Key takeaways
- The ITE Trip Generation Manual has a data center land use (code 160) with rates per 1,000 square feet, but it rests on very few surveyed sites.41
- Operational traffic is mostly shift workers and deliveries, but floor area still drives the ITE estimate: one 3.8 million square foot Florida proposal projected 2,793 daily trips.15
- Construction is the heavy phase: one large Ohio project expected more than 1,000 vehicles a day at peak, and phased campuses can carry heavy trucks for years.26
- Whether a study is required depends on local and state triggers, often around 100 peak-hour trips or 1,000 daily trips locally,78 and 5,000 daily trips for a Virginia rezoning.9
- Counties increasingly ask for road use agreements, pre-construction road surveys and paid traffic control, not only turn lanes.310
01What a traffic impact study is and when one is required
A traffic impact study (also called a traffic impact analysis, TIA, or transportation impact study) is an engineering report that estimates how many vehicle trips a project will generate, assigns those trips to the road network, and compares future traffic conditions with and without the project. It ends with a list of improvements, if any, needed to keep intersections operating at the level the reviewing agency requires. It is usually filed with a rezoning, special use permit or site plan, and it is one of the first technical studies neighbors and staff read.
Triggers vary by jurisdiction. Many local codes require a full study when a project will generate about 100 peak-hour trips or 1,000 daily trips. North Richland Hills, Texas, uses 1,000 vehicles a day or 100 trips in the peak direction, and St. James, North Carolina, uses 100 peak-hour or 1,000 daily trips based on the latest ITE Trip Generation Manual.78 States can add their own layer. Virginia’s rule treats a rezoning as substantially affecting state highways when it produces more than 5,000 daily trips at its connection to a state-controlled road (in localities where VDOT maintains the secondary system), and the locality must then send the package to VDOT for review.9
Because operational data center traffic is light, some campuses fall below local triggers on paper. Staff often ask for a study anyway, especially on large rezonings, because the real question is construction access. The study is one piece of the broader data center permitting process and usually feeds conditions at site plan review.
02Trip generation: how ITE rates apply to data centers
Traffic engineers estimate trips with the Institute of Transportation Engineers (ITE) Trip Generation Manual. The current 12th edition added data from more than 550 new sites, introduced nine new land use classifications, and removed data collected before 1990.11 Data center is land use code 160. Palm Beach County’s summary of 12th-edition rates lists it per 1,000 square feet of floor area, with daily trips estimated by a logarithmic regression equation rather than a flat rate.4
The data are thin. A traffic memorandum filed in Stafford County, Virginia, notes that the ITE data center rates rest on two sites for daily trips, six for the morning peak and five for the evening peak, and that the manual itself urges caution because few sites report tenant and employee data.1 The same memo observes that data centers have very few visitors, so most trips are employees and deliveries.1
Large buildings still produce real numbers. A June 2026 traffic report for a proposed Florida data center applied the 12th edition and land use 160 to roughly 3.8 million square feet and estimated 2,793 daily trips.5 Engineers and reviewers frequently cross-check ITE output against a first-principles estimate built from staffing, shift times and deliveries. Where shift changes on a 24/7 schedule fall outside the morning and evening commuter peaks, the peak-hour impact can be small even for a large building, which is why reviewers ask for the shift schedule as well as the floor area.
03Construction traffic vs. operational traffic
A data center campus has two very different traffic profiles. Once operating, it looks like a lightly staffed industrial use. During construction, it can look like a small city’s worth of commuters plus a steady stream of heavy trucks. In Wood County, Ohio, a $750 million data center was expected to bring more than 1,000 vehicles a day at the peak of construction, and the county built a roundabout and turn lanes to serve the site.2 In Caddo Parish, Louisiana, officials said heavy truck traffic for the Stateline Data Center could last five to seven years as buildings are built in phases.6
Fig. 1Operational vs. construction traffic
Usually modest
Operations
- Shift workers on 24/7 schedules
- Few visitors; some vendor and delivery trips
- Peaks often fall outside commuter hours
- Covered by ITE land use 160 rates
Usually the issue
Construction
- Hundreds to thousands of workers a day
- Earthwork, aggregate and concrete trucks
- Oversize loads for transformers and generators
- Can last years on a phased campus
Reviewers have started asking for construction traffic to be analyzed explicitly. In Morrow County, Oregon, the county’s public works staff asked for a separate assessment of construction volumes on Tower Road after reviewing a study that focused on post-construction traffic; the consultant used a week of tube counts to set the baseline.12 In Hanover County, Virginia, the 2025 study for a proposed 900 MW, 434-acre data center rezoning analyzed existing, 2034 no-build and 2034 build conditions and designated a US-33 emergency and utility access as a temporary construction driveway.13
Where construction traffic was not managed well, it became the public story. In Port Washington, Wisconsin, damage to local roads from construction of a large campus became a county issue and ended in a repair agreement with the developer, described below.3 Oversize deliveries for transformers and switchgear add a separate permit track, covered in heavy-haul routes and construction access.
