Key takeaways
- The asset being bought is the energized interconnection: Bernstein analysts estimate close to 50 months to secure a gigawatt of new power in U.S. markets, and bitcoin mining machines themselves cannot run AI workloads.2
- Core Scientific’s CoreWeave contracts grew from about 200 MW in June 2024 to about 590 MW across six sites by February 2025, with $10.2 billion of projected revenue.53
- Galaxy delivered 133 MW of critical IT to CoreWeave at its former Helios mining site in 2026, under a 15-year lease.6
- Mining sites were built to curtail on demand; AI tenants expect continuous uptime, which adds backup generation and redundant distribution.74
- Air-cooled mining halls rarely suit GPU racks; conversions often add liquid cooling or new buildings, and the cooling retrofit can approach greenfield cost.48
- Large tech companies are backstopping some deals, such as Google’s $1.4 billion backstop of Fluidstack’s lease at Cipher’s Barber Lake site.9
01Why miners are converting to AI hosting
Bitcoin mining built a large fleet of power-hungry sites across the United States. EIA’s preliminary 2024 estimate put cryptocurrency mining at roughly 0.6% to 2.3% of U.S. electricity consumption, and noted that miners in volatile wholesale markets cut their load when prices spike.10 Many of those sites were developed in Texas and other low-cost power regions, with grid connections of tens to hundreds of megawatts.
Two forces pushed operators toward AI. Mining revenue per unit of computing fell after the 2024 halving cut the block reward from 6.25 to 3.125 bitcoin.11 At the same time, AI developers ran into a power bottleneck. In a May 2026 note, Bernstein analysts estimated that securing a gigawatt of power can take close to 50 months across U.S. markets, called power access rather than chips the main constraint on AI data centers, and described miners’ grid-connected sites as “warm powered shells” ready for GPUs.2 VanEck argued in 2024 that suitable mining sites could energize GPUs in under a year, against four or more years for greenfield AI developments.1
The resulting deals have been large. IREN signed a five-year, $9.7 billion GPU cloud contract with Microsoft, and Cipher Mining announced a roughly $5.5 billion, 15-year lease with Amazon Web Services.11 Our guide to AI data center site requirements explains why power availability now leads the AI siting order.
02The Core Scientific and CoreWeave case
Core Scientific’s agreements with CoreWeave are the most closely watched example. In June 2024 the companies announced about 200 MW of infrastructure to host CoreWeave’s high-performance computing, with more than $3.5 billion of projected revenue over initial 12-year terms and about $290 million a year on average. About $300 million of Core Scientific’s capital costs was to be credited against hosting payments at no more than 50% of monthly fees.5
CoreWeave then exercised further options, bringing contracted capacity to about 500 MW of critical IT load at six sites and $8.7 billion of potential revenue by October 2024.12 A February 2025 expansion at Denton, Texas, added 70 MW, taking Denton to just over 260 MW and the total to about 590 MW across six sites, with $10.2 billion of projected revenue.3
Fig. 1Core Scientific’s CoreWeave contracts
The case also shows the limits. CoreWeave’s roughly $9 billion all-stock bid to acquire Core Scientific failed when Core Scientific shareholders voted it down on October 30, 2025, leaving the hosting contracts in place.13 Delivery has been uneven: a January 2026 report said CoreWeave had brought more than 16,000 GPUs online at Denton for OpenAI after construction delays tied to weather and a third-party developer.14 Converting a mine is construction, with construction risk.
03The power advantage, and its limits
A mining site’s main value is an existing interconnection agreement and, often, a substation already built and energized. That can save years compared with a new large-load interconnection. Galaxy’s Helios site in West Texas illustrates the scale: Galaxy said CoreWeave had committed to 526 MW across three phases under 15-year leases, backed by 800 MW of approved gross power, and it delivered the first 133 MW of critical IT load in 2026.6
Three cautions apply. First, gross power is not critical IT load. A mining site can put nearly all its grid power into hashing, while an AI data center loses a share to cooling and electrical losses; Cipher’s Barber Lake deal, for example, delivers 168 MW of critical IT from up to 244 MW of gross capacity.9 Second, expansion power still runs through the grid operator. In September 2026 Galaxy reported that ERCOT’s Batch Zero large-load review had conditionally classified Helios I (800 MW) and Helios II (830 MW) as base load, while a 1,000 MW Helios III request was classified as studied load, which remains subject to capacity allocation.15 See Texas Senate Bill 6 and ERCOT site selection.
