Key takeaways
- Prefabrication compresses the building schedule; it does not speed up load studies, transmission upgrades or substation work, which often set the real finish date.
- JLL projects modular and micro data center sales could reach $48 billion a year by 2030, with designs growing into “mega-modules” of 10 MW or more.3
- Factory capacity is being locked up by contract, from Schneider Electric’s $3 billion, five-year agreement with Compass Datacenters to deals for modules delivered monthly over several years.45
- Loads wider than 102 inches need state overwidth permits, so the route from the interstate to the parcel is part of the site screen.6
- A UL 2755 listing can cover a module’s electrical approval under NEC Article 646, but the local authority still decides whether the unit is equipment or a building.72
- State modular programs approve the factory-built units; local officials still permit and inspect foundations, utilities and site work.89
01What “modular” and “prefabricated” mean
The terms cover a spectrum rather than one product. At one end, individual systems are built and tested in a factory: power skids, switchgear line-ups, prefabricated electrical rooms (often called eHouses or power modules) and packaged chiller plants. In the middle are modular white-space products that combine racks, power distribution and cooling in units set inside a shell. At the far end are containerized or volumetric data centers, where the IT space itself arrives on a truck. Most large campuses mix these: a conventional building surrounded by factory-built power and cooling.
The scale of a single module has grown. Vertiv’s OneCore, announced for global availability in August 2025, packages power, thermal and IT infrastructure in blocks of 5 to 50 MW configurable for 96 to 944 racks, inside a Vertiv-supplied steel shell, and Vertiv says parallel manufacturing of the electrical and mechanical modules shortens timelines.10 JLL describes a shift from build-to-suit development to “assemble-at-scale” and expects designs to grow into mega-modules of 10 MW or more.3 At the small end, containerized units remain common for edge data centers.
Fig. 1Degrees of prefabrication
- 01Stick-built buildingShell, systems and fit-out assembled in the field
- 02Factory-built componentsSwitchgear, skids, generators, packaged chillers
- 03Prefabricated power roomseHouses and power modules set by crane
- 04Modular white spaceRacks, power and cooling pods inside a shell
- 05Integrated multi-MW blocks5–50 MW systems; 10 MW+ mega-modules expected
02Why owners are turning to factory-built capacity
The main driver is schedule risk. Trade coverage of JLL’s 2026 outlook reported that more than half of 2025 data center projects ran at least three months late.11 Moving work into factories lets fabrication run in parallel with site work and replaces some field labor with controlled assembly.12 Operators using factory-built power skids, prefabricated cooling modules and pre-assembled electrical rooms report 12–18 months from site clearance to energization.1
Adoption is broad but the best survey data is sponsored. In a 2022 Omdia survey sponsored by Vertiv, roughly half of 228 companies that operate their own data centers had deployed some form of prefabricated modular solution, and 93% said prefabricated modular solutions would become their default construction strategy.13
Factory output is now committed years ahead. Schneider Electric and Compass Datacenters announced a five-year, $3 billion agreement in 2023 to jointly manufacture prefabricated modular data centers; Schneider had already delivered about 150 modular solutions to Compass from its West Chester, Ohio operation, and the companies run a 110,000-square-foot facility in Red Oak, Texas.4 In 2026 Schneider wrote that buyers increasingly sign multi-year agreements, giving the example of 10 modules a month for three years, cited prefab deals with Switch and Digital Realty, and said it planned to double its prefab team to more than 2,000 employees.5 Factory slots behave like any other long-lead item; see data center equipment supply chain constraints.
The most extreme example is temporary. In July 2025, reporting relayed from SemiAnalysis said Meta was erecting tent structures with prefabricated power and cooling modules to add AI capacity while permanent buildings were under construction, trading redundancy for speed.14 Few owners would accept that trade, but it shows how far speed has moved up the priority list.
03Speed: what gets faster and what does not
Published time savings cluster around a third or more. Flex estimates that factory integration and parallel workflows can shorten schedules by 30% or more, against traditional end-to-end delivery of about 24–36 months.12 Trade analysis cites 30–50% reductions for highly modularized projects, and modular builders claim 10–15% lower installed cost.111 Nearly all of these numbers come from companies that sell modules, so treat them as upper bounds and ask for reference projects with dates from notice to proceed through commissioning.
Fig. 2Reported delivery time to energization
- Stick-built data hall24–36
- Prefabricated build12–18
The savings sit inside the building scope. Prefabrication does nothing for a utility’s load study, a transmission upgrade or a new substation, and a module that arrives before service is ready has nowhere to plug in. On many sites the power path is the longest track, which is why power timelines and a phased build-out matter more than the construction method. Our guide to how long it takes to build a data center covers the full sequence.
