Oregon Data Center Power Rules: Large-Load Tariffs and State Law
How Oregon’s utilities and lawmakers handle data-center-sized power requests: 3 utilities and 1 state measure, compiled from public filings, with a source on every entry.
Last checked October 22, 2026All states
Utilities
Oregon utilities and their large-load rules.
Idaho Power
ID, OR · Non-RTO West · IDACORP
ApprovedMay 2023Special contracts for customers above 20 MW; Schedule 20 for speculative high-density loads
Idaho Power serves every customer above 20 MW under its own state-approved contract, as with Meta's Kuna data center in 2023.
- Applies to: Above 20 MW
- No standard large-load tariff: each customer above 20 MW needs its own contract approved by the Idaho PUC
- Contract ties the customer to its ramp schedule
- Separate Schedule 20 class for speculative, relocatable loads such as crypto mining
Sources: Idaho Public Utilities Commission, Final Order No. 35777, Case IPC-E-21-42 (2023); Idaho Public Utilities Commission, Final Order No. 35461, Case IPC-E-21-37 (2022); KIVI-TV, Idaho lawmaker aims to shield customers from rising power rates tied to data centers (2026)
Pacific Power (PacifiCorp, Oregon)
OR · Non-RTO West · PacifiCorp (Berkshire Hathaway Energy)
Settlement filedSep 2026POWER Act data center tariff (Oregon PUC docket UE 463)
Pacific Power reached a settlement that would charge new Oregon data centers the full cost of the new supply and grid built for them.
- Applies to: Over 20 MW (POWER Act definition)
- Costs of new energy projects and infrastructure needed for data centers assigned directly to data center operators
- Separate customer class with contracts of 10 years or longer under the POWER Act
Sources: Washington State Standard (Oregon Capital Chronicle), Pacific Power to charge new Oregon data centers for all costs associated with growing energy need (2026); Oregon Public Utility Commission, 2026 POWER Act Legislative Report (2026)
Portland General Electric
OR · Non-RTO West
ApprovedMay 2026Schedule 96 (POWER Act large energy use facilities)
Oregon approved a separate PGE rate class for loads above 20 MW, with long contracts, minimum demand charges and customer-paid upgrades.
- Applies to: Above 20 MW
- Contracts of at least 10 years, up to 30 years for the largest loads
- Pays generation and transmission demand charges on at least 90% of contracted capacity
- Customer pays 100% of distribution upgrades
- 1 cent per kWh surcharge at 100 MW or more
- Exit fees and a separate interconnection queue for data centers
Sources: Oregon Public Utility Commission, Order No. 26-154 (UM 2377) (2026); Clearing Up (NewsData), Oregon Regulators Approve PGE Data Center Rate Framework (2026); Office of the Governor of Oregon, Governor Kotek Applauds PUC for Rate Increase on Data Centers (2026)
State law and regulation
Oregon laws and rulemakings.
enacted · 2025-06
POWER Act, House Bill 3546 (2025)
Requires a separate rate class for facilities of 20 MW or more, with contracts of at least 10 years and minimum payments regardless of use.
Data Center Dynamics (2025); Oregon Public Utility Commission (2026)
What this can and can’t tell you
The rules are public. Whether your site can get power isn’t.
Anyone could pull these filings; we compile them so they’re easy to find. Terms change often, so confirm them with the utility or the commission docket before relying on them.
Going deeper: Data Center Site Selection in Oregon
This tracker · Public, free
- A utility’s published rules for large new loads
- The same answer for every site in that utility’s territory
- What the terms are if power is available
- Compiled from filings anyone can read
A BlackForge report · Site-specific
- Whether a specific parcel can actually be served, and roughly when
- Substation headroom and the realistic connection path
- Gas, water, fiber, buildable land and zoning, checked together
- Built and refreshed for your load, your timeline and your parcels
Cite this tracker
BlackForge Data Centers. "Oregon data center power rules," Large-Load Power Tracker. Last checked October 22, 2026. https://www.blackforgedatacenters.com/data-center-power-tracker/oregon
Free to reuse under CC BY 4.0 with credit.
Need the answer for a specific site in Oregon?
Parcel-level screening and verification, built for your load and timeline.