04What the study contains and how reviewers read it
Most traffic impact studies follow the same structure, though each agency publishes its own scoping rules. The scope (study area, intersections, analysis years and methods) is normally agreed with the reviewing engineer before counts are taken.
| Component | What it covers | Data center notes |
|---|---|---|
| Existing conditions | Traffic counts, crash history, road geometry | Rural roads may have very low counts; one entrance road carried about 40 vehicles a day14 |
| Trip generation | ITE rates or a first-principles estimate | Land use 160 rests on few sites; staffing-based checks are common1 |
| Distribution and assignment | Where trips come from and which routes they use | Construction workers may come from a much wider area than operators |
| Future no-build and build | Background growth plus approved projects, with and without the site | Horizon years can run a decade on phased campuses13 |
| Turn lane and signal warrants | Tests against local or state criteria | Low volumes often mean no turn lane is warranted14 |
| Construction traffic | Worker and truck volumes, haul routes, temporary access | Increasingly requested as a separate analysis1312 |
| Recommendations | Improvements and their timing | Often tied to phases or building permits |
Skeptical reviewers look for a few things: whether ITE rates were applied to the right floor area, whether shift changes overlap with school or commuter peaks, whether the study counted construction at all, and whether the access plan works for fire apparatus and oversize vehicles. Site access and frontage constraints that shape the driveway layout are covered in site shape, access and frontage.
05Road improvements and who pays for them
A study’s recommendations become conditions of approval. For an operating data center, the result is often limited. A 2026 turn lane memo for a 750,000-square-foot campus in Spotsylvania County, Virginia, found no turn lanes warranted at the entrance, on a road carrying about 40 vehicles a day.14 Larger campuses on busier roads can still face turn lanes, signals or a roundabout, as in Wood County, Ohio.2
The bigger negotiation is usually about pavement. Rural county roads are rarely built for months of loaded trucks. Counties have answered with road use agreements: in Ozaukee County, Wisconsin, the arrangement makes the developer financially responsible, with the county highway department doing repairs and billing monthly for time and materials, and either side able to end it on 60 days’ notice.3 Pueblo County, Colorado’s 2026 road use agreement template requires a pre-construction survey of each road on the haul route, paid for by the company, and a repair plan where the survey calls for one.10 In Caddo Parish, officials have said the developer will be held responsible for significant road damage.6
Fig. 2From scoping to road conditions
- 01
Scoping
Agree study area, intersections, years and methods with the reviewer.
- 02
Counts and trips
Collect counts; estimate operating and construction trips.
- 03
Analysis
Test no-build and build conditions and turn lane warrants.
- 04
Agency review
Local engineer and, where triggered, the state DOT comment.
- 05
Conditions
Improvements, haul routes and road use terms attached to approval.
Road commitments often end up in a proffer, condition set or development agreement, sometimes alongside formula-based transportation fees, which are explained in impact fees and connection fees.
06What to check on a candidate site
Traffic rarely kills a data center site on its own, but it can add cost, delay and opposition. A short desk screen before an option is signed can surface most of the issues.
- Find the local TIA trigger and whether a state DOT review applies, such as Virginia’s 5,000-trip rezoning criterion.9
- Identify the road class and owner for every frontage and likely haul route: state, county, township or private.
- Check posted weight limits, bridges and seasonal restrictions on routes to the nearest interstate or rail siding.
- Estimate construction workforce and truck volumes by phase, not only operating trips.12
- Ask the county engineer whether a road use agreement, pre-construction survey or bond is expected.10
- Look for schools, crossroads communities and commuter peaks that construction shifts would overlap.
