Alabama Data Center Power Rules: Large-Load Tariffs and State Law

How Alabama’s utilities and lawmakers handle data-center-sized power requests: 2 utilities and 1 state measure, compiled from public filings, with a source on every entry.

Last checked October 22, 2026All states

Utilities

Alabama utilities and their large-load rules.

State law and regulation

Alabama laws and rulemakings.

  • enacted · 2026-10

    Act 2026-610

    Sends Alabama Power contracts with data centers of 150 MW or more to PSC review to confirm prices recover the cost of serving them; effective October 1, 2026.

    NBC 15 (2026); ABC 33/40 (2026)

What this can and can’t tell you

The rules are public. Whether your site can get power isn’t.

Anyone could pull these filings; we compile them so they’re easy to find. Terms change often, so confirm them with the utility or the commission docket before relying on them.

Going deeper: Data Center Site Selection in Alabama

This tracker · Public, free

  • A utility’s published rules for large new loads
  • The same answer for every site in that utility’s territory
  • What the terms are if power is available
  • Compiled from filings anyone can read

A BlackForge report · Site-specific

  • Whether a specific parcel can actually be served, and roughly when
  • Substation headroom and the realistic connection path
  • Gas, water, fiber, buildable land and zoning, checked together
  • Built and refreshed for your load, your timeline and your parcels

Cite this tracker

BlackForge Data Centers. "Alabama data center power rules," Large-Load Power Tracker. Last checked October 22, 2026. https://www.blackforgedatacenters.com/data-center-power-tracker/alabama

Free to reuse under CC BY 4.0 with credit.