Key takeaways
- Data center load drives the demand: DOE expects data center electricity use to double or triple by 2028, and interconnection queues remain slow, so speed to power is what buyers pay for.56
- FERC rejected an expanded behind-the-meter deal at Susquehanna in 2024, and Talen and Amazon then restructured it as a 1,920 MW front-of-the-meter agreement.17
- In December 2025 FERC ordered PJM to set clear co-location rules, including new non-firm and contract-demand transmission services.38
- In ERCOT, a large load of 75 MW or more that wants to net meter with existing generation now needs ERCOT study and PUCT review.49
- Equipment is a constraint: GE Vernova had roughly 10 GW of 2029 gas turbine production left to sell entering 2026.10
01Why data center buyers come to power developers
Data center load is now a major source of new electricity demand. A DOE-commissioned Lawrence Berkeley National Laboratory report found data center load growth had tripled over the past decade and projected it to double or triple again by 2028.5 The grid is slow to absorb it. In Berkeley Lab’s 2025 queue study, the typical project built in 2024 took 55 months from interconnection request to commercial operation, up from 36 months for projects built in 2015.6 Only 13% of the capacity that requested interconnection from 2000 to 2019 had reached commercial operation by the end of 2024; 77% had withdrawn.6
For an independent power producer, that gap is the opportunity. A developer with an operating plant, an executed interconnection agreement, or a site that can host new generation near transmission has something a data center developer cannot buy quickly. Berkeley Lab counted 408 GW of capacity with a draft or executed interconnection agreement that had not yet reached operation.6 The queue eased somewhat in 2025, to 2,061 GW actively seeking interconnection, a 10% drop, but timelines remained long.11 Our guide to power timelines and queues covers the load side of that wait.
Fig. 1Why speed to power commands a premium
- request to operation, typical 2024 project
- 55 months
- of 2000–2019 queue capacity built by 2024
- 13%
- with an interconnection agreement, not yet built
- 408 GW
- actively seeking interconnection, end of 2025
- 2,061 GW
02Three ways to pair generation with a data center
Most deals fall into one of three structures, and each answers differently the questions that matter to a developer: who regulates the sale, whether the load uses the transmission system, and how quickly the load can ramp.
Fig. 2Co-location, grid PPA or new energy park
Behind the meter at a plant
- Load sits inside or beside an existing generator
- Can avoid some transmission upgrades
- Draws scrutiny over grid reliability and cost shifts
- In PJM, now governed by FERC-ordered tariff rules
Most common
Grid-connected PPA
- Plant stays on the grid; buyer contracts for output
- Utility delivers power and charges for transmission
- Fewer federal approvals for the deal itself
- Load still needs its own utility interconnection
New-build energy park
- Generation, storage and campus planned together
- Sized and phased to the data center ramp
- Needs land, water, gas or renewable resource
- New generation still faces equipment lead times
The Talen and Amazon deal at the Susquehanna nuclear plant moved from the first structure to the second. Under the restructured agreement, Talen sells up to 1,920 MW through 2042 as a retail supplier while PPL Electric Utilities handles transmission and delivery, a structure Talen says does not require FERC approval.1 Constellation’s 20-year agreement with Microsoft for the restarted 835 MW Crane Clean Energy Center (formerly Three Mile Island Unit 1) is a grid-connected PPA from the start: Microsoft buys the output to match its PJM data center consumption with carbon-free energy.12 The third structure is newer. In December 2025, Alphabet agreed to acquire Intersect, a developer of co-located data center and power projects, for about $4.75 billion in cash and assumed debt, a bet on building generation and campuses together.2
For the trade-offs from the load’s side, see behind-the-meter vs. front-of-the-meter power and co-locating data centers with power plants.
03PJM and FERC: what changed after Susquehanna
Co-location became a federal issue in November 2024, when an amended interconnection service agreement for Susquehanna sought to raise the co-located load there from 300 MW to 480 MW. Two utilities objected that the arrangement would give the data center preference over the grid, and FERC rejected the amendment; it affirmed that position in April 2025, and the plant’s owners appealed to the Fifth Circuit.7
On December 18, 2025, FERC found PJM’s tariff unjust and unreasonable because it lacked clear, consistent terms for co-located generation and load, and ordered reforms.3 The order created three transmission service options as alternatives to network service: interim non-firm service while upgrades are built, firm contract demand service for loads that can hold their grid withdrawals to a set level using on-site generation, and a non-firm contract demand service.8 FERC also directed PJM to explain how generators can use provisional interconnection service, request service below nameplate capacity and use surplus interconnection service for new generation serving co-located load, and found PJM’s behind-the-meter generation rules in need of revision.8
The practical effect for developers is more options, not fewer obligations. A contract demand arrangement lets a project size transmission service to the load’s net withdrawals, but the load and generator must actually hold to those limits, which shapes how much on-site battery storage or backup generation the site needs.8
04ERCOT and Texas Senate Bill 6
Texas took a different route. Senate Bill 6, passed in June 2025, gave the PUCT and ERCOT new tools for large loads, including a review of net metering arrangements in which a load of 75 MW or more pairs with existing generation.9 ERCOT describes the concern as generation being pulled out of the supply that serves everyone else.9
Fig. 3Texas review of a net metering arrangement
- 01
Notice to ERCOT
Generator or utility notifies before starting.