Fig. 3Illustrative parallel schedule with prefabrication
Illustrative- Entitlements and permits
- Utility power pathStudies, agreements, substation
- Factory fabrication
- Grading and foundations
- Delivery and crane setting
- Integration and testing
04Footprint and site layout
Prefabrication moves space out of the building and into the yard. Power modules, packaged chillers and generators usually sit on outdoor pads, so the equipment yard, its clearances and its orientation toward neighbors carry more weight in the layout. See cooling plant and equipment yard space and noise setbacks and buffers. Pads and paved access add impervious area, which feeds into stormwater management.
Construction logistics also need land. Modules arrive in sequence and may be staged before setting, so a site needs laydown area, crane pads, turning room for long trailers and roads built for heavy loads. Foundations are designed around module weights and soils, which makes an early geotechnical investigation more important, not less; see slope, soils and geotechnical review.
Density changes the ratio of building to plant. UL says its revised standard addresses AI workloads of 200 kW or more per rack.7 Higher rack density shrinks the data hall for a given load, but not the transformers, switchgear and heat rejection behind it, so total acreage is still driven by power, cooling and setbacks. Our guide to building footprint and lot coverage covers the zoning math.
| Site element | Stick-built emphasis | Prefabricated emphasis |
|---|---|---|
| Building area | Larger shell holds most systems | Smaller shell or none; more outdoor pads |
| Construction staging | Material storage, trailers, labor parking | Module laydown, crane pads, sequencing |
| Access | Standard trucks | Oversize loads and turning radii |
| Field labor | Large crews over many months | Smaller crews for connections and testing |
05Getting modules to the site
Module size is limited by the road. Federal rules set a 102-inch width limit for commercial vehicles, and FHWA guidance says a vehicle whose cargo extends past 102 inches needs an overwidth permit on the National Network and its access routes.6 Permits come from each state on the route and typically specify the route and travel times. Many power and cooling modules exceed that width, so they move as oversize loads.
The last miles are where sites fail. A parcel can sit near an interstate and still be hard to reach if county roads are narrow, bridges carry low weight ratings, rail crossings are tight or overhead lines cross the route. Height limits are set state by state, so a route survey belongs in early diligence for any modular plan. Our guide to heavy-haul routes and construction access explains what a route study checks, and the same route usually serves the large transformers a campus needs.
06Permitting: factory approvals and local approvals
Prefabrication splits approvals into two tracks. On the electrical side, UL explains that NEC Article 646 lets manufacturers meet the requirements for prefabricated data centers with a single certification, UL 2755, if it is obtained before the module ships from the factory.7 UL says the 2025 edition adds newer NEC requirements, high-density power and cooling, and interoperability requirements for modules from different manufacturers.7
A listing is not a building approval. Intertek notes that UL 2755 does not replace the International Building Code or state and local review, and that the authority having jurisdiction decides whether a unit is equipment or a building; features such as side-hinged man doors or walkable interior space can change that call.2 The classification matters because a building triggers occupancy, egress and fire protection rules; see building and fire codes for data centers.
For factory-built building modules, the ICC/MBI 1200 and 1205 standards (2021) cover planning, design, fabrication, transport and assembly, and the inspection and approval process, including state modular programs, third-party inspectors and the local authority.15 State programs illustrate the split. Maryland sets construction standards for modular buildings and preempts local ones, but the owner still applies to the local building department, which issues the permit after state approval and inspects the foundation and all site work.8 Texas uses third-party in-plant inspections, while the local building official handles site inspections and may require plans before a permit.9
Zoning does not change. Use permission, height, setbacks, noise limits, stormwater and generator air permits all still apply; see zoning for data centers and the data center permitting process. Temporary structures such as tents may fall under separate rules, so confirm with the county early.
07How to screen a site for a modular build
A modular plan pays off only if the site can feed it power on time and receive the modules. A practical screen:
- 01Confirm the power date first. If the utility path takes longer than the factory, prefabrication will not move the finish date.
- 02Survey the delivery route from the nearest interstate for width, height, bridge and turning limits, and ask which state permits apply.6
- 03Lay out the equipment yard, crane pads and laydown area early, and check them against setbacks, lot coverage and stormwater limits.
- 04Commission geotechnical work sized to module and crane loads.
