Key takeaways
- Fairfax County’s September 2024 amendment set a 200-foot residential setback and required noise studies before and after construction.14
- Loudoun County required special exception approval for data centers in its IP, GI and MR-HI districts in March 2025, and in September 2026 voted for a temporary pause on certain data center and substation applications.26
- Prince William County voted 8–0 on September 22, 2026 to shrink its data center overlay from about 9,698 acres to roughly 3,650 acres and require special use permits for most new projects.37
- Overlays can steer data centers to suitable land or, when reduced, remove by-right rights from thousands of acres.7
- Grandfathering and vesting windows are short and specific; missing a filing date can change the approval path.87
01How data center ordinances are built
For years many codes had no data center use at all, so staff classified projects as warehouses, offices or utilities, and large campuses often went through with administrative site plan review. That is changing quickly. Most new ordinances use three tools in combination. First, a definition and a use table that says where data centers are permitted, where they need a special exception or conditional use, and where they are banned. Second, use-specific standards that apply wherever the use is allowed, such as setbacks, equipment screening and noise limits. Third, an overlay district: a mapped area laid over the base zoning that adds rights, adds rules, or both.
Fig. 1How zoning rules stack on a data center parcel
- 01Base zoning districtIndustrial, employment or planned district use table.
- 02Overlay districtAdds or removes data center eligibility in a mapped area.
- 03Use-specific standardsSetbacks, noise, screening, height and design rules.
- 04Approval pathBy-right review, or special exception with a hearing.
- 05Conditions and site planProject-specific limits enforced at site plan stage.
For the difference between by-right, special use and rezoning paths in general, see zoning for data centers. The policy that sits above all of this, and that often drives the ordinance text, is covered in comprehensive plans and future land use maps.
02Northern Virginia: Fairfax, Loudoun and Prince William
The three largest Northern Virginia counties rewrote their rules within about two years, and the direction was the same in each: fewer by-right approvals and more written standards. These changes matter well beyond Virginia, because other jurisdictions often borrow from them. See the Northern Virginia data center market for the market context.
| County | Action and date | Key effects |
|---|---|---|
| Fairfax | Zoning ordinance amendment adopted Sept. 10, 2024, effective Sept. 111 | 200 ft from residential lot lines; equipment enclosed or screened; noise studies before and after construction4; special exception for almost all data centers8 |
| Loudoun | Phase 1 plan and zoning changes adopted March 18, 20252 | Special exception required in IP, GI and MR-HI districts; applications accepted before Feb. 12, 2025 could continue under prior rules2 |
| Loudoun | Phase 2 under way; pause on certain applications voted Sept. 20266 | Review of height, onsite power generation, energy storage, noise and parking9 |
| Prince William | Overlay overhaul adopted Sept. 22, 20263 | Overlay cut from about 9,698 to roughly 3,650 acres; most new projects need a special use permit7 |
Fairfax’s rules are the most detailed on separation. Coverage of the amendment reported that data center buildings must be 200 feet from the lot line of adjacent residential property and that equipment such as backup generators must be 300 feet away, with pre- and post-construction noise studies to show compliance with the county noise ordinance.4 Site plans accepted by July 16, 2024 could proceed under the old ordinance if approved by July 16, 2025.8
Loudoun’s Phase 2 is meant to produce new policy guidance and use-specific standards for data centers and substations, and the county says it is not expected to change the plan or zoning maps.9 The published schedule called for a planning commission hearing in November 2026 and board action in early 2027, and in September 2026 the board voted for a temporary pause on certain legislative applications for data centers and substations while that work continues, with a formal resolution scheduled for October 20, 2026.96
Fig. 2Northern Virginia data center zoning changes
- Fairfax amendmentAdopted Sept. 10, 2024
- Loudoun Phase 1Adopted March 18, 2025
- Prince William overlay reviewInitiated March 2026, adopted Sept. 22
- Loudoun Phase 2 and pausePause vote Sept. 2026; board action expected 2027
03Overlay districts: steering the use, and taking it back
An overlay lets a locality pick the land where data centers make sense, usually near transmission and away from homes, without rezoning every parcel. Prince William County’s Data Center Opportunity Zone Overlay District allowed data centers by right on land within it. The 2026 amendment substantially reduced the overlay and, under the new framework, most future projects need a special use permit.3 Parcels stay in the reduced overlay only if they meet one or more of five county-defined eligibility pathways, and Venable notes that being vested for development is one route.103 Owners had 90 days to qualify, and a motion to cut that period to zero failed 5–3.7
Fig. 3Prince William data center overlay, before and after
- Overlay before 2026 amendment9,698
- Overlay after amendment3,654
acres
Overlays are also appearing outside Virginia. Provo, Utah, amended its data center overlay chapter, including permitted uses and development standards, in an ordinance adopted April 28, 2026.11 Montgomery County, Maryland, introduced a zoning text amendment in January 2026 that would define data centers as a new use, list the zones where they may locate as conditional uses, and add 500 feet to minimum setbacks where a site abuts residential zoning.12 In July 2026 the council also adopted an 18-month pause on new data centers, so check the adopted text rather than the introduced version.13 Neighboring Frederick County adopted a Critical Digital Infrastructure overlay through a comprehensive plan amendment, which the comprehensive plan guide covers.
