits while ensuring new large loads pay the full cost of serving them.2 The tariff applies to customers of 100 MW or more, or aggregated loads of 100 MW under common ownership where individual sites are 20 MW or more. It requires a minimum 15-year contract, a minimum bill of 80% of contracted demand, a ramp period of up to five years, a $100,000 project proposal fee and collateral equal to half the exit fee, provided as a letter of credit or cash rather than a parent company’s pledge. Customers may request a one-time capacity reduction of up to 10% with four years’ notice.8
DTE Electric and the Saline Township contracts
DTE served its first very large load through special contracts. The MPSC approved them unanimously on December 18, 2025, for a 1,383 MW data center in Saline Township being built by Oracle and Related Digital for OpenAI. Approval was conditioned on DTE absorbing any costs it cannot recover from the Oracle subsidiary, and on the data center’s load being reduced or interrupted before service to other customers in an emergency.1 The contracts require a minimum 19-year term rather than five years, 80% minimum billing demand rather than the standard 50–60%, and termination payments of up to 10 years of minimum billing. The Commission directed DTE to propose a general very-large-load tariff, filed as Case U-22061, which was still being litigated in August 2026; check the docket for a final order.95
Fig. 2Consumers tariff vs. DTE Saline contracts
100 MW+, U-21859
Consumers Energy tariff
- 15-year minimum term
- 80% minimum billing demand
- Ramp of up to five years
- Collateral of half the exit fee
1,383 MW, U-21990
DTE Saline contracts
- 19-year minimum term
- 80% minimum billing demand
- Termination payment up to 10 years
- Curtailed first in emergencies
Our guide to large-load tariffs and electric service agreements explains how minimum bills, exit fees and curtailment terms affect underwriting.
03The 2024 sales and use tax exemption
Public Acts 181 and 207 of 2024 amended the Use Tax Act and General Sales Tax Act to exempt data center equipment used by a qualified entity in an enterprise data center; the exemptions took effect on April 2 and April 17, 2025.3 Michigan already had a narrower exemption from 2015, and the new law extends it to 2050 for qualified data centers and to 2065 for facilities on brownfield or former power plant sites.43 House passage was delayed by concerns from environmental groups about data centers’ energy and water use.4
- Capital investment of at least $250 million.3
- At least 30 full-time jobs paying 150% or more of the prosperity region’s median wage, maintained through 2050, or 2065 for brownfield and former power plant sites.3
- No use of certain electric rates, such as the long-term industrial load rate.3
- No certain property tax benefits unless the local government approves by resolution.3
- A certificate from the Michigan Strategic Fund; none will be issued after December 31, 2029.3
The property tax condition matters for landowners and townships: abatements are not automatic, so local negotiation remains part of the deal. Confirm current requirements with the Michigan Economic Development Corporation and tax counsel, and see our sales tax exemptions by state and property taxes guides.
04Saline Township: what the first mega-campus shows
The Saline Township project shows the full Michigan approval path. It sits on farmland south of Ann Arbor; the township board voted against rezoning the land in September 2025 and later settled after landowners and Related Digital sued. The MPSC approved DTE’s contracts without a contested case, which drew criticism from Attorney General Dana Nessel and environmental groups.141
State environmental permits followed. In January 2026 the Department of Environment, Great Lakes, and Energy (EGLE) granted air and wetland permits that allow about 9 acres of wetlands to be filled and 15 diesel backup generators to be installed.15 The developers held a construction celebration in June 2026 for a campus of three single-story 550,000-square-foot data halls, and they say its closed-loop, non-evaporative cooling will keep daily water use comparable to an office building.16
Fig. 3Approval path for a Michigan mega-campus
- 01
Township zoning
Rezoning denied, then settled after litigation.
- 02
Utility contracts
MPSC approved DTE special contracts, Dec. 2025.
- 03
EGLE permits
Air and wetland permits, Jan. 2026.
- 04
Construction
Groundbreaking celebrated June 2026.
Our guides to wetlands and generator air permits cover those two permit tracks.
05Water, the Great Lakes and local moratoriums
Michigan already regulates large water withdrawals, and depending on design and location, EGLE review of a data center may cover withdrawals as well as other permits under the Natural Resources and Environmental Protection Act.7 Those rules sit within the Great Lakes–St. Lawrence River Basin Water Resources Compact, a binding agreement among eight states and two Canadian provinces. Critics note that withdrawal volumes are often shielded by nondisclosure agreements between companies and local governments.13
In June 2026 Senate Democrats introduced a package that would go further. Senate Bill 1046 would require a permit and public hearings for facilities consuming more than 550,000 gallons of water per day and let EGLE monitor data center wastewater; Senate Bill 1047 addresses electricity rates and large-load utility classes.11 As of the latest reporting, the package had not passed.
Townships moved faster. Many adopted temporary moratoriums in 2026 while they wrote zoning rules: Lenox Charter Township’s runs four months with one possible extension, and Springfield Township’s 180-day pause bars data center plans from being accepted for review.6 Plan for closed-loop cooling and clear water disclosures, and see our guide to moratoriums.
