BlackForge Data Centers

Site strategy by data center type

What Does a Gigawatt-Scale AI Data Center Campus Require?

A gigawatt-scale AI campus needs power on the scale of a large power plant, delivered through new transmission and often new generation, plus roughly a thousand acres or more of contiguous land.12 The two best-documented U.S. examples, the 1.2 GW Stargate campus in Abilene, Texas, and Meta’s Hyperion campus in Richland Parish, Louisiana, show that at this size the site question becomes a utility, water and community question as much as a real estate one.3

Last reviewed · 9 min read · BlackForge Data Centers

Key takeaways

  • A survey-based industry report expects about one in five data center campuses to exceed 1 GW by 2030, so gigawatt sites are moving from novelty to a planning category.4
  • Meta’s Hyperion went from a 2,250-acre, $10 billion announcement in 2024 to a planned 5 GW, 3,200-plus-acre campus in 2026.53
  • Serving Hyperion took three new gas plants (2.26 GW), a 500 kV line, eight 230 kV lines and eight substations in the first approved phase alone.62
  • Abilene uses closed-loop liquid cooling, so its water need is mostly an initial fill, reported at 1 to 8 million gallons, rather than daily evaporation.78
  • Construction labor, roads and local utilities scale too: Hyperion’s peak workforce estimate rose from about 5,000 to about 7,500.53

01What “gigawatt scale” means for a site

A gigawatt is 1,000 megawatts. For a data center, it usually describes the planned peak electrical demand of a whole campus at full build-out, not a single building or the first phase. For context, Lawrence Berkeley National Laboratory estimated that all U.S. data centers together used about 4.4% of the nation’s electricity in 2023 and could reach 6.7% to 12% by 2028.9 A single 1 GW campus running near full load would use a meaningful share of that national total by itself.

Campuses of this size are becoming a recognized category. Bloom Energy’s 2026 survey of hyperscalers, colocation providers, utilities and suppliers projects that about one in five data center campuses will exceed gigawatt scale by 2030, rising to one in three by 2035.4 That is a survey of expectations, not a count of built projects, but it matches what utilities are seeing in their load requests.

The difference between a 100 MW hyperscale campus and a 1 GW AI campus is not just ten times more of everything. At gigawatt scale the local grid almost never has the capacity waiting, so the project becomes a transmission and generation project. Water, roads, housing for construction workers and local politics all move from line items to gating issues. Our broader guide to AI data center site requirements covers AI sites in general; this guide focuses on the very top of the size range, using the two most thoroughly reported U.S. examples.

02Two reference campuses: Abilene and Hyperion

The Stargate campus in Abilene, Texas, developed by Crusoe and leased to Oracle for OpenAI workloads, is planned at about 1.2 GW in eight buildings.1011 The first phase of two buildings and more than 200 MW started in June 2024, and the second phase of six more buildings and roughly another gigawatt started in March 2025.10 Epoch AI’s tracker estimated that four of the eight buildings were operating, projected completion in the second half of 2026, and noted that a planned expansion to 2.1 GW had been reversed.11 A project directory lists the campus at about 1,100 acres.1

Meta’s Hyperion campus in Richland Parish, Louisiana, was announced on December 4, 2024, as a $10 billion, four-million-square-foot data center on the state-owned, 2,250-acre Franklin Farms site about 30 miles northeast of Monroe.5 In July 2026 Meta announced another $40 billion, bringing the total to about $50 billion including power infrastructure, with the campus planned to cover more than 3,200 acres and reach 5 GW across two phases.3 Meta has said it expects about 2 GW by 2030, with no public timeline for the full 5 GW.3

The two reference campuses at a glance, as reported in the sources cited in this section; Hyperion figures reflect the July 2026 expansion.[^3]
ItemStargate, Abilene, TXHyperion, Richland Parish, LA
Planned powerAbout 1.2 GW2 GW by 2030; 5 GW planned
Reported landAbout 1,100 acres2,250 acres at announcement; 3,200+ planned
Power strategyProposed on-site gas plant of up to 360.5 MWUtility-built gas plants and transmission
Cooling and waterClosed-loop liquid coolingNot detailed in the sources reviewed
Peak construction laborNot reported in the sources reviewedAbout 7,500 (revised from about 5,000)

Fig. 1Gigawatt campuses by the numbers

Planned power, Stargate Abilene
1.2 GW
Planned power, Meta Hyperion
5 GW
First approved gas plants for Hyperion
2.26 GW
Meta’s stated Hyperion investment
$50B
Planned figures as reported; both campuses are still under construction.103

03Power: new generation, new transmission

At gigawatt scale, power is not something a site has; it is something the utility and developer build. Hyperion shows the pattern. On August 20, 2025, the Louisiana Public Service Commission approved, through a settlement with one commissioner dissenting, Entergy Louisiana’s plan for three combined-cycle gas plants totaling about 2.26 GW: two in Richland Parish and one at the existing Waterford site in St. Charles Parish, with two units expected in 2028 and the third in late 2029.6 The package also included a roughly 100-mile, 500 kV line expected by December 2026.6