- 02
ERCOT study
System impact study and recommendation by day 120.
- 03
PUCT decision
Approve, deny or condition within 60 days.
- 04
Operation
Subject to conditions and emergency curtailment.
The review applies to existing generation. New generation built alongside a large load does not need to file the net metering notice, and units that registered with a co-located load at energization are exempt, as are units majority-owned as of January 1, 2025 by the load customer’s parent.4 In July 2026, the PUCT approved the first application under the law, in Docket No. 59220, and held that emergency curtailment of a co-located data center is not capped at the capacity of the paired generator.15 That point matters to anyone underwriting a co-located Texas deal: the load cannot assume its own plant shields it in a grid emergency. Separately, on September 18, 2026, the PUCT adopted its SB 6 large-load interconnection rule for single-site loads of 75 MW or more in ERCOT, with a flat $100,000 study fee and $50,000 per MW of financial security posted before interconnection studies.16 Our guide to Texas SB 6 covers the law’s other large-load provisions.
05Structuring the offtake: term, ramp and risk
Data center buyers rarely take full output on day one. Campuses fill in phases, and the Talen and Amazon agreement makes that explicit: deliveries are scheduled to ramp over years, depending on how fast AWS builds.1 Developers should model offtake against a ramp schedule and decide who takes the unsold energy and capacity in the early years.
Fig. 4Scheduled delivery ramp, Talen and Amazon
- Until spring 2026300 MW (behind the meter)
- By 2029840–1,200
- By 20321,680–1,920
Terms that carry the most risk
- Term and extension rights: 20-year terms appear in major nuclear deals, and the Talen agreement runs through 2042.112
- Ramp and minimum take: who pays if the campus fills more slowly than planned.
- Shape and firmness: whether the product is unit-contingent output, a fixed shape, or firm supply backed by storage or gas.
- Curtailment and emergency rules: how grid-operator curtailment is shared, especially in ERCOT after the first SB 6 order.15
- Credit support and assignment: the buyer is often a project entity, not the parent company.
Our guide to power purchase agreements for data centers goes deeper on contract structures.
06Hybrid sites and the equipment bottleneck
Many new pairings combine resources: solar or wind for energy, batteries for shaping, and gas for firm capacity, all sized to the campus. Gas is where the bottleneck shows. Entering the first quarter of 2026, GE Vernova had roughly 10 GW of 2029 gas turbine production still available, and about 20% of the 100 GW it had under contract was tied directly to data center load.10 Berkeley Lab also recorded active natural gas capacity in interconnection queues rising 72% in 2024, to 136 GW.6 A developer with turbine slots, a gas lateral route and air permits in hand has a real advantage; see gas turbines vs. reciprocating engines.
A hybrid site also has to work as a data center site, which is where power developers are most often surprised. The campus needs large, flat, buildable acreage outside floodplains, water or a dry-cooling plan, diverse fiber routes, and zoning that allows both uses. A parcel that is excellent for a solar project can fail on fiber or on the county’s appetite for data centers.
07Where an energy developer should start
- 01Inventory what you can offer: operating units, interconnection agreements, surplus capacity, land and turbine or transformer positions.
- 02Pick the structure first, then the counterparty: behind the meter, grid PPA or new-build park each has different regulators and timelines.48
- 03Check the market’s current rules: the PJM compliance outcome and FERC’s large-load proceedings, or SB 6 notice, study and interconnection requirements in ERCOT.913
- 04Screen the land for data center use, not just generation: acreage, flood, water, fiber and zoning.
- 05Model the ramp and the unsold early-year output before agreeing to price.1
- 06Talk to the utility early; even a co-located load usually needs its cooperation. Our utility guide shows what they look for.
If you have a site where generation and a campus might fit together, you can get a site reviewed against the full set of data center criteria.
Common questions
Can a data center connect directly to a power plant without using the grid?