06How to screen a Michigan site
- 01Confirm the serving utility and whether the load will fall under Consumers’ 100 MW tariff or DTE’s pending large-load tariff.85
- 02Model a 15- to 19-year commitment with 80% minimum billing and the required collateral before signing land options.9
- 03Check whether the township has a moratorium or new data center zoning rules.6
- 04Test the project against the $250 million and 30-job thresholds for the tax exemption, and whether a brownfield or former power plant site extends the term.3
- 05Screen wetlands and generator air permitting early, as at Saline Township.15
- 06Choose a cooling design that keeps water use low and can be disclosed, given pending water legislation.11
If you want an independent read on a specific tract, you can get a site reviewed.
Common questions
Does Michigan have a data center sales tax exemption?
Yes. Laws enacted in 2024 exempt data center equipment for qualified enterprise data centers that invest at least $250 million and create at least 30 jobs at 150% of the regional median wage. The exemption runs to 2050, or 2065 for brownfield and former power plant sites, and certificates must be issued by December 31, 2029.3
What does Consumers Energy require from data centers?
For loads of 100 MW or more, a contract of at least 15 years, a minimum bill of 80% of contracted demand, collateral and a $100,000 proposal fee, with up to five years to ramp.8 The MPSC approved the tariff in November 2025.2
Who is building the Saline Township data center?
Oracle and Related Digital are building it for OpenAI as part of the Stargate initiative, with DTE Electric supplying 1,383 MW under contracts the MPSC approved in December 2025.1 Construction was celebrated in June 2026.16
Are Michigan townships banning data centers?
Many adopted temporary moratoriums in 2026, typically lasting a few months while they write zoning rules, rather than permanent bans.6 Check the township’s current ordinances before committing to a site.
Notes
- 1.Michigan Public Service Commission, “MPSC approves DTE Electric energy contracts for data center,” 2025. michigan.gov
- 2.Michigan Public Service Commission, “MPSC approves terms of service between Consumers Energy and data centers,” 2025. michigan.gov
- 3.Michigan Economic Development Corporation, “Enterprise Data Center Sales & Use Tax Exemption,” n.d. michiganbusiness.org
- 4.Data Center Dynamics, “Michigan extends data center tax breaks in bid to lure hyperscalers,” 2025. datacenterdynamics.com
- 5.Earthjustice, “Michigan’s Public Service Commission Grapples with AI Data Center Load,” 2026. earthjustice.org
- 6.Baldori Law, “Michigan Data Center Tracker,” 2026. baldorilaw.com
- 7.State of Michigan, “Data Centers,” n.d. michigan.gov
- 8.Varnum LLP, “MPSC Approves Consumers Energy Tariff for Large Data Centers,” 2025. varnumlaw.com
- 9.T&D World, “Michigan Regulators Approve DTE Data Center Power Contracts with Added Ratepayer Protections,” 2025. tdworld.com
- 10.MarketBeat, “DTE Energy Q2 Earnings Call Highlights,” 2026. marketbeat.com
- 11.Michigan Senate Democrats, “Legislation would shield Michigan workers, consumers, and natural resources from impact of data center projects,” 2026. senatedems.com
- 12.U.S. Energy Information Administration, “Michigan State Profile and Energy Estimates: Analysis,” 2025. eia.gov
- 13.McDonald Hopkins, “The next water war: AI data centers and Michigan’s most precious resource,” 2026. mcdonaldhopkins.com
- 14.Planet Detroit, “DTE data center contracts approved,” 2025. planetdetroit.org
- 15.Planet Detroit, “Saline data center air, wetlands permits,” 2026. planetdetroit.org
- 16.Tradeline, “Oracle and OpenAI Celebrate Construction of Stargate Data Center,” 2026. tradelineinc.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Site selection by state
- Data Center Site Selection in Texas: Grids, SB 6, Water and Incentives
- Data Center Site Selection in Virginia: Power, GS-5, Zoning and Tax Rules
- Data Center Site Selection in Georgia: Georgia Power, PSC Rules, Water and Taxes
- Data Center Site Selection in Arizona: APS, SRP, TEP, Water and Heat
- Data Center Site Selection in Illinois: ComEd, Ameren, PJM vs. MISO and the Incentive Pause
- Data Center Site Selection in Nevada: NV Energy, Reno and Las Vegas, Water Rules and GOED Abatements
- Data Center Site Selection in Oregon
- Data Center Site Selection in Iowa
- Data Center Site Selection in North Carolina
- Data Center Site Selection in South Carolina
- Data Center Site Selection in Pennsylvania
- Data Center Site Selection in Indiana
- Data Center Site Selection in Minnesota
- Data Center Site Selection in Nebraska
- Data Center Site Selection in Oklahoma
- Data Center Site Selection in Utah
- Data Center Site Selection in Washington State
- Data Center Site Selection in Louisiana
- Data Center Site Selection in Mississippi
- Data Center Site Selection in Alabama
- Data Center Site Selection in Tennessee
- Data Center Site Selection in Kentucky
- Data Center Site Selection in Missouri
- Data Center Site Selection in Kansas
- Data Center Site Selection in New Mexico
- Data Center Site Selection in Wyoming
- Data Center Site Selection in North Dakota
- Data Center Site Selection in New York: NYISO, Hydropower and the 2026 Permit Pause
- Data Center Site Selection in Arkansas: Entergy, SWEPCO, 2025 Laws and Local Rules
- Data Center Site Selection in Colorado: Xcel’s Large-Load Tariff, Water and Local Rules
- Data Center Site Selection in Idaho
- Data Center Site Selection in West Virginia
- Data Center Site Selection in Maryland
- Data Center Site Selection in Montana
- Data Center Site Selection in South Dakota
- Data Center Site Selection in Florida