The delivery network was just as large. Entergy described two company-owned and six customer-owned substations, eight new 230 kV lines, and a substation in Richland Parish funded entirely by Meta.2 In March 2026 Entergy announced seven more gas plants, about 5.2 GW, which would bring the total serving the campus to ten plants and more than 7 GW.12 On April 15, 2026, the Public Service Commission voted 4–1 to fast-track that application, which Entergy said Meta would pay for; the vote set the review schedule rather than approving construction, with a final decision expected late in 2026.13

Fig. 2How Hyperion’s first power phase is assembled

  1. 01GenerationThree combined-cycle gas plants, about 2.26 GW
  2. 02Bulk transmissionAbout 100 miles of new 500 kV line
  3. 03Regional linesEight new 230 kV transmission lines
  4. 04SubstationsTwo utility-owned and six customer-owned
  5. 05CampusData halls fed from the new substations
Simplified from the 2025 approval; later phases add more plants pending regulatory review.62

Abilene shows a second approach: alongside its utility service, developers filed to site an on-site gas plant of up to 360.5 MW, at an expected cost of up to $500 million.14 Competition for grid capacity is intense. By August 2026, large-load requests on the Texas grid had reportedly reached about 474 GW, and the state paused new data center grid approvals pending an audit.15 Most of that queue is speculative, but it shows how crowded the line for power has become. Texas rules for large loads are covered in our guide to Texas Senate Bill 6, and the trade-offs of building generation on site are covered in on-site generation and bridge power.

04Land: how many acres a gigawatt takes

There is no fixed acres-per-gigawatt rule, because building height, rack density, cooling plant, substations and on-site generation all change the footprint. The reported figures still give a useful range. Dividing the reported acreage by the planned power gives roughly 900 acres per gigawatt at Abilene,1 about 1,100 acres per gigawatt for Hyperion’s first 2 GW on 2,250 acres,5 and about 640 acres per gigawatt for the full 5 GW plan on 3,200 acres.3 The planned Hyperion expansion packs more power onto each acre as the campus densifies.

Fig. 3Reported acres per gigawatt of planned power

  • Abilene (1,100 acres, 1.2 GW)≈ 920
  • Hyperion initial (2,250 ac, 2 GW)≈ 1,130
  • Hyperion full plan (3,200 ac, 5 GW)≈ 640

acres per GW

Our arithmetic from reported acreage and planned power. Actual footprints depend on design.153

What matters more than the ratio is shape and control. A gigawatt campus needs one contiguous, reasonably regular tract that can hold long buildings, several high-voltage substations at the edge nearest the transmission corridor, cooling yards, possible generation, internal roads and buffers from neighbors. Start from buildable acreage, not deeded acreage; our guide to gross vs. buildable acreage explains the deductions. Room for later phases is part of the requirement: Hyperion’s footprint grew by roughly 1,000 acres within two years of its announcement.53

Phasing should be designed in from the start. Our guides to campus master planning and load ramp schedules cover how buildings, substations and power blocks are sequenced.

05Water: design choice decides the number

Water demand at gigawatt scale depends far more on the cooling design than on the megawatts. Epoch AI reports that at least six Stargate sites, Abilene among them, use closed-loop liquid cooling that does not evaporate water.11 A closed loop needs an initial charge and then only top-ups for minor losses.

Even then, the reported numbers differ. Associated Press coverage put the initial fill at about one million gallons of municipal water, with Oracle expecting each of the eight buildings to need about 12,000 more gallons per year.7 The Texas Tribune reported an initial fill of 8 million gallons, which a city water official called minimal against Abilene’s average use of about 22 million gallons a day, while noting he could not say how much refill water would follow.8 The same AP report noted the city’s reservoirs were at roughly half capacity at the time.7 A gigawatt of evaporative cooling would be a very different water story.

Wastewater and supply infrastructure also scale. Meta committed more than $200 million to local roads and water systems at the 2024 announcement, and then about $1 billion for roads, water and wastewater with the 2026 expansion.53 See closed-loop and waterless cooling and water stress and drought risk for how to test a site’s supply.

06Labor, roads and public process

A gigawatt campus is a multiyear megaproject for its region. At the 2024 announcement, Hyperion was expected to employ about 5,000 construction workers at peak and more than 500 permanent staff.5 By the July 2026 expansion, the peak construction estimate had risen to about 7,500 and permanent jobs to about 1,000.3 Thousands of daily workers and deliveries mean road upgrades, traffic management and often temporary housing pressure in rural areas. Heavy equipment such as large power transformers needs a planned route; see heavy-haul access.

Public review also scales. Hyperion’s first power package went through a contested Public Service Commission proceeding before approval, and the larger second package went back to regulators.613 Tax incentives draw scrutiny too: the original Louisiana deal relied on a state program offering data center tax breaks for 20 years with a possible 10-year extension.5 Developers should expect ratepayer cost allocation, water use and local road impacts to be argued in public, and should plan community engagement early.