04Setbacks from homes and property lines
Distance from residential property is now the most common data-center-specific standard. Rules differ in what they measure from (lot line, district boundary or the house itself) and what they apply to (the building, the equipment yard or both). Separate, larger distances for generators, chillers and other noise-generating equipment are increasingly common.414
Fig. 4Residential setbacks in recent rules and drafts
- Fairfax, building (adopted)200
- Fairfax, equipment (adopted)300
- Franklin Co., IN, building (draft)300
- Franklin Co., IN, equipment (draft)500
- Greenwood Co., SC, lot line (proposed)200
- Greenwood Co., SC, homes (proposed)1,000
feet
Franklin County, Indiana’s March 2026 draft, for example, would require a 300-foot setback along street frontage and property lines shared with other districts, and would place chillers, exhaust fans and backup generators at least 500 feet from any property line unless a third-party acoustic study shows compliance at the line.14 On a long, narrow parcel, setbacks like these can remove a large share of the usable area, so run them through a buildable acreage test early. The engineering side is covered in noise, setbacks and buffers.
05Noise standards written into zoning
Noise used to be left to a general county noise ordinance, which often exempted HVAC equipment. Data center rules increasingly close that gap. In 2023 Prince William County removed the commercial HVAC exemption from its nighttime sound limits and directed a review of noise walls, buffering, berms, setbacks, screening and building height for data centers.15 Fairfax requires noise studies before and after construction.4
- Property-line limits in dBA: Greenwood County, South Carolina’s proposed ordinance would cap sound at 60 dBA at the boundary of nonindustrial uses or districts and 70 dBA next to industrial ones.5 In July 2026 the county council adopted a one-year moratorium on data centers.16
- Study-based compliance: some drafts allow equipment closer than the default setback if an acoustic study shows limits are met.14
- Before-and-after measurement: baseline and post-construction studies, as in Fairfax, create a record that enforcement can use.
- Process-based control: some cities rely on a conditional use permit and council approval rather than fixed numbers.17
For site screening, the question is not only the limit but where it is measured and at what time of day. A nighttime limit at a residential property line next to the site can govern generator testing schedules, chiller selection and yard placement.
06Design, height and operational standards
Beyond distance and sound, ordinances now reach into how the building looks and how the campus runs. Fairfax requires equipment to be enclosed or screened by a wall or barrier to reduce visual and noise impacts, and its amendment added design requirements and size limits that vary by location.1 Loudoun’s Phase 2 is reviewing building height, onsite power generation and energy storage alongside noise and parking.9 Aurora, Illinois, as described in APA’s Planning magazine, requires a conditional use permit, limits new facilities to specific industrial and planned development zones, bans evaporative cooling and requires renewable energy and battery backup.17
Standards on cooling type, onsite generation and storage can affect the power and water plan as much as the site plan, so they belong in early design. Facade, materials and screening requirements are covered in more depth in architectural and visual standards.
07Grandfathering, vesting and how to screen a site
Every recent rewrite came with a cutoff. Loudoun let applications accepted before February 12, 2025 continue without special exception approval;2 Fairfax let site plans accepted by July 16, 2024 proceed under the prior rules if approved within a year;8 Prince William gave owners 90 days to qualify for the reduced overlay.7 Venable described the Prince William change as a closing window for by-right development, with vesting through an approved plan of development as one way to stay eligible.3 Windows like these are short, and pending amendments are often the best warning; see data center moratoriums and local restrictions.
- 01Read the current use table and the data center definition, and confirm the approval path for the parcel’s district.
- 02Check whether the parcel is in, or near the edge of, a data center overlay, and whether any amendment to it is pending.
- 03Map the setbacks for buildings and for equipment from every residential lot line and district boundary.
- 04Find the noise standard, the measurement point and any nighttime limit, and whether studies are required.
- 05Note design, height, cooling and onsite generation standards that could change the building or utility plan.
- 06Confirm grandfathering and vesting dates in writing with staff and land use counsel.
Ordinance text changes faster than most acquisition timelines, so treat any summary, including this one, as a starting point and read the adopted text. If you want a parcel checked against current zoning, setbacks and utilities together, get a site reviewed.
Common questions
What is a data center overlay district?