Traffic also feeds directly into community engagement: truck traffic and road damage are common complaints once construction starts, as the Port Washington and Caddo Parish cases show.36 If you want a second look at access, haul routes and entitlement risk on a parcel, you can get a site reviewed.
Common questions
Do data centers generate a lot of traffic?
Not once they are operating. They employ relatively few people and have very few visitors, so most trips are shift workers and deliveries.1 Construction is different and can bring more than 1,000 vehicles a day on a large project.2
What ITE land use code is used for a data center?
Land use code 160, Data Center, in the ITE Trip Generation Manual, with rates expressed per 1,000 square feet.4 The rates are based on only a handful of surveyed sites, so engineers often check them against staffing and shift assumptions.1
Is a traffic impact study required for a data center?
It depends on local and state triggers. Many local codes use about 100 peak-hour trips or 1,000 daily trips as the threshold,78 and some states add their own review.9 Staff can often require a study on large rezonings even when trip estimates are low.
Who pays for road damage during data center construction?
Increasingly, the developer, through a road use agreement or conditions of approval. Agreements in Wisconsin and templates in Colorado assign repair costs to the company and may require pre-construction road surveys.310 Terms are negotiated, so confirm them with the county engineer and your attorney.
Notes
- 1.Stafford County, Virginia, “Exhibit F: Traffic Memorandum,” n.d. cdn.staffordcountyva.gov
- 2.BG Independent News, “Roundabout construction to begin soon to access new data center north of BG,” n.d. bgindependentmedia.org
- 3.Ozaukee Press, “County seals deal to fix data center road damage,” n.d. ozaukeepress.com
- 4.Palm Beach County Engineering, Traffic Division, “Trip Generation Rates, ITE 12th Edition,” n.d. discover.pbcgov.org
- 5.City of Fort Pierce, Florida (Technical Review Committee), “Willow Lakes Data Center Traffic Report,” 2026. public.destinyhosted.com
- 6.KTBS, “Caddo Parish aims to hold data center developer liable for road damage,” n.d. ktbs.com
- 7.City of North Richland Hills, Texas, “NRH Trip Generation Form,” n.d. nrhtx.com
- 8.Village of St. James, North Carolina, “Appendix A: Unified Development Ordinance,” n.d. codelibrary.amlegal.com
- 9.Virginia Administrative Code, “24VAC30-155-40, Rezoning,” n.d. law.lis.virginia.gov
- 10.Pueblo County, Colorado, “Road Use Agreement Template,” 2026. county.pueblo.org
- 11.Institute of Transportation Engineers, “Trip Generation: The Industry’s Go-To Reference for Estimating Development-Generated Travel,” n.d. ite.org
- 12.Morrow County, Oregon (Kittelson & Associates), “Tower Road Construction Traffic,” 2023. morrowcountyor.gov
- 13.Hanover County, Virginia (Kimley-Horn), “TIA Report: Mountain Road Technology Park,” 2025. hanovercounty.gov
- 14.Spotsylvania County, Virginia, “SUP26-0003 Turn Lane Warrant Analysis Memo,” 2026. spotsylvania.va.us
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Zoning, permitting & community
- FAA Airspace, Airports and Height Limits for Data Centers
- Zoning for Data Centers: By-Right, Special Use and Rezoning
- Community Engagement and Local Concerns About Data Centers
- Data Center Tax Incentives: What to Look For
- Noise, Setbacks and Buffers for Data Centers
- Annexation, Jurisdiction and Utility Service Areas for Data Center Sites
- Data Center Moratoriums and Local Restrictions: How to Screen for Them
- Building and Fire Codes for Data Centers: IBC, NFPA 75 and 76, NFPA 855
- Data Center Sales Tax Exemptions by State: Thresholds, Pauses and Repeals (2026)
- Public Hearings for Data Center Projects: Notice, Testimony and How to Prepare
- Comprehensive Plans and Future Land Use Maps for Data Center Sites
- Data Center Zoning Ordinances and Overlay Districts: Recent Rules and Standards
- Contested Data Center Projects: Lessons From Prince William, Peculiar, Tucson and Other Public Fights
- State Data Center Legislation: 2025–2026 Trends in Tariffs, Incentives, Water and Moratoriums
- Data Center Architectural and Visual Standards: Facades, Screening, Lighting and Height
Guide 16 of 20 in Zoning, permitting & community · all 242 guides · glossary · calculators