Key takeaways
- Lead with power. Many developers now rank speed to power above land and price, so promote only sites with a credible utility path.1
- Know what the serving utilities will ask of a large load; long minimum-bill contracts, collateral and study fees are now common.34
- Publish clear standards before the first application. Northern Virginia counties have added setbacks, noise studies and public hearings for data centers.56
- Describe benefits precisely: most of the industry’s job count is construction, and a 250,000-square-foot building may employ about 50 people.78
- Expect scrutiny of incentives and secrecy. Georgia, Virginia and Texas each forgo $1 billion or more a year in data center tax breaks, and officials’ NDAs are drawing legislative attention.910
01What developers ask economic development organizations
Data center site searches are usually confidential and fast. A site selector may contact a state or regional organization with a short brief: a megawatt load, an acreage range, a schedule and a few requirements on fiber or water. The organizations that stay in the search are the ones that can answer quickly with accurate information.
The order of the questions has changed. Kroll’s advisers describe the old sequence of land, then incentives, then utilities giving way to one in which electricity, water and permitting risk decide where large projects go,11 and JLL warns that land without committed power can end up stranded.1 Expect questions like these, roughly in this order:
- Which sites can support the load, from which substations, and on what timeline?
- How much buildable acreage does each site have, and who owns it?
- Is the use allowed under current zoning, and what is the approval process?
- What fiber, water and sewer service is available?
- What incentives apply, and what are their conditions?
- How has the community responded to similar projects?
Fig. 1How a confidential site search narrows
- 01
Brief
Load in MW, acreage, schedule, fiber and water needs.
- 02
Long list
Desktop screen of power, land and zoning.
- 03
Short list
Site visits and utility calls, often under NDA.
- 04
Diligence
Load studies, surveys, zoning and incentive terms.
- 05
Decision
One site moves to agreements; the rest drop out.
- 06
Announcement
End user, approvals and incentives become public.
The site selection criteria guide shows how developers weigh these factors, and confidentiality, NDAs and code names explains how those agreements usually work.
02Build a site inventory that matches data center needs
Most industrial parks were planned for manufacturing or logistics. They may have good roads and water but not the transmission access or contiguous acreage a data center needs. Screening an inventory against data center criteria shows which sites are worth promoting and which are not.
A useful inventory records, for each site: buildable acreage, distance to transmission and the voltage, nearest substations, serving utility, zoning, ownership and willingness to sell, fiber routes, and water and sewer providers. Our guide to screening a land portfolio describes how to do this at scale, and gross vs. buildable acreage explains why stated acreage often overstates capacity.
Fig. 2Sample screen of one industrial park site
Illustrative- PassTransmission access230 kV line about one mile from the park boundary.
- WatchSubstation headroomUtility has not confirmed capacity; a load study is needed.
- WatchBuildable acreage180 gross acres; about 120 after floodplain and easements.
- WatchZoningIndustrial district, but data centers are not a listed use.
- PassFiberTwo providers along the frontage road.
- PassWater and sewerMunicipal service with a capacity letter on file.
Certification programs help only when their criteria reflect data center needs, such as transmission access, large contiguous acreage and a documented utility conversation. Certified sites and shovel-ready programs explains what those programs verify.
03Readiness work that changes outcomes
Some preparation makes a site meaningfully more competitive. The table below lists common steps, why they matter and who usually leads them. The lead varies by state and by how the organization is structured.
| Readiness step | Why it matters to developers | Usually led by |
|---|---|---|
| Utility capacity screening for priority sites | Power decides most searches; early signals save weeks | Economic development with the serving utility |
| Zoning or text amendment that defines data centers | Reduces approval uncertainty and hearing risk | Local planning staff and elected officials |
| Boundary survey, title review and owner commitment | Shows the land can actually be secured | Landowner, with economic development support |
| Phase I ESA and wetland review | Removes common early diligence questions | Landowner or economic development |
| Water, sewer and fiber documentation | Answers infrastructure questions quickly | Utilities and service providers |
| Incentive framework published in advance | Lets developers model costs without negotiation | State and local governments |
The power step deserves the most attention. Utilities increasingly require large-load customers to fund studies, post collateral and sign long contracts with minimum bills: a 2026 Lawrence Berkeley National Laboratory review of 55 large-load tariffs from 47 utilities found that minimum contract terms, minimum billing demand and collateral are now well established.3 Our guide for utilities explains what utilities need before they can give meaningful answers.
04Work with utilities before a prospect calls
The single most useful thing an economic development organization can bring to a data center search is a reliable read on power. That requires a working relationship with the utilities that serve its sites, built before any specific prospect appears.
- Know which utility serves each priority site, and where service territory boundaries fall.
- Understand, at least generally, which substations and transmission lines near those sites have room and which are constrained.
- Learn how each utility handles large-load requests: who to call, what information it needs, what studies cost and how long a preliminary answer usually takes.