Third, an interconnection agreement says little about the electrical path to the rack. Creative Strategies notes that mining sites often distribute at 208–240 volts, while AI systems need 480 volts or more, which means new transformers, switchgear and protection with long equipment lead times.4 Our guide to UPS and electrical distribution explains what that path includes.
04Redundancy and cooling: the main gaps
Mining sites were designed to switch off. That flexibility is a feature for a miner: in August 2023, Riot Platforms earned $31.7 million in power and demand response credits in Texas while cutting its load by more than 95% during peak periods.7 An AI tenant paying for capacity expects the opposite. Few mining sites have the redundant feeds, uninterruptible power or generator fleets that a Tier III-style facility uses, and Creative Strategies cites industry practice of sizing AI backup generation at 1.2 to 2.0 times critical IT load.4
Fig. 2Bitcoin mine vs. AI data center
Built to curtail
Bitcoin mining site
- Load drops on price signals or grid stress
- Minimal backup power and redundancy
- Low-voltage distribution to racks of miners
- Air-cooled halls or immersion tanks
- Basic connectivity is enough
Built for uptime
AI data center
- Load expected to run continuously
- UPS, generators and redundant paths
- 480 V or higher distribution to dense racks
- Direct-to-chip liquid cooling for GPUs
- High-capacity, diverse fiber
Cooling is often the largest change. Air-cooled mining halls are rarely built for GPU racks, and Creative Strategies concludes that retrofitting a mining shell for AI cooling can approach the complexity and cost of a greenfield build.4 Bitfarms’ plan for its 18 MW Washington mining site illustrates the target: liquid-cooled infrastructure for up to 190 kW per rack, with completion targeted for December 2026.8 In practice, many operators keep the substation and land and build new halls beside or in place of the old ones. See air vs. liquid cooling and retrofit or build new.
Fiber is the other gap. Mining needs very little bandwidth, so remote sites may have a single modest connection. AI training tolerates distance better than interactive services, but tenants still expect diverse, high-capacity routes; see fiber connectivity for data center sites.
05How conversion deals are structured
Most conversions are long-term hosting or lease contracts in which the former miner provides land, power and the building, and an AI cloud company or hyperscaler installs the computing. Core Scientific’s contracts run 12 years,3 Galaxy’s Helios leases 15 years,6 and Applied Digital’s three CoreWeave leases at Polaris Forge 1 in Ellendale, North Dakota, total 400 MW of critical IT with about $11 billion of anticipated revenue.16
Credit support has become part of the structure. Google agreed to backstop $1.4 billion of Fluidstack’s lease obligations at Cipher’s Barber Lake site to support project debt, receiving warrants for about 5.4% of Cipher.9 Lenders and tenants underwrite the site’s power and construction plan much as they would a greenfield campus. Our guide to how data center deals are structured covers the main forms.
06How to screen a mining site for AI conversion
The screen starts with the power position and works inward to the building. A conversion makes sense when the interconnection is firm and the gaps can be closed faster than a greenfield site could be powered.
Fig. 3Sample screen of a mining site for AI use
Illustrative- PassEnergized interconnection150 MW firm service from an on-site substation.
- WatchExpansion powerAdditional 200 MW pending utility and ISO studies.
- WatchCurtailment obligationsDemand response contract must be ended or restructured.
- FailElectrical distributionLow-voltage gear; new MV transformers and switchgear needed.
- FailCoolingAir-cooled halls; liquid cooling requires new buildings.
- WatchFiberOne provider; a second diverse route is about 20 miles away.
- 01Confirm the interconnection terms: firm or interruptible, contracted MW, and any curtailment or demand response commitments. See firm vs. interruptible power.
- 02Translate gross MW to deliverable critical IT load after cooling and losses.9
- 03Inventory the substation, transformers and switchgear and price the upgrade to AI-grade distribution.4
- 04Decide whether the existing halls can take liquid cooling or should be replaced.
- 05Check fiber routes, water for cooling, and whether local zoning treats an AI data center differently from a mining operation.
A mining site with a firm, energized connection can be one of the fastest paths to AI capacity, but the parcel and building still need a full data center review. If you hold or are evaluating one, we can get a site reviewed for conversion potential.
Common questions
Can a bitcoin mining facility be turned into an AI data center?
Yes, and several have been, including Core Scientific sites hosting CoreWeave and Galaxy’s Helios campus.36 The power connection usually carries over, but electrical distribution, backup power and cooling generally need major upgrades or new buildings.4
Why do AI companies want bitcoin mining sites?
