Key takeaways
- Data center loads are large and steady and often ask for redundant service; they used 4.4% of U.S. electricity in 2023 and could reach 6.7–12% by 2028.4
- Ask for a phased ramp schedule and ride-through data, not just a final megawatt number; NERC’s May 2026 Level 3 alert made sudden load loss a formal reliability concern.3
- Gauge maturity through site control, approvals and money at risk. Texas now requires $50,000 per MW of security from ERCOT loads of 75 MW or more before studies begin.5
- Minimum bills, long terms, collateral and exit terms protect existing customers from stranded investment.6
- Co-ops should bring in their wholesale supplier, and the regional grid operator where there is one, before choosing how to serve the load.7
01Why data center loads differ from other large loads
A single data center campus can request more capacity than a utility’s existing industrial customers combined, and several such requests can arrive at once. Single requests to co-ops now run as high as 1,000 MW.1 The load also behaves differently from most heavy industry:
- Size: from tens of megawatts for enterprise and colocation sites to hundreds of megawatts or more for hyperscale and AI campuses.
- Load factor: data centers tend to run near their demand level around the clock, with little seasonal or daily swing.
- Ramp: the load usually arrives in phases over several years, not on a single energization date.
- Redundancy: many request two independent feeds, sometimes from separate substations.
- Speed: developers often want service sooner than normal planning and construction cycles allow.
- Uncertainty: the same project may be shopped to several utilities at once, and some requests never proceed.
Fig. 1Data center load in context
- of U.S. electricity, 2023
- 4.4%
- projected U.S. share by 2028
- 6.7–12%
- peak demand at many G&T co-ops
- 1,000–2,000 MW
- single prospective data center loads
- 500–1,000 MW
Large loads can also behave in ways system operators now study closely. Many data centers protect their equipment by disconnecting from the grid and shifting to backup power during a voltage disturbance, so one fault can remove a large block of load within seconds; NERC’s May 2026 Level 3 alert, only the third in its history, followed a series of such incidents since 2022 involving 1,000 MW or more.3 In July 2024, about 60 Northern Virginia data centers, roughly 1,500 MW, dropped off the grid at once.8 In July 2026 FERC directed NERC to file reliability standards for computational loads by the end of the year.9 Our guide to NERC reliability and large loads covers what that means for studies and commissioning.
02Questions to ask a large-load requester
A consistent intake form helps staff compare requests and decide which to study first. The table lists questions many utilities ask and why each matters. Exact requirements vary by utility, state rules and tariff.
| Question | Why it matters |
|---|---|
| Peak demand at full build-out, and by phase | Sets the system study scope and upgrade sequence |
| Ramp schedule with target energization dates | Determines when facilities are needed and how to stage them |
| Expected load factor and operating profile | Affects resource planning and energy supply |
| Redundancy request: single, dual feed, separate substations | Changes the scope and cost of interconnection |
| Ride-through settings and backup transfer behavior | Shows how the load will respond to faults, now a reliability focus3 |
| Site location, acreage and site control status | Shows whether the request is tied to real land |
| Zoning and permitting status | Indicates whether the project can be built where proposed |
| Requests for the same project made elsewhere | Flags duplicates; Texas’s SB 6 calls for this disclosure10 |
| On-site generation or storage plans | Affects protection, interconnection and how much grid service is needed |
| Willingness to fund studies and post collateral | Signals commitment and protects other customers |
A phased ramp is especially important. A request for 300 MW on one date is harder to plan for and less realistic than a schedule of blocks over several years. Our guide on load ramp schedules explains how developers build them.
03Judging project maturity
Not every request represents a project that will be built. Developers often study several sites to keep options open, which fills study queues with duplicates and inflates forecasts. Grid Strategies found that utilities’ five-year forecasts of peak load growth rose from 24 GW to 166 GW in about three years, and that the roughly 90 GW of data center growth utilities expect by 2030 runs about 25 GW above market analysts’ estimates.11 Indicators of a more mature request include:
- Site control through ownership, a purchase contract or an option with a meaningful term.
- A zoning approval, or an application filed in a jurisdiction that allows the use.
- Engineering detail on the substation location and the campus layout.
- Financial commitment: study deposits, engineering payments or collateral.
- A credible end user or a sponsor with a record of completing similar projects.
Many utilities and regulators now tie study priority or capacity to milestones like these. Texas’s Senate Bill 6 calls for proof of site control, study fees and disclosure of substantially similar requests elsewhere in the state,10 and the rule the Public Utility Commission adopted on September 18, 2026 requires ERCOT loads of 75 MW or more to post $50,000 per MW of security before interconnection studies begin.5 NRECA’s guidance to co-ops makes a simpler version of the point: asking a prospect to pay for something like an engineering study is one way to gauge seriousness.7 See Texas Senate Bill 6 and the large-load interconnection process.