It is a mapped zone laid over the base zoning that changes the rules for data centers inside it, usually by allowing the use or adding standards. Prince William County’s overlay allowed by-right data centers until its 2026 amendment cut its size and required special use permits for most new projects.37
Are data centers still allowed by right in Loudoun County?
Generally no. Since March 18, 2025, data centers in the IP, GI and MR-HI districts need special exception approval, with a grandfathering path for certain applications accepted before February 12, 2025.2 In September 2026 the board also paused consideration of certain data center and substation applications while it works on new standards.6
How far must a data center be from homes?
It depends on the ordinance. Fairfax County requires 200 feet from residential lot lines for the building and 300 feet for equipment such as generators, unless the building sits between the equipment and the residential lot line.14 Recent drafts elsewhere range up to 1,000 feet from homes.5
What noise limits apply to data centers?
Many use the general noise ordinance, but data-center rules increasingly add property-line dBA limits, nighttime limits or required studies. One proposed South Carolina ordinance sets 60 dBA at nonindustrial boundaries and 70 dBA at industrial ones.5 Fairfax requires studies before and after construction.4
Does an approved site plan protect a project from a new ordinance?
Often it helps, but the rules vary by state and by each ordinance’s transition clause. Fairfax tied its grandfathering to site plans accepted by July 16, 2024 and approved by July 16, 2025.8 Confirm vesting with land use counsel.
Notes
- 1.Fairfax County, Virginia, “Board of Supervisors Approves New Data Center Zoning Ordinance Amendment,” 2024. fairfaxcounty.gov
- 2.Loudoun County, Virginia, “Data Center Standards & Locations,” n.d. loudoun.gov
- 3.Venable LLP, “The Window for By-Right Data Center Development,” 2026. venable.com
- 4.Data Center Frontier, “Northern Virginia’s Fairfax County Tightens Data Center Rules,” 2024. datacenterfrontier.com
- 5.Index-Journal, “Residents press county on data center rules at information session,” 2026. indexjournal.com
- 6.Loudoun County, Virginia, “Statement: Loudoun Board Enacts Pause on Data Centers,” 2026. loudoun.gov
- 7.Bisnow, “Prince William County Drastically Shrinks By-Right Data Center Map,” 2026. bisnow.com
- 8.McGuireWoods, “Fairfax County Board Adopts Data Center Zoning Changes,” 2024. mcguirewoods.com
- 9.Loudoun County, Virginia, “Phase 2: Data Center Standards & Locations,” n.d. loudoun.gov
- 10.Prince William County, Virginia, “DPA2026-00006: Data Center Opportunity Zone Overlay District (DCOZOD),” 2026. pwcva.gov
- 11.City of Provo, Utah, “Ordinance 2026-13,” 2026. provo.municipal.codes
- 12.Montgomery County Council, Maryland, “Zoning Text Amendment 26-01, Introduction Packet (January 20, 2026),” 2026. montgomerycountymd.gov
- 13.Montgomery Community Media, “Montgomery County pauses new data centers for 18 months,” 2026. mymcmedia.org
- 14.Franklin County, Indiana, “Data Center Regulations Draft v2.0,” 2026. franklincounty.in.gov
- 15.Prince William County, Virginia, “Prince William Board of County Supervisors Votes to Initiate Amendments to County Code Regarding Data Centers,” 2023. pwcva.gov
- 16.FOX Carolina, “Greenwood Co. Council approves final reading of one-year moratorium on data centers,” 2026. foxcarolina.com
- 17.American Planning Association, Planning Magazine, “Feeding the Beast Behind the AI,” 2026. planning.org
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Zoning, permitting & community
- FAA Airspace, Airports and Height Limits for Data Centers
- The Data Center Permitting Process, Step by Step
- Community Engagement and Local Concerns About Data Centers
- Data Center Tax Incentives: What to Look For
- Development Agreements for Data Center Projects: What They Cover
- Annexation, Jurisdiction and Utility Service Areas for Data Center Sites
- Site Plan Review for Data Centers: What It Covers and How Long It Takes
- Building and Fire Codes for Data Centers: IBC, NFPA 75 and 76, NFPA 855
- Data Center Sales Tax Exemptions by State: Thresholds, Pauses and Repeals (2026)
- Public Hearings for Data Center Projects: Notice, Testimony and How to Prepare
- Traffic Impact Studies for Data Centers: Trip Generation, Construction Traffic and Road Improvements
- Impact Fees and Utility Connection Fees for Data Centers: How They Work and What Is Negotiable
- Contested Data Center Projects: Lessons From Prince William, Peculiar, Tucson and Other Public Fights
- State Data Center Legislation: 2025–2026 Trends in Tariffs, Incentives, Water and Moratoriums