07How to screen a site for gigawatt potential

Few parcels can be judged gigawatt-ready from a desktop review, but many can be ruled out quickly. A practical first pass tests whether the site could plausibly carry the infrastructure that Abilene and Hyperion needed.

  • Transmission: 345 kV or 500 kV lines nearby, and a utility or RTO willing to study a load of this size. See transmission voltage for data centers.
  • Generation path: a credible plan for new supply, whether utility-built plants, on-site gas with firm pipeline capacity, or both.
  • Land: roughly 650 to 1,100 contiguous buildable acres per gigawatt planned, with control of adjoining land for growth and buffers.
  • Water: a cooling design matched to local supply, with the initial fill and any ongoing use confirmed in writing by the water provider.
  • Access and labor: routes for heavy loads and thousands of daily workers, and a workforce market that can supply them.
  • Public process: the regulatory approvals the power plan will need, and how the host community is likely to respond.

Fig. 4Sample gigawatt readiness screen

Illustrative
  • PassTransmission500 kV line crosses the north boundary.
  • WatchNew generation pathUtility open to new plants; no filing yet.
  • PassContiguous acreage1,300 buildable acres under one owner.
  • WatchWaterSupply fits closed-loop cooling only.
  • FailHeavy-haul routeBridge on the only access road is load-posted.
Illustrative sample. Not a real parcel.

Treat every result as a question for the utility, the RTO, the water provider and the county, not as a final answer. If you want an outside view of whether a tract could grow into this class of campus, you can get a site reviewed.

Common questions

How much land does a 1 GW data center need?

Reported examples work out to roughly 640 to 1,100 acres per gigawatt, depending on design and how much generation and substation equipment sits on site.13 Contiguous buildable land, plus room for buffers and later phases, matters more than the raw ratio.

How is a gigawatt AI campus powered?

Usually through new transmission and new generation built for the load. Meta’s Hyperion relies on utility-built gas plants, a 500 kV line and new 230 kV lines, while Abilene’s developers filed to build an on-site gas plant of up to 360.5 MW.614

How much water does a gigawatt data center use?

It depends mostly on the cooling design. Abilene’s closed-loop system needs an initial fill, reported at 1 to 8 million gallons, and then small top-ups, while evaporative designs use far more water every day.78

How long does it take to build a gigawatt campus?

Several years. Abilene’s first phase began in June 2024, with all eight buildings projected to be finished in the second half of 2026, and Meta expects Hyperion to reach about 2 GW by 2030 with no public date for the full 5 GW.113

Are gigawatt data center campuses becoming common?

They are becoming a planning category. An industry survey projects that about one in five campuses will exceed 1 GW by 2030, and large-load requests on the Texas grid alone reportedly reached about 474 GW by August 2026, though most of those requests will not be built.415

Notes

  1. 1.Data Center Map, “Crusoe Abilene Stargate Campus,” n.d. datacentermap.com
  2. 2.Entergy, “Entergy Louisiana receives LPSC approval for major infrastructure investments to support Meta’s data center and improve reliability,” 2025. entergy.com
  3. 3.WRKF, “Meta is investing $40B more to expand Richland Parish data center project,” 2026. wrkf.org
  4. 4.Bloom Energy, “2026 Data Center Power Report,” 2026. bloomenergy.com
  5. 5.Louisiana Illuminator, “Meta plans $10B data center with 500 jobs in NE Louisiana: Details of the deal,” 2024. lailluminator.com
  6. 6.Data Center Dynamics, “Entergy obtains approval to construct three gas facilities to serve Meta’s 2GW data center in Louisiana,” 2025. datacenterdynamics.com
  7. 7.Associated Press (via Bangor Daily News), “OpenAI and Oracle show off Stargate AI data center in Texas and plan five more elsewhere,” 2025. bangordailynews.com
  8. 8.The Texas Tribune, “Data centers are thirsty for Texas’ water, but state planners don’t know how much they will need,” 2025. texastribune.org
  9. 9.U.S. Department of Energy, “DOE Releases New Report Evaluating Increase in Electricity Demand from Data Centers,” 2024. energy.gov
  10. 10.Data Center Dynamics, “Crusoe secures $11.6bn in debt and equity for OpenAI’s Stargate data center campus in Abilene, Texas,” 2025. datacenterdynamics.com
  11. 11.Epoch AI, “OpenAI Stargate: Where the US Sites Stand,” n.d. epoch.ai
  12. 12.The Lens, “Meta triples order of gas-fired power plants for its AI campus in Louisiana,” 2026. thelensnola.org
  13. 13.Fox 8 WVUE, “Seven new power plants for Meta data center in northern Louisiana fast-tracked,” 2026. fox8live.com
  14. 14.Data Center Dynamics, “Natural gas plant planned for Stargate AI data center campus: report,” 2025. datacenterdynamics.com
  15. 15.TechRepublic, “Texas Pauses Data Center Grid Approvals as Power Requests Hit 474 GW,” 2026. techrepublic.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Related guides

More in Site strategy by data center type