- Share the site inventory with the utility, so its planners can flag sites that cannot be served soon.
- Agree on how confidential prospect information will be handled between the organizations.
Expect the utility’s answers to come with conditions. In Texas, rules the Public Utility Commission adopted on September 18, 2026 require loads of 75 MW or more in ERCOT to post $50,000 per MW of financial security before interconnection studies begin.4 Requirements like these screen out speculative requests, but they also mean serious prospects will ask early what a site’s utility will require and how long it will take.
Utilities cannot promise capacity without a study, but many can say which areas are more or less constrained. That alone helps an organization stop promoting sites that will not survive a developer’s first call to the utility.
05Zoning, permitting and local policy
Many local codes do not mention data centers. That leaves developers to fit the use into another category or seek a special use permit, which adds uncertainty for everyone. Clear standards for setbacks, noise, generators, lighting and screening can make approvals more predictable and give residents a clearer picture of what to expect. See data center zoning ordinances and overlay districts for examples.
Northern Virginia shows where standards are heading. Fairfax County’s 2024 amendments require data center buildings to sit at least 200 feet from residential lot lines, keep generators and other ground-level equipment generally 300 feet away, and call for a noise study before site plan approval.5 In 2025 Loudoun County removed data centers as a by-right use in the districts where they had been allowed, so new projects need a special exception with public hearings,6 and on September 22, 2026 Prince William County adopted an overhaul that shrinks its data center overlay district and requires a special use permit for most future projects.12 A community earlier in the cycle can set standards before the first application rather than after the first fight.
Some communities respond to fast growth with pauses or new restrictions. Data Center Watch counted at least 75 projects worth about $130 billion blocked or delayed by local opposition in the first quarter of 2026, a record for its tracker.13 Developers screen for this, so economic development staff should know where local policy stands. Moratoriums and local restrictions explains what they look for.
06Incentives: what they do and what they cost
Incentives can influence a decision between otherwise comparable sites, but they rarely overcome a power or land problem. Common forms include sales and use tax exemptions on equipment and property tax abatements, with structures that vary by state and locality. Data center tax incentives covers how they work and what conditions usually attach.
They are also costly and increasingly scrutinized. Good Jobs First estimates that Georgia, Virginia and Texas each forgo $1 billion or more a year to data center tax breaks, and it found 14 states that do not report their losses at all.9 Virginia’s sales and use tax exemption requires at least $150 million of investment and 50 jobs paying 150% of the local average wage (fewer jobs in distressed localities), and over fiscal 2014–2023 it returned about 48 cents in new state revenue for each dollar forgone, compared with about 17 cents for comparable exemptions, according to the state’s legislative auditors.7 That is a better return than most incentives earn, but it does not recover the full cost in state revenue.
Local revenue often matters more than state policy. In five mature Virginia localities, data centers accounted for anywhere from under 1% to 31% of total local revenue, mostly from business personal property tax on equipment and real estate tax, and several jurisdictions had cut equipment tax rates to compete.7 Whatever the package, write performance terms into it: investment and job thresholds, recapture if they are not met, and public reporting.
07Set realistic expectations with the community
Be candid about benefits and impacts. Data centers can add significant tax base and bring large construction workforces for a period, but permanent employment is modest compared with the size of the investment. Virginia’s auditors estimated that the industry supports about 74,000 jobs a year in the state, roughly 59,000 of them tied to construction, and data center representatives told the auditors that a typical 250,000-square-foot building may have about 50 full-time workers, about half of them contractors, after a construction peak of around 1,500 people on site.7 The economic impact of data centers goes deeper.
Fig. 3Virginia’s data center ledger
- jobs a year, mostly in construction
- ~74,000
- full-time staff, 250,000 sq ft building
- ~50
- new state revenue per $1 of exemption
- 48¢
- of local revenue, five mature localities
- <1–31%
Public support can no longer be assumed. In a March 2026 Gallup poll, 71% of U.S. adults opposed an AI data center being built in their area, with opposition across party lines, and opponents most often pointed to strain on resources such as electricity and water.2 In Loudoun County, residents have also complained about noise and fumes from data center backup generators.14
Residents also ask whether a large new load will raise their electric bills or strain local water supplies. Virginia’s auditors found that data centers were paying their full cost of service under the rates then in effect, but warned that rapid growth could shift costs to other customers and estimated that the average Dominion residential bill could rise by roughly $14 to $37 a month by 2040.7 Regulators have since approved new Dominion rates that assign more costs to data centers.15 Staff do not need to answer these questions alone, but they should bring the people who can to early public meetings: the utility for rates, the water provider for supply and the developer for its cooling design. That builds more trust than general reassurance. See community engagement for data centers.
08Common mistakes
- Promoting sites as data center ready without a utility capacity conversation.
- Listing gross acreage and ignoring floodplain, wetlands and easements.
- Presenting total or construction job counts as if they were permanent jobs.
