Minnesota Data Center Power Rules: Large-Load Tariffs and State Law

How Minnesota’s utilities and lawmakers handle data-center-sized power requests: 1 utility and 1 state measure, compiled from public filings, with a source on every entry.

Last checked October 22, 2026All states

Utilities

Minnesota utilities and their large-load rules.

  • Xcel Energy (Northern States Power Co.-Minnesota)

    MN · MISO · Xcel Energy

    ApprovedMay 2026

    Large Load Tariff

    Minnesota regulators approved Xcel's large load tariff with 15-year contracts, an exit charge and a separate customer class for very large users.

    • 15-year minimum contract
    • Exit charge equal to 80% of demand charges
    • Separate rate class for large customers
    • Incremental Cost Test to show other customers are not charged more

    Source: Fresh Energy, Regulatory Update: Commission approves Xcel Energy's large load tariff (2026)

State law and regulation

Minnesota laws and rulemakings.

What this can and can’t tell you

The rules are public. Whether your site can get power isn’t.

Anyone could pull these filings; we compile them so they’re easy to find. Terms change often, so confirm them with the utility or the commission docket before relying on them.

Going deeper: Data Center Site Selection in Minnesota

This tracker · Public, free

  • A utility’s published rules for large new loads
  • The same answer for every site in that utility’s territory
  • What the terms are if power is available
  • Compiled from filings anyone can read

A BlackForge report · Site-specific

  • Whether a specific parcel can actually be served, and roughly when
  • Substation headroom and the realistic connection path
  • Gas, water, fiber, buildable land and zoning, checked together
  • Built and refreshed for your load, your timeline and your parcels

Cite this tracker

BlackForge Data Centers. "Minnesota data center power rules," Large-Load Power Tracker. Last checked October 22, 2026. https://www.blackforgedatacenters.com/data-center-power-tracker/minnesota

Free to reuse under CC BY 4.0 with credit.

Need the answer for a specific site in Minnesota?

Parcel-level screening and verification, built for your load and timeline.