04System studies and upgrades
Serving a large load usually requires some combination of new or expanded substations, new transmission lines or reinforcements, and sometimes upgrades on neighboring systems; a utility load study identifies them. Larger loads generally connect at higher transmission voltages, which raises both the cost and the reach of the study, and many ask for redundant utility feeds. Supply matters too: the utility or its wholesale supplier needs enough generation or market purchases to serve a high load factor around the clock.
In organized markets, the regional transmission organization’s processes may apply in addition to the utility’s own, and those processes are changing. After the Department of Energy asked FERC in October 2025 to take up rules for connecting loads larger than 20 MW to the transmission system,12 FERC chose region-by-region reform. On June 18, 2026 it ordered all six RTOs and ISOs to justify or revise their rules for large loads and co-location, covering study timing, network upgrade costs and behind-the-meter arrangements, while leaving retail service and siting with the states.213 See ISO and RTO markets for how market structure affects this.
Fig. 2Who sets the terms for a large load
- 01FERC and NERCTransmission service rules; reliability standards in development.
- 02RTO or ISORegional large-load, co-location and study procedures.
- 03State commissionRetail rates, cost allocation and service territory.
- 04Utility tariffLarge-load rate schedule, study fees and collateral rules.
- 05Service agreementOne customer’s demand, ramp, minimum bill and exit terms.
Cost allocation is the policy question at the center of it. Who pays for upgrades, how costs are recovered if the load does not materialize, and how other customers are protected all vary by state and utility. Transmission upgrades and cost allocation explains the common approaches.
05Service terms and protecting other customers
Commercial terms carry much of the risk management. Large-load tariffs and electric service agreements commonly address contract length, minimum demand charges, collateral or credit support, ramp commitments, exit fees and what happens if the customer reduces or cancels its load. A 2026 Lawrence Berkeley National Laboratory review of 55 large-load tariffs from 47 utilities found that minimum contract terms, minimum billing demand and collateral are now well established while exit fees are emerging, and that the median minimum term for tariffs proposed since 2025 has reached 12 years, up from five.6 RMI’s review of 65 state-level tariffs treats collateral, minimum terms and exit fees as the core safeguards against costs stranded by a load that never arrives or leaves early.14
Fig. 3When large-load protections apply
Before studies
- Proof of site control
- Study fees paid up front
- Disclosure of duplicate requests
- Security per MW in some states
Before construction
- Signed electric service agreement
- Collateral or parent credit support
- Payment for dedicated facilities
- Ramp schedule tied to contract demand
During service
- Minimum bill on contracted demand
- Minimum terms often 12 years or more
- Exit or early termination fees
- Ride-through and operating requirements
On-site generation and storage add options and questions. Some projects propose bridge generation until the grid can serve them, partial self-supply, or co-location with an existing plant. Each affects interconnection, protection and wholesale arrangements, and FERC’s 2026 orders asked the regional operators to address co-located and behind-the-meter loads directly.2 See behind-the-meter vs. front-of-the-meter and large-load tariffs and electric service agreements.
06Considerations for cooperatives and municipal utilities
Distribution cooperatives and municipal utilities often face these requests with smaller staffs and different structures, and co-ops often serve the rural land that large campuses want.15 Many co-ops buy wholesale power and transmission service from a generation and transmission cooperative or other supplier, so a large load needs early coordination with that supplier and with the transmission owner. NRECA’s guidance recommends contacting wholesale suppliers and regional transmission operators early, bringing the supplier in before choosing how to serve the load, educating the board on risks and benefits, and lining up legal and financial advisers before negotiating.7
The goal is to keep one project’s costs with that project. Kentucky’s electric cooperatives describe using rate schedules, contract terms, upfront payments, dedicated facilities and collateral so that costs tied to a data center stay with it, which matters most if the project is delayed, shrinks or closes before its contract ends.16 Membership rules, board approval and the effect on other members’ rates are often central questions.
Service territory also matters. Developers sometimes discover that a site straddles service areas or lies near a boundary, which can raise questions about which entity serves the load. Annexation and utility service areas covers these issues. Coordinating with state and local economic development staff, described in our economic development guide, helps align site readiness work with what the system can actually serve.
07Common mistakes in handling large-load requests
- Accepting a single final megawatt number without a phased ramp schedule.
- Studying every request in arrival order, regardless of site control or project maturity.
- Planning resources as if every queued request were firm, when duplicate and speculative requests inflate forecasts.
- Giving informal capacity signals that a developer then treats as a commitment.
- Leaving cost allocation and collateral terms until after upgrades are designed.
- Overlooking the wholesale supply side: a high load factor needs energy around the clock, not only connection capacity.
- Leaving ride-through and protection settings out of the study, even though sudden load loss is now a recognized reliability risk.
- Not coordinating with neighboring utilities or the transmission owner when the load affects their systems.
- Treating on-site generation proposals as a distribution matter when they raise protection and wholesale questions.
Most of these come down to the same principle: be clear early about what the utility needs from a requester and what it can and cannot say before a study. Developers and site selectors plan around those answers, so clear, consistent ones help everyone.
Common questions
How do utilities evaluate a large data center load request?