- 05Ask the county or city whether the modules will be treated as equipment or buildings, and which agency inspects what.28
- 06Confirm the manufacturer’s factory slot and listings, such as UL 2755, in writing.75
If you are weighing a parcel for a fast, factory-built deployment, we can get a site reviewed for power timing, access and layout before you commit to a module order.
Common questions
Are modular data centers faster to build?
Usually for the building itself. Builders report 12–18 months from site clearance to energization for prefabricated builds, against 24–36 months for stick-built halls, though these figures come largely from vendors.1 Prefabrication does not shorten the utility’s timeline for delivering power.
Does a modular data center need a building permit?
Generally yes. A UL 2755 listing does not replace building code or local review, and the local authority decides whether a module is equipment or a building.2 Foundations, utilities and site work are permitted and inspected locally even where a state program approves the modules.8
What is UL 2755?
It is UL’s standard for prefabricated modular data centers. Under NEC Article 646, a manufacturer can meet the electrical requirements for a prefabricated data center with a UL 2755 certification obtained before shipment, and the 2025 edition addresses high-density racks and multi-vendor interoperability.7 A proposed NFPA amendment would remove that reference from the NEC, so confirm what the local inspector accepts.16
How large can a prefabricated data center be?
Single systems now reach utility scale. Vertiv’s OneCore is offered in blocks of 5 to 50 MW, and JLL expects mega-modules of 10 MW or more.103 Large campuses usually combine many modules with conventional buildings.
Can data center modules travel on ordinary highways?
Only within size limits. Cargo wider than 102 inches needs an overwidth permit on the National Network, and states issue those permits route by route.6 Local roads, bridges and overhead lines near the site are often the tighter constraint.
Notes
- 1.Datacentres.com, “Factory-Built and Fast: Modular Construction Cuts Data Centre Delivery Times by 40% as Transformer Backlogs Bite,” 2026. datacentres.com
- 2.Intertek, “UL 2755 Testing and Certification Solutions for Modular Enclosures and the Data Center Industry,” n.d. intertek.com
- 3.W.Media (reporting JLL), “Modular systems and micro DCs could fetch US$ 48 billion by 2030: JLL,” 2026. w.media
- 4.Lightwave, “Schneider Electric and Compass Datacenters expand partnership with $3B agreement,” 2023. lightwaveonline.com
- 5.Schneider Electric, “Fast-track AI growth with a modular data center approach,” 2026. blog.se.com
- 6.Federal Highway Administration, “Office of Operations Freight Management and Operations: Size and Weight Questions and Answers,” n.d. ops.fhwa.dot.gov
- 7.UL Solutions, “Addressing the Needs of the Modern Prefabricated Modular Data Center,” 2025. ul.com
- 8.Maryland Department of Labor, “Modular Buildings: Site Procedures,” n.d. labor.maryland.gov
- 9.Texas Department of Licensing and Regulation, “Industrialized Housing and Buildings Program,” n.d. tdlr.texas.gov
- 10.Vertiv, “Vertiv Announces Vertiv OneCore to Accelerate Deployment of Scalable Prefabricated Infrastructure for AI, HPC and High-Density 5+ MW Data Centers,” 2025. vertiv.com
- 11.DCNT Global, “Prefabricated Data Center: The Shift to Manufacturing-Led Execution,” 2026. dcntglobal.com
- 12.Flex, “Prefabricated Modular Data Center Solutions (ebook),” n.d. flex.com
- 13.ACHR News, “Prefabricated Modular Data Centers Are on the Rise,” 2022. achrnews.com
- 14.TechCrunch, “Meta is reportedly using actual tents to build data centers,” 2025. techcrunch.com
- 15.International Code Council, “International Code Council and Modular Building Institute release new standards for off-site construction,” 2021. iccsafe.org
- 16.National Fire Protection Association, “NFPA 70 Proposed TIA 1949,” n.d. docinfofiles.nfpa.org
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Site strategy by data center type
- Site Needs by Data Center Type: Edge, Colocation and Hyperscale
- What Are the Site Requirements for an AI Data Center?
- AI Training vs. Inference Data Centers: How Site Needs Differ
- Colocation Data Center Site Selection: Markets, Connectivity and Multi-Tenant Needs
- Converting Bitcoin Mining Sites to AI Data Centers: Power Advantage and Gaps
- What Does a Gigawatt-Scale AI Data Center Campus Require?
- High-Density GPU Racks: What 120 kW+ Racks Ask of a Data Center Site
- Government, Defense and Sovereign Data Center Siting: Security, Federal Rules and Data Residency
- Enterprise Data Center Site Selection: Distance From HQ, DR Separation and Hybrid Cloud