Because the sites already have large, energized grid connections. Analysts have estimated multi-year waits for new gigawatt-scale power, while suitable mining sites can host GPUs much sooner.21
Can mining hardware be used for AI?
No. Bitcoin mining machines use chips built for one hashing algorithm, so they cannot run AI workloads. The value lies in the site’s power, land and buildings, which Bernstein analysts describe as “warm powered shells” for GPUs.2
What happened with CoreWeave and Core Scientific?
Core Scientific contracted about 590 MW of hosting capacity to CoreWeave over 12-year terms.3 CoreWeave’s roughly $9 billion offer to acquire the company was rejected by Core Scientific shareholders on October 30, 2025, but the hosting partnership continued.13
Does a mining site’s power capacity equal its AI capacity?
No. AI data centers lose part of their grid power to cooling and electrical overhead, so critical IT load is lower than gross capacity; Cipher’s Barber Lake deal pairs 168 MW of critical IT with up to 244 MW of gross power.9
Notes
- 1.VanEck, “Bitcoin Miners’ AI Arbitrage Play to Boost Revenue,” 2024. vaneck.com
- 2.The Block, “‘Follow the gigawatts’: Bernstein sees upside in several bitcoin miners amid $90 billion in AI data center deals,” 2026. theblock.co
- 3.Core Scientific, Inc., “Core Scientific and CoreWeave Announce $1.2 Billion Expansion at Denton, TX Site,” 2025. investors.corescientific.com
- 4.Creative Strategies, “From Bitcoin to AI: The Hard Road Ahead, and Why Some Miners Can Still Make the Jump,” n.d. creativestrategies.com
- 5.Core Scientific, Inc. (Business Wire), “Core Scientific to Provide Approximately 200 MW of Infrastructure to Host CoreWeave’s High Performance Computing Services Capturing Significant AI Compute Opportunity,” 2024. businesswire.com
- 6.The Block, “Galaxy delivers 133 MW of critical IT load to CoreWeave as Helios bitcoin mine turns AI hub,” 2026. theblock.co
- 7.ABC13 Houston, “ERCOT paid Bitcoin miner $31.7 million to reduce energy usage during August heat wave,” 2023. abc13.com
- 8.Bitfarms (press release via Seeking Alpha), “Bitfarms Announces Plans for Conversion of Washington Site to HPC/AI Workloads,” n.d. seekingalpha.com
- 9.Decrypt, “Google Dives Deeper Into Bitcoin Mining by Backstopping AI Hosting Deal,” 2025. decrypt.co
- 10.U.S. Energy Information Administration, “Tracking electricity consumption from U.S. cryptocurrency mining operations,” 2024. eia.gov
- 11.Decrypt, “Bitcoin Miners IREN, Cipher Rise After Multi-Billion-Dollar Microsoft, Amazon Deals,” 2025. decrypt.co
- 12.Core Scientific, Inc. (U.S. Securities and Exchange Commission filing), “EX-99.1 (Form 8-K exhibit: CoreWeave exercises final option),” 2024. sec.gov
- 13.Yahoo Finance, “Core Scientific shareholders reject $9 billion CoreWeave offer, deal terminated,” 2025. finance.yahoo.com
- 14.The Energy Mag, “CoreWeave Deploys 16,000 GPUs at Delayed Texas Data Center for OpenAI,” 2026. theenergymag.com
- 15.Galaxy Digital (press release via Investing News Network), “Galaxy Provides Update on ERCOT Batch Zero Large Load Classifications,” 2026. investingnews.com
- 16.Data Center Dynamics, “CoreWeave signs on for another 150MW of capacity at Applied Digital data center campus,” 2025. datacenterdynamics.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Site strategy by data center type
- Site Needs by Data Center Type: Edge, Colocation and Hyperscale
- AI Training vs. Inference Data Centers: How Site Needs Differ
- Edge Data Center Site Selection: Location, Power and Zoning
- Colocation Data Center Site Selection: Markets, Connectivity and Multi-Tenant Needs
- Modular and Prefabricated Data Centers: Speed, Footprint and Permitting
- What Does a Gigawatt-Scale AI Data Center Campus Require?
- Government, Defense and Sovereign Data Center Siting: Security, Federal Rules and Data Residency
- Enterprise Data Center Site Selection: Distance From HQ, DR Separation and Hybrid Cloud
Guide 6 of 11 in Site strategy by data center type · all 242 guides · glossary · calculators