Most start with an intake review of the requested demand, ramp schedule, location, redundancy needs and project status, then study the transmission and distribution system to identify needed upgrades and their costs and schedules. Commercial terms such as contract length, minimum charges and collateral follow. Processes vary by utility and state, and in organized markets regional procedures may also apply; those are under FERC review in 2026.2
Why do data centers request two utility feeds?
Data centers aim to stay online through equipment failures and maintenance. Two independent feeds, ideally from separate substations or transmission paths, reduce the chance that a single outage interrupts the facility. On-site backup generation provides another layer. Redundant service adds interconnection scope and cost, so utilities and developers usually discuss what level of independence is practical at a given site.
How can a utility tell whether a data center request is speculative?
Look for site control, zoning progress, a phased ramp schedule, engineering detail and money at risk, such as study fees, deposits or collateral. A request with all of these is far likelier to proceed. Texas now makes several of these tests mandatory for large ERCOT loads, including security of $50,000 per MW before studies.5
What is a load factor and why does it matter for data centers?
Load factor compares a customer’s average demand with its peak demand over a period. Data centers typically run at a high, steady load factor, which affects how much energy the utility or its supplier must provide, how resources are planned and how the customer’s rates are structured. The assumption still deserves checking for each project: Grid Strategies has questioned how intensively some forecasts assume new large customers will run.11
What do NERC and FERC require of large data center loads?
As of October 2026, NERC has no mandatory standard aimed specifically at data center loads, but one is coming. NERC’s May 2026 Level 3 alert asks registered entities to evaluate and report on how they model, study, protect and communicate about large loads, and FERC’s July 16, 2026 order directs NERC to file reliability standards and registration criteria for computational loads by December 31, 2026.39 Grid operators and utilities can set their own ride-through and commissioning requirements in the meantime, so expect them in studies and service agreements.
Notes
- 1.National Rural Electric Cooperative Association, “Comments of NRECA on DOE Speed to Power Request for Information,” 2025. electric.coop
- 2.Foley & Lardner, “FERC Issues Six Tailored “Show Cause” Orders to Accelerate Large Load Interconnection,” 2026. foley.com
- 3.Davis Wright Tremaine, “NERC Signals Rare Level 3 Alert on Large Loads and Data Centers,” 2026. dwt.com
- 4.Lawrence Berkeley National Laboratory, “2024 United States Data Center Energy Usage Report,” 2024. eta-publications.lbl.gov
- 5.White & Case, “PUCT sets financial commitments for data center interconnection as governor pauses permit approvals,” 2026. whitecase.com
- 6.Lawrence Berkeley National Laboratory, “Electricity Rate Designs for Large Loads: Evolving Practices and Opportunities 2026 Update,” 2026. emp.lbl.gov
- 7.National Rural Electric Cooperative Association, “New NRECA Report Explores Cost Recovery Strategies for Serving Data Centers,” n.d. cooperative.com
- 8.Data Center Dynamics, “Virginia narrowly avoided power cuts when 60 data centers dropped off the grid at once,” 2025. datacenterdynamics.com
- 9.Willkie Farr & Gallagher, “FERC Orders New Reliability Standards for Data Centers and Other Computational Loads,” 2026. willkie.com
- 10.Bracewell, “Texas Senate Bill 6 Ushers in Major Overhaul of Large Load Interconnection and Grid Access Rules,” 2025. bracewell.com
- 11.Grid Strategies, “National Load Growth Report 2025,” 2025. gridstrategiesllc.com
- 12.Beveridge & Diamond, “DOE Invokes Rare Authority to Direct FERC to Accelerate Grid Access for Large Loads and Data Centers,” 2025. bdlaw.com
- 13.Orrick, “FERC Show Cause Orders Signal Broad Reform to Large Load Interconnection Policies,” 2026. orrick.com
- 14.RMI, “Large Energy Users Want Power. Here’s How to Protect Other Ratepayers From the Costs,” n.d. rmi.org
- 15.National Rural Electric Cooperative Association, “NRECA Urges ‘Whole-of-Government Approach’ to Help Co-ops Serve Large Loads,” 2025. electric.coop
- 16.Kentucky Electric Cooperatives, “Data Centers in Kentucky: The Cooperative Approach,” 2026. kyelectric.coop
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Guides by role
- A Landowner’s Path: From First Question to Signed Deal
- Site Selection for Data Center Developers: What to Answer, in Order
- Site Risk for Data Center Investors and Lenders
- Representing Land for Data Center Use: A Broker’s Guide
- Attracting Data Centers: A Guide for Economic Development Organizations
- Data Centers: A Guide for County Officials and Planners
- Data Center Interest in Farm and Ranch Land: A Guide for Farmers
- Family Land, Estates and Trusts: How to Handle a Data Center Offer
- Pairing Power Projects With Data Centers: A Guide for Energy Developers
- Data Center Site Selection for Corporate Real Estate Teams
- A Data Center Is Proposed Near You: What to Know and What to Ask
Guide 6 of 12 in Guides by role · all 242 guides · glossary · calculators