Physically yes, but regulators look closely at it. FERC rejected an expanded co-location agreement at Susquehanna in 2024, and in December 2025 ordered PJM to adopt clear tariff rules and new transmission services for co-located load.37 In ERCOT, pairing a large load with existing generation now requires notice, an ERCOT study and PUCT review.4
Why did Talen and Amazon move from behind the meter to front of the meter?
After FERC rejected the expanded co-location agreement, the parties restructured the deal so Talen sells as a retail supplier and PPL delivers the power over the grid, a structure Talen says does not require FERC approval.17 The agreement covers up to 1,920 MW through 2042.1
Does new generation built next to a data center in Texas need PUCT approval under SB 6?
The SB 6 net metering notice and review apply to existing generation; new generation developed together with a co-located large load is not required to file that notice.4 Other large-load rules still apply, so confirm requirements with ERCOT and counsel.
What is surplus interconnection service and why does it matter here?
It lets a generator use unused capacity under an existing interconnection agreement for new resources. FERC’s December 2025 order directed PJM to explain how surplus interconnection service can support new generation serving co-located load.8
Will a co-located data center be curtailed in a grid emergency?
It can be. In its first SB 6 net metering decision, the PUCT held that emergency curtailment of a co-located data center is not capped at the capacity of its paired generator.15 Contracts should say how curtailment affects payment and supply.
Notes
- 1.POWER Magazine, “Talen, Amazon Launch $18B Nuclear PPA: A Grid-Connected IPP Model for the Data Center Era,” 2025. powermag.com
- 2.Axios, “Google parent Alphabet buys data center and energy firm in $4.75B deal,” 2025. axios.com
- 3.Troutman Pepper Locke, Energy Report, “FERC Orders PJM to Establish Terms and Conditions in Its Tariff for Co-Location Arrangements,” 2025. troutmanenergyreport.com
- 4.Bracewell, “Texas Senate Bill 6 Ushers in Major Overhaul of Large Load Interconnection and Grid Access Rules,” 2025. bracewell.com
- 5.U.S. Department of Energy, “DOE Releases New Report Evaluating Increase in Electricity Demand from Data Centers,” 2024. energy.gov
- 6.Lawrence Berkeley National Laboratory, “Queued Up: 2025 Edition, Characteristics of Power Plants Seeking Transmission Interconnection As of the End of 2024,” 2025. emp.lbl.gov
- 7.The Register, “Amazon has changed its nuclear deal in Pennsylvania to bypass grumpy regulators,” 2025. theregister.com
- 8.Beveridge & Diamond, “FERC Orders PJM to Create Clear Rules for Co-Located Data Centers and Large Loads,” 2025. bdlaw.com
- 9.ERCOT, “ERCOT Trending Topic: Grid Reliability, Data Centers and Net Metering Arrangements,” 2026. ercot.com
- 10.Power Engineering, “Data centers drive record surge in GE Vernova power equipment orders as turbine slots tighten through 2030,” 2026. power-eng.com
- 11.Lawrence Berkeley National Laboratory, “Backlog of power plants seeking transmission grid connection eased somewhat in 2025 amidst high withdrawals,” 2026. emp.lbl.gov
- 12.Constellation Energy, “Constellation to Launch Crane Clean Energy Center Restoring Jobs and Carbon Free Power to The Grid,” 2024. constellationenergy.com
- 13.Troutman Pepper Locke, Energy Report, “FERC Orders Further Compliance Filing in PJM Co-Location Proceedings,” 2026. troutmanenergyreport.com
- 14.Orrick, “FERC Show Cause Orders Signal Broad Reform to Large Load Interconnection Policies,” 2026. orrick.com
- 15.White & Case, “PUCT Affirms Curtailment Authority Over Co-Located Data Centers in First Net Metering Decision,” 2026. whitecase.com
- 16.White & Case, “PUCT Sets Financial Commitments for Data Center Interconnection as Governor Pauses Permit Approvals,” 2026. whitecase.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Guides by role
- A Landowner’s Path: From First Question to Signed Deal
- Site Selection for Data Center Developers: What to Answer, in Order
- Site Risk for Data Center Investors and Lenders
- Representing Land for Data Center Use: A Broker’s Guide
- Attracting Data Centers: A Guide for Economic Development Organizations
- Data Centers: A Guide for County Officials and Planners
- Data Center Interest in Farm and Ranch Land: A Guide for Farmers
- Family Land, Estates and Trusts: How to Handle a Data Center Offer
- Data Center Site Selection for Corporate Real Estate Teams
- A Data Center Is Proposed Near You: What to Know and What to Ask