- Assuming incentives can make up for a slow power timeline.
- Offering incentives without performance terms, recapture provisions or public reporting.9
- Leaving zoning standards undefined until a specific project files.
- Sharing prospect details too widely, or signing broad NDAs without planning for what becomes public, and when.
Most of these come from moving faster than the facts. A short desk review of priority sites, done with the serving utility and planning staff, avoids most of them and makes the organization a more credible partner when a real prospect calls. For an outside view of a site or portfolio, you can get a site reviewed.
Common questions
What makes a community attractive for data centers?
Mostly power: transmission access and a utility that can serve a large load on a workable timeline. After that, developers look for large, flat, buildable sites, a clear zoning path, fiber connectivity, water where the cooling design needs it, and a stable local policy environment. Incentives help between comparable options, but advisers to large developers now treat them as secondary to power, water and permitting risk.11
How many jobs does a data center create?
Far fewer permanent jobs than its cost suggests, and many more during construction. In Virginia, industry representatives told state auditors that a typical 250,000-square-foot building may have about 50 full-time workers once it operates, about half of them contractors, after a construction peak of around 1,500 people on site.7 The lasting benefit is usually tax base rather than payroll, so present both effects using figures from the specific project.
How can an economic development organization get sites ready for data centers?
Start by screening sites against data center criteria and working with serving utilities to understand capacity near the best ones, including what studies, fees and collateral they will require.3 Then document buildable acreage, ownership, title, environmental conditions and infrastructure. Clarifying zoning standards for data centers and publishing incentive terms in advance also help.
Why are data center site searches so confidential?
End users compete for sites and power, and early disclosure can raise land prices, invite competing interest or draw public attention before plans are settled. Site selectors often use code names and nondisclosure agreements, which have become common in these talks; at least four Wisconsin local governments signed such agreements, and lawmakers in several states have proposed limits.1610 Protect prospect details, but agree at the outset what will become public and when.
Notes
- 1.Data Center Frontier, “JLL’s 2026 Global Data Center Outlook: Navigating the AI Supercycle, Power Scarcity and Structural Market Transformation,” 2026. datacenterfrontier.com
- 2.FOX 5 DC, “Not in my backyard: Most Americans oppose AI data centers, Gallup finds,” 2026. fox5dc.com
- 3.Lawrence Berkeley National Laboratory, “Electricity Rate Designs for Large Loads: Evolving Practices and Opportunities 2026 Update,” 2026. emp.lbl.gov
- 4.White & Case, “PUCT sets financial commitments for data center interconnection as governor pauses permit approvals,” 2026. whitecase.com
- 5.Holland & Knight, “Fairfax County, Virginia, Approves Updated Zoning Regulations Related to Data Centers,” 2024. hklaw.com
- 6.Holland & Knight, “Loudoun County, Virginia, Eliminates By-Right Data Center Development,” 2025. hklaw.com
- 7.Joint Legislative Audit and Review Commission (Virginia), “Data Centers in Virginia,” 2024. jlarc.virginia.gov
- 8.George Mason University, “STEP Brief 05: Data Centers,” 2026. care.gmu.edu
- 9.Stateline, “Many states don’t report losses from data center tax breaks, study says,” 2026. stateline.org
- 10.NPR, “Tech companies and local officials are covering data center talks in NDAs,” 2026. npr.org
- 11.Kroll, “BYOP & Site Selection: Powering Hyperscale Data-Center Growth,” 2026. kroll.com
- 12.Venable LLP, “The Window for By-Right Data Center Development in Prince William County Is Closing Quickly, and More Changes Are Proposed,” 2026. venable.com
- 13.Data Center Watch, “Q1 2026: Data Center Watch Report,” 2026. datacenterwatch.org
- 14.WJLA (7News), “Data center noise, fumes create flood of complaints in Loudoun County,” n.d. wjla.com
- 15.Inside Climate News, “Virginia Regulators Approve New Dominion Rates, Assign More Costs to Data Centers,” 2026. insideclimatenews.org
- 16.Wisconsin Watch, via PBS Wisconsin, “At least four local governments in Wisconsin signed data center secrecy deals,” 2026. pbswisconsin.org
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Guides by role
- A Landowner’s Path: From First Question to Signed Deal
- Site Selection for Data Center Developers: What to Answer, in Order
- Site Risk for Data Center Investors and Lenders
- Representing Land for Data Center Use: A Broker’s Guide
- Large Data Center Loads: What Utilities and Co-ops Look For
- Data Center Interest in Farm and Ranch Land: A Guide for Farmers
- Family Land, Estates and Trusts: How to Handle a Data Center Offer
- Pairing Power Projects With Data Centers: A Guide for Energy Developers
- Data Center Site Selection for Corporate Real Estate Teams
- A Data Center Is Proposed Near You: What to Know and What to Ask
Guide 5 of 12 in Guides by role · all 242 guides · glossary · calculators